ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 1 Monthly Status Report Report due 3/25/00 Schedule statused.

Slides:



Advertisements
Similar presentations
Control and IT Systems status and strategy ALBA, Piotr Goryl on behalf of Michał Ostoja-Gajewski, Krzysztof Wawrzyniak, Łukasz Żytniak, Tadeusz.
Advertisements

MIS 2000 Class 20 System Development Process Updated 2014.
L. Greiner 1HFT PXL LBNL F2F – March 14, 2012 STAR HFT The STAR-PXL sensor and electronics Progress report for F2F.
Project Control Techniques
IS112 – Chapter 1 Notes Computer Organization and Programming Professor Catherine Dwyer 2003.
1 Project Management & Project Management Software Yale Braunstein School of Information Management & Systems UC Berkeley.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test One and Two Tower Integration Readiness Review.
Development and Quality Plans
LSU 01/18/2005Project Life Cycle1 The Project Life Cycle Project Management Unit, Lecture 2.
Phase II Review MSD II P Size is too big and not comparable with original testing Hinge is not possible with rapid prototyping, metal hinge would.
Solar Probe Plus FIELDS Monthly Management Telecom Sep 17, 2012.
The Maintenance and Engineering Organization
S/W Project Management
GTRInewFormat.ppt-1 Electronic Systems Laboratory TMC Operator Requirements and Position Descriptions, Phase 2, Kickoff Meeting Presented by Dennis J.
Linac Marx Modulator Update Trevor Butler 10/29/2014.
ASPERA-3 Sep. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 9_25/ Page 1 Monthly Status Report Report due 9/25/00 Schedule statused.
ASPERA-3 July 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 7_25/ Page 1 Monthly Status Report Report due 7/25/00 Schedule statused.
Nightly Releases and Testing Alexander Undrus Atlas SW week, May
ASPERA-3 July 31, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 7_31/ Page 1 Monthly Status Report Report due 7/25/01 Schedule statused.
ASPERA-3 April. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/01 Schedule statused.
Installing Windows Vista Lesson 2. Skills Matrix Technology SkillObjective DomainObjective # Performing a Clean Installation Set up Windows Vista as the.
Product Development Chapter 6. Definitions needed: Verification: The process of evaluating compliance to regulations, standards, or specifications.
AGATA Pre-processing team report AGATA Week, July 2008.
CSE 548 Advanced Computer Network Security Document Search in MobiCloud using Hadoop Framework Sayan Cole Jaya Chakladar Group No: 1.
Plan Design Analyze Develop Test Implement Maintain Systems Development Life Cycle MAT Dirtbikes.
1 Kenneth Osborne, 9/14/07 Inter Group communications at the Advanced Light Source. Overview of the different methods of communication between different.
ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused.
Brief status on key on-going PCR activities NWE Regulators IG Meeting 28 Mar March 2012.
ASPERA-3 Jan. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 1_25/ Page 1 Monthly Status Report Report due 1/25/01 Schedule statused.
ASPERA-3 June 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 6_25/ Page 1 Monthly Status Report Report due 6/25/00 Schedule statused.
PDS Geosciences Node Page 1 Archiving Mars Mission Data Sets with the Planetary Data System Report to MEPAG Edward A. Guinness Dept. of Earth and Planetary.
Fall CS-EE 480 Lillevik 480f06-l10 University of Portland School of Engineering Senior Design Lecture 10 Webs Scheduling MS Project (Optional)
Systems Life Cycle A2 Module Heathcote Ch.38.
Presented by A.B. Galvin STEREO SWG NOAA Boulder, Co 22 March 2004 PLASTIC Activities.
ASPERA-3 June 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 6_25/ Page 1 Monthly Status Report Report due 6/25/01 Schedule statused.
THE PROJECT LIFE CYCLE PROJECT MANAGEMENT LIFE CYCLE LSU 01/18/2005 PROJECT LIFE CYCLE 1.
Swift HUG April Swift data archive Lorella Angelini HEASARC.
ASPERA-3 May 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 5_25/ Page 1 Monthly Status Report Report due 5/25/01 Schedule statused as.
GLAST LAT Project – Cost and Schedule ReviewJanuary 27, 2004 AntiCoincidence Detector 1 GLAST Large Area Telescope: Cost/Schedule Review January 27, 2005.
ASPERA-3 Mar. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 1 Monthly Status Report Report due 3/25/01 Schedule statused.
1 LHC-DFBX Fabrication Oversight Plan Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab.
Connecting with Computer Science2 Objectives Learn how software engineering is used to create applications Learn some of the different software engineering.
ASPERA-3 Feb. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 2_25/ Page 1 Monthly Status Report Report due 2/25/01 Schedule statused.
Project Management Inspections and Reviews 1 February.
Project Management. Introduction  Project management process goes alongside the system development process Process management process made up of three.
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
L. Greiner1IPHC-LBNL Phone Conference 05/2012 STAR IPHC-LBNL Phone Conference News and updated ladder testing.
PASI OsC meeting 12th July 2012
GLAST LAT ProjectCAL Peer Design Review, Mar 17-18, 2003 W. N. Johnson Naval Research Lab Washington DC GLAST Large Area Telescope Calorimeter Subsystem.
ATLAS Pixel Detector September 2002 N. Hartman LBNL 1 Pixel Support Tube: Cost and Production Schedule September 2002.
1 SUZAKU HUG 12-13April, 2006 Suzaku archive Lorella Angelini/HEASARC.
March 25, FVTX Monthly/Quarterly Report June, 2009 Technical Status, Cost & Schedule Melynda Brooks, LANL.
IBM Express Runtime Quick Start Workshop © 2007 IBM Corporation Deploying a Solution.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems November 2003 GSFC Status Marc Campell, Subsystem Manager.
1 Sean Aluoto Anthony Keeley Eric Werner. 2 Project Plan Overview Project Lifecycle model Time line Deliverables Organization plan Risk management Design.
1 BNL LHC Hi-Lumi QXF Vertical Test Facility Status Update M. Anerella, H. Hocker, P. Joshi, P. Kovach, A. Marone March 28, 2016.
The information systems lifecycle Far more boring than you ever dreamed possible!
MAVEN-SWEA Assembly, Integration & Test (AIT) Contents AIT: CESR Team Facilities Main subcontractors Applicable documents AIT documentation Cleanliness.
Proctor Caching and System Check September 4, 2014 Becky Hoeft Conference Number: (877) Conference Pin:
Computer Technology: Your Need to Know Chapter 1 Slide 1.
PSL APA Update May 3, 2016 UW Physical Sciences Lab.
Bill Raynor Naval Research Lab
Principles of Information Systems Eighth Edition
Systems Analysis and Design
Microsoft FrontPage 2003 Illustrated Complete
Maintenance module Martin Heigl CTO
X-ray Pump-Probe Instrument
Presentation transcript:

ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 1 Monthly Status Report Report due 3/25/00 Schedule statused as of Mar. 10, 2000

ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 2 Project Status Summary Technical Jan Feb Mar Detailed Description: (for items identified as yellow or red) Programmatic Jan Feb Mar Schedule Jan Feb Mar Resources Jan Feb Mar We were becoming increasingly worried about when the final contract would be put in place. For the entire month of February, we have been working at our own financial risk. We completed the 4-month Bridge phase which was put in place solely to allow time for the final contract to be finalized. With the contract now received at SwRI, it appears that this is no longer a concern. We do not see any problems at this time either technical, schedule, or programmatic. We are still on schedule though the schedule is tight. We have been continuing to use additional personnel (while remaining on our spend plan) to maintain the schedule. Latest project photos are available on Aspera-3 web site.

ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 3 Problem and Concern Summary P=Problem C=Concern R=Resolved

ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 4 Accomplishments of the Last Month -ELS Completed bench test of the HVPS. Interfaced the HVPS to the FEE for a compatibility test. No “noise” seen in FEE. This test eliminated the potential need for some sort of shield between the HVPS and the FEE. This is a major program milestone. We agreed to a price and subcontract with Walton Plating. P.O. has been placed. Prototype mechanical parts are currently being plated at Walton Plating.  Communication between the Swedish DPU and and the SwRI controller that will be used during ELS vacuum characterization was completed successfully.

ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 5 Accomplishments of the Last Month -ELS (cont.)  Input tests to the Swedish DPU have been successfully detected at the controller  The feasibility of ELS power supply control by the DPU during calibration is currently under investigation  Vacuum goniometer control solved with separate computer system controllers, one to control ELS and the other for the vacuum system Modification of lab test control software is almost done, just received the last files.

ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 6 Accomplishments of the Last Month - IMA Received the two printed circuit boards (anode / amplifier board & digital board). Digital board part installation is 50% complete. We are waiting on some parts to come in. Anode board is currently in fab and is about 50% complete. Mechanical parts for prototype, flight and flight spare IMA detector are being machined to be completed first week of April. IMA MCPs are in house. Began design of the IMA GSE.

ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 7 Accomplishments of the Last Month - Data Reduction Software  Set up ASPERA-3 Processing and Archiving Facility (APAF) Lab  Configured APAF Network and Servers  Continued Defining IDFS Web Tools  Updated Software Development Plan (version 1.1 to be available by March 31, 2000)  Held monthly ASPERA-3 Software Status Meeting (March 21, 2000)

ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 8 Planned Activities for the Next Month - ELS Perform fit check of housing, HVPS and FEE when housing is received back from UV coating at Walton Plating. Continue bench level compatibility tests between HVPS and FEE. Decide whether the current printed circuit boards that were used for the prototype are suitable for flight. (Note: They were bought with certs.) Begin cabling for ELS vacuum tests. Finalize modification of the Astrid EGSE to use for ELS.

ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 9 Planned Activities for the Next Month - IMA Finish populating circuit boards. Finalize fabrication of IMA prototype mechanical parts. Finalize the mechanical analysis. Continue design and fabrication of the IMA EGSE.

ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 10 Planned Activities for the Next Month - Data Reduction Software Tasks  Finish Configuration of ASPERA-3.org Server  Complete ASPERA-3.org Web Site Documentation  Provide Technical Assistance for EPO Web Information  Continue Implementation of IDFS Web Tools  Continue to Define IDFS Information Gathering Tools  Update Data System Interface Document Based on Latest Information  Provide Draft of Project Data Management Plan

ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 11 Problem and Concern Status (cont.) MOU / SOW with MSSL for UV coating: Resolved. MOU / SOW in place. Purchase Order has been placed. Prototype ELS parts are currently being coated. Plan is in place for coating the flight parts. Get ELS EGSE up and running: Resolved. We continue to make good progress with the EGSE. We now have on-board a student from IRF to help out in setting up the GSE. We now have it running and only need to make minor mods to it to get it finalized. It is no longer one of our worries.

ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 12 Problem and Concern Status (cont.) Getting final contract in Place by March 1, 2000 (now April ): Still a concern. The dealing with NASA contracts continues to be our number one problem area on the project. We did receive a copy of the contract on March 24 (after waiting almost 5 months). We are in the process of reviewing it to turn it around by the end of the month. Fortunately for the ASPERA project, SwRI administration has allowed us to continue work with only a letter rather than the signed contract. We still see this issue as a concern, and will until it is signed-off by all parties.

ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 13 Problem and Concern Status (cont.) Fabrication of IMA MCP Holder: Resolved. The fabrication of the IMA MCP holder is a underway with all prototype, flight and flight spare parts due to be finished the first week of April. Due to the simple nature of the parts and the their flight history, we opted to go ahead and make all flight parts with the prototype parts to get ahead of the schedule and to realize the savings of a single set-up in the machine shop.

ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 14 Problem and Concern Status (cont.) Assembly Process for ELS with UV Coated Parts: A new concern. We will soon be receiving the prototype ELS parts from Walton plating. We will start to to develop special handling, storage, and assembly procedures, processes and aids during the next month. We are concerned with the fragility of the coating and how we will assemble the very intricate ELS mechanical and electrical subassemblies.

ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 15 Schedule Summary Total float on the tasks in the schedule has not changed much since last month. Mechanical is again the critical path (ELS Mechanical Details) with about 15 days float. As with last month: –Schedule still has 21 days slack at the end (DEL0050) in addition to float shown for each task –FEE & HVPS have 20 days each allotted for mods after prototype testing. –All flight activity is completely serial with prototype activities. We can (will) do activities in parallel to maintain schedule. If we opt to use any of the prototype PCB’s for flight, we will update the schedule accordingly buying us additional float that can be used downstream if problems arise. Software activities are on schedule. Full-up schedule is available on the ASPERA-3 Web site.

ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 16 ASPERA-3 PHASE B/C/D MASTER SCHEDULE