1 KEK test-beam software progress Malcolm Ellis MICE Video Conference 4 th May 2005.

Slides:



Advertisements
Similar presentations
Kondo GNANVO Florida Institute of Technology, Melbourne FL.
Advertisements

SciFi Tracker DAQ M. Yoshida (Osaka Univ.) MICE meeting at LBNL 10.Feb.2005 DAQ system for KEK test beam Hardware Software Processes Architecture SciFi.
1 Simulation Status/Plans Malcolm Ellis Sci Fi Tracker Meeting Imperial College, 10 th September 2004.
1Malcolm Ellis - Tracker Meeting - 18th May 2006 Reconstruction Plans  Staged process of building up Reconstruction over the rest of this year  Will.
Software Summary Database Data Flow G4MICE Status & Plans Detector Reconstruction 1M.Ellis - CM24 - 3rd June 2009.
KEK Test Beam Phase II Plan Makoto Yoshida (Osaka Univ.) MICE FT Daresbury 2005/8/30.
1 Scintillating Fibre Tracker Simulation Malcolm Ellis Imperial College London Tuesday 9 th March 2004.
First Results from Tracker 1  Cryostat Commissioning  AFE/VLSB Firmware and Readout  Cosmic Ray Setup  Tracker Readout  Software  Trigger Timing.
Tracker Software 1M.Ellis - CM23 - Harbin - 15th January 2009  Four key areas that currently need some work: u Digitisation u Decoding files u Unpacking.
1 Scintillating Fibre Cosmic Ray Test Results Malcolm Ellis Imperial College London Monday 29 th March 2004.
Tracker DAQ Makoto Yoshida (Osaka Univ.) MICE Frascati 2005/6/27.
1 Status of Cosmic Analysis Malcolm Ellis Imperial College London Wednesday 10 th March 2004.
Status of the MICE SciFi Simulation Edward McKigney Imperial College London.
1 VLPC system and Cosmic Ray test results M. Ellis Daresbury Tracker Meeting 30 th August 2005.
SciFi Tracker DAQ M. Yoshida (Osaka Univ.) MICE Tracker KEK Mar. 30, 2005.
Prototype Performance in D0 test stand M.Yoshida (Osaka Univ.)
KEK Analysis Report Makoto Yoshida Osaka Univ. 2006/06/10 MICE CM15.
1Malcolm Ellis - Video Conference - 7th December 2006 Data Challenge Report  Disclaimer  Data Challenge definition(s)  Software status u G4MICE u GRID.
Sci Fi Simulation Status Malcolm Ellis MICE Meeting Osaka, 2 nd August 2004.
1 Online data quality and monitoring M. Ellis Daresbury DAQ Meeting 31 st August 2005.
Detector Systems Update MICO May 19, MICE Detector Systems  Beam Monitors u Over heating of sender boards has been s Solution.
2005/10/22 MICE CM at RAL, Tracker Parallel, Makoto Yoshida 1 KEK test beam - introduction - M. Yoshida MICE CM tracker parallel 2005/10/ /10/22.
Linda R. Coney – 24th April 2009 Online Reconstruction & a little about Online Monitoring Linda R. Coney 18 August, 2009.
1 Analysis code for KEK Test-Beam M. Ellis Daresbury Tracker Meeting 30 th August 2005.
Prototype Performance in D0 test stand & fiber intrinsic performance with KEK test beam M.Yoshida (Osaka Univ.) Osaka.
1Malcolm Ellis - Software Meeting - 17th May 2006 MICE Model and MICERun  MiceModel: u Overall Model that is used throughout G4MICE to represent any stage.
DAQ for KEK beam test M.Yoshida (Osaka Univ.). Components VLPC readout –Stand Alone Sequencer (SASeq) Slow < 100Hz –Buffering VLPC data with VME interface.
1 G4MICE Analysis of KEK Test Beam Aron Fish Malcolm Ellis CM15 10th June 2006.
6 th April 2005 Malcolm Ellis, Imperial College London 1 Sci Fi Status & KEK Test.
1 G4MICE Malcolm Ellis SciFi Tracker Meeting, KEK Thursday 31st March 2005.
1Malcolm Ellis - Tracker Meeting - 6th November 2006 Tracker Software  Offline u Modeling u GRID u Tests u Decoding u Kalman fit u Reconstruction & “data.
Status of the preparation for KEK test beam M. Yoshida (Osaka Univ.) MICE VC 2005/9/14.
J. Estrada - Fermilab1 AFEII in the test cryostat at DAB J. Estrada, C. Garcia, B. Hoeneisen, P. Rubinov First VLPC spectrum with the TriP chip Z measurement.
1 G4MICE TOF Reconstruction & KEK Test Beam Analysis Update Aron Fish Tracker Phone Conference May 25, 2006.
1M. Ellis - MICE Video Conference - 15th March 2007 Software Report  New G4MICE Users  TOF Simulation and Digitisation  SciFi Reconstruction  Tracker.
Tracker Summary Makoto Yoshida Osaka Univ. MICE Frascati June 28 th, 2005.
1 MICE Tracker Update M. Ellis UKNFIC Meeting 25 th August 2005.
1 G4MICE Design Iteration Malcolm Ellis MICE Video Conference 21 st April 2004.
1 Persistency – Update and Plans Malcolm Ellis Software Phone Meeting 25 th August 2005.
1 MICE Tracking Detectors Malcolm Ellis NFMCC Meeting 12 th March 2006.
Sci-Fi Tracker: Progress Report Malcolm Ellis, MICE Video Conference Wednesday 6 th October 2004.
Software Status  Last Software Workshop u Held at Fermilab just before Christmas. u Completed reconstruction testing: s MICE trackers and KEK tracker.
1 MICE Tracker Readout Update, Preparation for Cosmic Ray Tests Cosmic Ray Tests at RAL AFE-IIt Firmware Development VLSB Firmware Development Summary.
1 Software for the KEK test Malcolm Ellis 13 th April 2005.
1M. Ellis - MICE Tracker Meeting - 12th February 2007 Readout Electronics & DAQ  Introduction  DAQ Spreadsheet u VLSB_DAQ Sheet u Initialisation u Bias.
Status of cosmic-ray test of the SciFi prototype and SciFi software in G4MICE M. Yoshida (Osaka Univ.)
MICE Phase 1 Koji Yoshimura KEK June
Online Reconstruction 1M.Ellis - CM th October 2008.
DAQ Status for cosmic-ray test in RAL Hideyuki Sakamoto MICE Phone meeting 12 th July 2007 Contents Status Setup for cosmic-ray test bench Schedule.
1M. Ellis - 17th May 2007 SciFi Decoding (Everything you never wanted to know but couldn’t avoid going over and over)  VLSB Data (unpacking to AFE, MCM,
1Malcolm Ellis - Tracker Meeting - 28th November 2006 Electronics - Station Acceptance  Hardware: u 1 MICE cryostat with 1 VLPC cassette. u VME crate,
1 A first look at the KEK tracker data with G4MICE Malcolm Ellis 2 nd December 2005.
Linda R. Coney – 5 November 2009 Online Reconstruction Linda R. Coney 5 November 2009.
2005/10/24 MICE CM at RAL, KEK test beam, Makoto Yoshida 1 KEK Beam Test for MICE SciFi Tracker - KEK-PS T585 - M. Yoshida MICE 2005/10/ /10/24.
Database David Forrest. What database? DBMS: PostgreSQL. Run on dedicated Database server at RAL Need to store information on conditions of detector as.
Detector Summary Tracker. Well, as far as the tracker hardware is concerned, we are done. – Need to do the system test to make sure nothing has degraded.
1 Light Yield results from the KEK tracker test using G4MICE M. Ellis Tracker Phone Meeting 25 th January 2006.
Summary of final results from MICE note: “ MICE Scintillating Fibre Tracker Prototype - First progress report - ” M.Yoshida (Osaka Univ.) for the SciFi.
1 Software Workshop Report Malcolm Ellis MICE Video Conference Wednesday 9 th November 2005.
Software Overview 1M. Ellis - CM21 - 7th June 2008  Simulation Status  Reconstruction Status  Unpacking Library  Tracker Data Format  Real Data (DATE)
1 Tracker Software Status M. Ellis MICE Collaboration Meeting 27 th June 2005.
Station Acceptance Test. 22/02/2007 M. Takahashi 2 Lab Layout at IC.
1M. Ellis - MICE Tracker PC - 1st October 2007 Station QA Analysis (G4MICE)  Looking at the same data as Hideyuki, but using G4MICE.  Have not yet had.
MICE Tracker Software A. Dobbs CM32 9 th Feb 2012.
Online – Data Storage and Processing
Requirements for the Software Group (and agreed actions)
Tracker Specific Software
MICE Collaboration Meeting Saturday 22nd October 2005 Malcolm Ellis
Preparation for Station Acceptance Test
Tracker Software Status
Presentation transcript:

1 KEK test-beam software progress Malcolm Ellis MICE Video Conference 4 th May 2005

2 G4BeamLine

3 G4MICE – Detector Model Staging (i.e. selecting different configurations such as MICE Stage III, and including the KEK test setup) now works. Staging (i.e. selecting different configurations such as MICE Stage III, and including the KEK test setup) now works. A field map for the KEK magnet has been provided and is being integrated. A field map for the KEK magnet has been provided and is being integrated. First version of the beam defining scintillators and aerogel Cherenkov models have been commited (Amit). First version of the beam defining scintillators and aerogel Cherenkov models have been commited (Amit). TOF will be a modification of the existing TOF model (via the datacards). TOF will be a modification of the existing TOF model (via the datacards). More refined detector model for the SciFi (translations and rotations) still to be implemented. More refined detector model for the SciFi (translations and rotations) still to be implemented.

4 G4MICE - Visualisation A new domain has been added to provide a simple 3D visualisation within G4MICE. A new domain has been added to provide a simple 3D visualisation within G4MICE. A first test version has been produced that shows the key mechanical details of the KEK setup. A first test version has been produced that shows the key mechanical details of the KEK setup. Will eventually show hits, tracks, extrapolations, etc... Will eventually show hits, tracks, extrapolations, etc... Code will use the staging facilities to control detector representation, so this will also be useful for the full MICE simulation. Code will use the staging facilities to control detector representation, so this will also be useful for the full MICE simulation.

5 G4MICE - Reconstruction Separate Helix and Straight line track fit models are implemented and reconstruction code modified to allow use of either. Separate Helix and Straight line track fit models are implemented and reconstruction code modified to allow use of either. Further work and testing needed to allow use of straight line fit through BField datacard Further work and testing needed to allow use of straight line fit through BField datacard

6 G4MICE – VLPCs Code from previous cosmic test has been imported into G4MICE as start of extension to allow: Code from previous cosmic test has been imported into G4MICE as start of extension to allow: –decoding of VLPC hits from raw data (board, MCM, channel → tracker, station, plane, fibre bundle) –calibration (pedestals and gains) Code to decode raw data format will come once full DAQ is written and tested. Code to decode raw data format will come once full DAQ is written and tested.

7 G4MICE – Applications No progress so far on applications to perform Analysis and Monitoring of test-beam data. No progress so far on applications to perform Analysis and Monitoring of test-beam data.

8 DAQ – TOF/CKOV Work is ongoing in Osaka to develop the DAQ code to read out the QDCs/TDCs with the UniDAQ code. Work is ongoing in Osaka to develop the DAQ code to read out the QDCs/TDCs with the UniDAQ code. VME TDCs and QDCs have been obtained on loan (CERN loan pool and TRIUMF) for the May test. VME TDCs and QDCs have been obtained on loan (CERN loan pool and TRIUMF) for the May test.

9 AFEII readout – Excel/VB Test stand at Fermilab (Wilson Hall) is being used to develop readout through the VLSB interface. Test stand at Fermilab (Wilson Hall) is being used to develop readout through the VLSB interface. Uses existing D0 code developed as Visual Basic macros embedded in Excel spreadsheets. Uses existing D0 code developed as Visual Basic macros embedded in Excel spreadsheets. Making good progress, some work still needed to finalise readout scheme. Making good progress, some work still needed to finalise readout scheme.

10 AFEII readout – Linux/C Code already written (Makoto) to use BIT3 interface and VME to communicate with 1553 interface. Code already written (Makoto) to use BIT3 interface and VME to communicate with 1553 interface. Once Excel/VB system is working, macros will be rewritten in C to operate as part of the UniDAQ system. Once Excel/VB system is working, macros will be rewritten in C to operate as part of the UniDAQ system. Linux machine setup in D0 area ready to operate with AFE boards in cryostat. Currently being used to develop and test slow-controls for VLPCs. Linux machine setup in D0 area ready to operate with AFE boards in cryostat. Currently being used to develop and test slow-controls for VLPCs.

11 Conclusions Lot of progress made so far on all fronts (DAQ, slow controls, simulation) Lot of progress made so far on all fronts (DAQ, slow controls, simulation) Still many areas that are incomplete Still many areas that are incomplete Once individual pieces are in place, more work will be required to integrate them. Once individual pieces are in place, more work will be required to integrate them. Any potential help for the D0, UniDAQ or G4MICE experts will always be appreciated! Any potential help for the D0, UniDAQ or G4MICE experts will always be appreciated!