LIGO- G020429-00-R 40mAdvLIGO R&D program, 10/8/021 40 Meter Lab program for AdvLIGO R&D Alan Weinstein, Caltech AdvLIGO R&D Technical Review, 10/8/02.

Slides:



Advertisements
Similar presentations
LIGO-G D Comments: Staged implementation of Advanced LIGO Adv LIGO Systems 17 may02 dhs Nifty idea: a way to soften the shock, spread cost, allow.
Advertisements

G R LIGO Laboratory1 Advanced LIGO Research and Development David Shoemaker LHO LSC 11 November 2003.
LIGO NSF review, 11/10/05 1 AdLIGO Optical configuration and control Nov 10, 2005 Alan Weinstein for AdLIGO Interferometer Sensing and Control (ISC) and.
1 Virgo commissioning status M.Barsuglia LAL Orsay.
1 LIGO-G v3 Transmission Monitoring Telescope and Suspension – TMS Eric Gustafson aLIGO NSF Review LIGO Livingston Observatory April 25-27, 2011.
LIGO NSF review, 11/10/05 1 AdLIGO Optical configuration and control Nov 10, 2005 Alan Weinstein for AdLIGO Interferometer Sensing and Control (ISC) and.
LIGO-G W Status of LIGO Installation and Commissioning Frederick J. Raab, LIGO Hanford Observatory.
LIGO-G D partial ADVANCED LIGO1 Optical Layout Cavity Lengths Input Mode Cleaner (IMC) »IMC FSR = ~9 MHz »Length = ~16.6 m = ~HAM1 to HAM3 separation.
LIGO-G D partial ADVANCED LIGO1 Development Plan R&D including Design through Final Design Review »for all long lead or high risk subsystems »LIGO.
LIGO- G05XXXX-00-R 40m meeting, May Experimental update from the 40m team 40m TAC meeting May 13, 2005 O. Miyakawa, Caltech and the 40m collaboration.
LIGO-G M April 5, 2006 Interferometer Sensing and Control (ISC) Cost and Schedule Breakout Presentation NSF Review of Advanced LIGO Project Richard.
LIGO-G W Status of LIGO Installation and Commissioning Frederick J. Raab, LIGO Hanford Observatory.
40m Laboratory Progress Report LSC meeting at LIGO Hanford Observatory
Design of Stable Power-Recycling Cavities University of Florida 10/05/2005 Volker Quetschke, Guido Mueller.
The GEO 600 Detector Andreas Freise for the GEO 600 Team Max-Planck-Institute for Gravitational Physics University of Hannover May 20, 2002.
LIGO- G R 40m Progress, LSC meeting, Aug m Laboratory Upgrade Progress Report Osamu Miyakawa, Caltech 40m Technical Advisory Committee.
LIGO-G R Aspen Current Status of the 40m Detuned RSE Prototype Seiji Kawamura 2004 Aspen Winter Conference on Gravitational Waves Gravitational.
LIGO-G M May 31-June 2, 2006 Input Optics (IO) Cost and Schedule Breakout Presentation NSF Review of Advanced LIGO Project David Reitze UF.
LIGO- G R 40m Progress, LSC meeting, 3/031 40m Laboratory Upgrade Progress Report Osamu Miyakawa, Caltech 40m Technical Advisory Committee LIGO-G R.
Amaldi conference, June Lock acquisition scheme for the Advanced LIGO optical configuration Amaldi conference June24, 2005 O. Miyakawa, Caltech.
G M 1 Advanced LIGO Update David Shoemaker LSC/Virgo MIT July 2007.
LIGO-G R AJW/40m, LSC meeting, March Caltech 40 meter Prototype Program  Objectives  Accomplishments in the last year »Infrastructure.
LIGO- G R Amaldi7 July 14 th, 2007 R. Ward, Caltech 1 DC Readout Experiment at the Caltech 40m Laboratory Robert Ward Caltech Amaldi 7 July 14.
G Z LIGO R&D1 Input Optics Definition, Function The input optics (IO) conditions light from the pre- stabilized laser (PSL) for injection into.
LIGO- G R Sensing and control, SPIE conference, June Sensing and control of the Advanced LIGO optical configuration SPIE conference at.
Advanced Virgo Optical Configuration ILIAS-GW, Tübingen Andreas Freise - Conceptual Design -
LIGO-G R AJW/40m, NSF Review, 1/29/011 Caltech 40 meter Prototype Program  Objectives  Accomplishments in the last year »Infrastructure »IFO.
Advanced LIGO Sensing and Control Readout schemes for Advanced LIGO K.A. Strain University of Glasgow G & G
LSC-March  LIGO End to End simulation  Lock acquisition design »How to increase the threshold velocity under realistic condition »Hanford 2k simulation.
G D Commissioning Progress and Plans Hanford Observatory LSC Meeting, March 21, 2005 Stefan Ballmer.
LIGO- G R Aspen winter conference, January Toward the Advanced LIGO optical configuration investigated in 40meter prototype Aspen winter.
LIGO-G R D. Ugolini, 40m Design Review, 10/18/ Meter Subsystems  PSL »Commissioning »Noise performance  Vacuum »Operating pressure goal.
AIGO 2K Australia - Italy Workshop th October th October 2005 Pablo Barriga for AIGO group.
LIGO- G R 40m Progress, LSC meeting, 8/021 40m Laboratory Upgrade Progress Report Dennis Ugolini, Caltech 40m Technical Advisory Committee LIGO-G R.
Update on Activities in Suspensions for Advanced LIGO Norna A Robertson University of Glasgow and Stanford University LSC meeting, Hanford, Aug 20 th 2002.
Nov 3, 2008 Detection System for AdV 1/8 Detection (DET) Subsystem for AdV  Main tasks and requirements for the subsystem  DC readout  Design for: the.
Advanced LIGO Simulation, 6/1/06 Elba G E 1 ✦ LIGO I experience ✦ FP cavity : LIGO I vs AdvLIGO ✦ Simulation tools ✦ Time domain model Advanced.
LIGO-G D 1 Status of Detector Commissioning LSC Meeting, March 2001 Nergis Mavalvala California Institute of Technology.
LSC Meeting at LHO LIGO-G E 1August. 21, 2002 SimLIGO : A New LIGO Simulation Package 1. e2e : overview 2. SimLIGO 3. software, documentations.
LIGO-G M Overview of LIGO R&D and Planning for Advanced LIGO Detectors Gary Sanders NSF R&D Review Caltech, January 29, 2001.
LIGO-G D Commissioning at Hanford Stan Whitcomb Program Advisory Committee 12 December 2000 LIGO Livingston Observatory.
LIGO- G R AJW,report to 40m TAC, Aug 13, Report to 40 Meter TAC  Caltech 40 Meter Prototype »Objectives and scope »Trade-offs and compromises.
LIGO- G Z LSC meeting at Baton Rouge, March Caltech 40m Lab Update LSC Meeting Baton Rouge Mar 21, 2007 Robert Ward, Caltech and the 40m.
Monica VarvellaIEEE - GW Workshop Roma, October 21, M.Varvella Virgo LAL Orsay / LIGO CalTech Time-domain model for AdvLIGO Interferometer Gravitational.
LIGO-G R DC Detection at the 40m Lab DC Detection Experiment at the 40m Lab Robert Ward for the 40m Lab to the AIC group Livingston LSC meeting.
LIGO-G Z 3) Current Status & Plan for Japan RSE -- Stabilization and Installation of PRC & Detuning -- LSC Livingston 2002 Kentaro Somiya.
G R 2004 Plan Update LIGO Systems meeting 22 Jan 04 dhs.
LIGO- G R Amaldi7 July 14 th, 2007 R. Ward, Caltech 1 Prototyping for eLIGO: Power Recycled Fabry Perot Michelson DARM RF ITMy ITMx BS PRM SRM.
Testing Advanced LIGO length sensing and control scheme at the Caltech 40m interferometer. at the Caltech 40m interferometer. Yoichi Aso*, Rana Adhikari,
Main Interferometer Subsystem
Main Interferometer Subsystem
Next Generation Low Frequency Control Systems
Demonstration of lock acquisition and optical response on
Reaching the Advanced LIGO Detector Design Sensitivity
Design of Stable Power-Recycling Cavities
Current Status of the 40m Detuned RSE Prototype
Interferometer Design for bKAGRA Phase 1 and Beyond
Workshop on Gravitational Wave Detectors, IEEE, Rome, October 21, 2004
Status of LIGO Installation and Commissioning
40m Laboratory Upgrade Progress Report
Interferometer Design for bKAGRA Phase 1 and Beyond
Interferometer Design for bKAGRA Phase 1 and Beyond
Interferometer Design for bKAGRA Phase 1 and Beyond
Advanced LIGO optical configuration investigated in 40meter prototype
Interferometer Design for bKAGRA Phase 1 and Beyond
Improving LIGO’s stability and sensitivity: commissioning examples
Progress report from 40m team for the Advanced LIGO
40m TAC Update October 2006 The 40m Team 11 April 2019 G I.
Interferometer Design for bKAGRA Phase 1 and Beyond
Presentation transcript:

LIGO- G R 40mAdvLIGO R&D program, 10/8/ Meter Lab program for AdvLIGO R&D Alan Weinstein, Caltech AdvLIGO R&D Technical Review, 10/8/02 LIGO-G R Primary objective: full engineering prototype of optics control scheme for a dual recycling suspended mass IFO, as close as possible to the Advanced LIGO optical configuration and control system

LIGO- G R 40mAdvLIGO R&D program, 10/8/022 Advanced LIGO technical innovations tested at 40m  a seventh mirror for signal recycling »length control goes from 4x4 to 5x5 MIMO  detuned signal cavity (carrier off resonance)  pair of phase-modulated RF sidebands » frequencies made as low and as high as is practically possible »unbalanced: only one sideband in a pair is used » double demodulation to produce error signals  short output mode cleaner » filter out all RF sidebands and higher-order transverse modes  offset-locked arms » controlled amount of arm-filtered carrier light exits asym. port of BS  DC readout of the gravitational wave signal Much effort to ensure high fidelity between 40m and Adv.LIGO!

LIGO- G R 40mAdvLIGO R&D program, 10/8/023 Differences between AdvLIGO and 40m prototype  Initially, LIGO-I single pendulum suspensions will be used »No room for full scale AdvLIGO multiple pendulums – to be tested at LASTI »Scaled-down versions to test controls hierarchy in 2004?  Only commercial active seismic isolation »STACIS isolators in use on all test chambers, providing ~30 dB of isolation from Hz »No room for anything like full AdvLIGO design – to be tested at LASTI  LIGO-I 10-watt laser, negligible thermal effects »Other facilities will test high-power laser (LASTI, Gingin) »Thermal compensation also tested elsewhere  Small (5 mm) beam spot at TM’s; stable arm cavities »AdvLIGO will have 6 cm beam spots, using less stable cavities »40m can move to less stable arm cavities if deemed useful  Arm cavity finesse at 40m chosen to be = to AdvLIGO »Storage time is x100 shorter »significant differences in lock acquisition dynamics, in predictable ways  Control RF sidebands are 33/166 MHz instead of 9/180 MHz »Due to shorter PRC length »Less contrast between PRC and SRC signals

LIGO- G R 40mAdvLIGO R&D program, 10/8/024 Milestones achieved so far  Laboratory infrastructure complete »Building, control room, vacuum controls & pumps, vacuum envelope, seismic stacks, in-vac cables, electrical power, racks, cable trays, optical tables, enclosures, computers & networking  STACIS, PEM, DAQ commissioned  PSL commissioned  Conceptual Design Review completed October 2001  Digital suspension controllers for MC1,MC2,MC3  13-meter suspended-mass MC commissioned  Detailed optical layout and ISC design for core IFO  3 of 7 core optics suspended

LIGO- G R 40mAdvLIGO R&D program, 10/8/025 Next 9 months  Install digital ASC (WFS) on 13m mode cleaner.  Fully characterize 13m mode cleaner performance.  The digital suspension controllers for all 10 suspended optics should be complete by the end of calendar  Assemble, hang, and install the remaining core suspended optics (BS, ITMx, ITMy, done; ETMx, ETMy, PRM, SRM next) by the end of calendar 2002, and have them damped by the controller system.  Fabricate and install all remaining optical sensing beamline equipment on the existing enclosed optical tables, by 2Q 2003 (SP,AP,POB,POI,TRx,Try).

LIGO- G R 40mAdvLIGO R&D program, 10/8/026 Next 9 months, continued Fabricate and install auxiliary optics systems: scattered light control, initial alignment system, optical levers, video monitoring. Fabricate and install the length sensing and control system. Fabricate and install the alignment sensing and control system. Data handling: fiber link to CACR? (Currently, we only save all trend frames, backed-up to AIT occasionally). There may be some necessary augmentation of the DAQS, computing, networking, and environmental monitoring systems.

LIGO- G R 40mAdvLIGO R&D program, 10/8/027 Longer term  All systems installed, commissioning begun by summer » First experiments in dual recycled configuration response, lock acquisition, and control are expected to take at least a year. » We expect that LSC members, as well as students, will participate in this most interesting phase of the project.  Elements not designed in detail will be delayed until FY04: » Output mode cleaner » DC demodulation scheme » Multiple suspensions?  The only impediments to this schedule that we foresee are: » Availability of sufficient funding » Sufficient communication and support to/from the LSC/AIC group on the top- level design

LIGO- G R 40mAdvLIGO R&D program, 10/8/028 Milestones revisited  2Q 2002: »All in-vacuum cables, feedthroughs, viewports, seismic stacks installed. »12m input MC optics and suspensions, and suspension controllers.  3Q 2002: »Begin commissioning of 12m input mode cleaner. »Acquisition of most of CDS, ISC, LSC, ASC.  4Q 2002: »Core optics (early) and suspensions ready. Ten Suspension controllers. Some ISC. »Glasgow 10m experiment informs 40m program »Control system finalized  2Q 2003: »Core optics (late) and suspensions ready. »auxiliary optics, IFO sensing and control systems assembled.  3Q 2003: Core subsystems commissioned, begin experiments »Lock acquisition with all 5 length dof's, 2x6 angular dof's »measure transfer functions, noise »Inform CDS of required modifications  3Q 2004: Next round of experiments. »DC readout. Multiple pendulum suspensions? »Final report to LIGO Lab.

LIGO- G R 40mAdvLIGO R&D program, 10/8/029 (Some) outstanding issues and action items (40m, AdvLIGO)  Any significant changes in people’s thinking re: optical configuration, controls, CDS architecture??  180 MHz PD’s for WFS, LSC. Double demodulation(180  36 MHz).  Develop ASC/WFS model.  Design servo filters for LSC, ASC!  Detailed noise model (RSENOISE, Jim Mason)  Lock acquisition studies with E2E/DRLIGO.  Develop lock acquisition algorithms, software.  Triple-check thermal effects (Melody) – negligible?  Output mode cleaner – will PSL-PMC-like device be adequate? (For 40m, for AdvLIGO). Suspended?  Offset-lock arms - algorithms, software.  DC GW PD – in vacuum? Suspended?

LIGO- G R 40mAdvLIGO R&D program, 10/8/ m Team Live and breathe 40m, ~100%  Alan Weinstein  Dennis Ugolini  Osamu Miyakawa  Steve Vass  Ben Abbott  Bob Taylor  Mike Smith Contributing LIGO engineers: Larry Jones Jay Heefner Janeen Romie GariLynn Billingsley Helena Armandula Betsy Bland CDS folks (Bork, Ivanov, …) PSL folks (King, Cardenas…) Lots of help from many others! Also: Typically 5 SURF students, visiting students & physicists, etc. The 40m team is minimal, but they’re first-rate, with a very appropriate mix of skills. Our size is, I believe, adequate for the task (well, at least until commissioning begins in earnest), provided that LIGO engineering technical support remains available. From now on, we will primarily need continued CDS support – or, more meaningfully, CDS will need the 40m lab more, as we develop AdvLIGO CDS…

LIGO- G R 40mAdvLIGO R&D program, 10/8/0211 Cost baseline and issues  FY03 budget aims to complete construction of the DR IFO, and begin commissioning / experiments.  Budget consists of salaries, misc. equipment and supplies, and… equipment to complete DR IFO.  Of course, you can’t build an IFO of this complexity without an adequate equipment budget, and you’re likely to regret cutting corners on instrumentation…

LIGO- G R 40mAdvLIGO R&D program, 10/8/0212 Additional slides with more detail

LIGO- G R 40mAdvLIGO R&D program, 10/8/0213 Milestones Achieved as of March LSC Meeting  Building renovation: Control room added; electronics racks, power conditioners, cable trays, computers & networking infrastructure installed  Vacuum revision: 13m MC and OOC added to envelope; pumps, controls updated  Active seismic isolation (STACIS) installed at all test mass chambers  Initial LIGO PSL commissioned and characterized; NPRO replaced and realigned  DAQ installed and logging frames; trends saved since July 2001  PEM installed and running (dust, seismometer, weather, STACIS readback)  Conceptual Design Review completed in Oct 2001  Optical layouts complete for in- and out-of-vacuum; parts lists assembled  Procurement of CDS, ISC, etc. begun  Mode cleaner optics and suspensions in hand, specs for core optics completed

LIGO- G R 40mAdvLIGO R&D program, 10/8/0214 Further Infrastructure  Final optical table, beam tubes, table covers installed  IR-coated viewports, cameras installed  MC reflected and transmitted optical paths assembled  MC, OOC seismic stacks installed and cabled  MC optics hung, balanced, installed in April

LIGO- G R 40mAdvLIGO R&D program, 10/8/0215 Digital Suspensions  Digital suspensions for the mode cleaner optics were installed in May; full control system for all 10 core optics expected by end of 2002  Digital notch filter added at 23.7 Hz to eliminate anomalous “roll mode” in MC1; may be due to lateral misalignment of OSEMs  GDS/DTT/AWG installed; used Mark Barton’s code to diagonalize input, output matrices of MC2, MC3

LIGO- G R 40mAdvLIGO R&D program, 10/8/ meter Mode Cleaner Lock ~8.7 hours M=3.0 earthquake at 3:10 AM After considerable work diagnosing problems, and differences between documents and as-built systems at sites: Lock is quickly and robustly achieved, and maintained (in detection mode), using the MC servo. Much valuable experience gained by Ugolini, Miyakawa, Abbott

LIGO- G R 40mAdvLIGO R&D program, 10/8/0217 Core Suspended Optics  The core optics for the main dual recycled interferometer were produced, polished, and coated as of Aug Completed pieces have been delivered and are have been measured by LIGO optical engineers (Armandula, Billingsley).  The mechanical suspensions for the remaining 7 optics, for the main dual recycled interferometer, have been designed, fabricated, cleaned and baked.  BS (SOS), ITMx & ITMy (“MOS”) suspended in September 2002 (Bland, Armandula, Vass, Ugolini, Taylor).  We plan to hang the remaining 4 optics (ETMx, ETMy, PRM, SRM), and install them in the vacuum envelope this winter.