RHIC 56 MHz HOM Damper Fundamental Damper Fundamental Power Coupler Pick-ups S. Bellavia January 19 th, 2010.

Slides:



Advertisements
Similar presentations
RF Cavity Module G. Gosling Dept. of Mechanical Engineering Imperial College London.
Advertisements

MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Mech Systems Proposed EMI Modifications Marc Campell 9/2/03.
Fabrication Progress for LHC Superconducting Crab Cavities April 17, 2015.
MICE RF Cavity Design and Fabrication Update Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 27, 2004.
J. H. ChrzanowskiNSTX TF Flag Joint Design Review1 NSTX TF Flag Joint Design Review Fabrication and Assembly April 10, 2003 By: James H. Chrzanowski.
Status of the SPL cavities at CERN I.Aviles & N. Valverde on behalf of SPL team 1I. Aviles & N. ValverdeLund, 11 December 2013.
Progress on the MICE 201 MHz Cavity Design Steve Virostek Lawrence Berkeley National Lab RF Working Group Fermilab August 22, 2007  automatic.
David H. Dowell Injector RF Design November 3, LCLS Injector RF Gun: Design, Fabrication & Tuning Plans D. H. Dowell,
BPM Upgrade Presented by: Nadine Kurita Contributors: S. Smith, S. Ecklund, J. Sebek, D. Martin, R. Hettel, R. Johnson, N. Reeck, M. Kosovsky, D. Arnett.
Fabrication Progress for LHC Superconducting Crab Cavities July 10, 2015.
3.9GHz Coupler Cold End Robustness Study Will Couplers survive on-site and overseas shipping? D. Olis, G. Galasso, M. McGee.
RF Cavity / Coupling Coil Module
Industrial Studies of ILC Cavities & Component Production in the Americas IPAC 11 – Kyoto, Japan May 23, 2010 Science Projects Homeland Security Medical.
LARG week 07/01 Paul Poffenberger University of Victoria Endcap Feedthrough Production at Victoria Status Summary.
Status report on “Industrialization studies” at LAL on power couplers for XFEL _____ TILC08 – Tohoku University 3-6 March 2008 Sendai - Japan G. Wormser.
Ernie Ihloff 21 May 08 Preliminary Heat Shield Design for nEDM.
RF power & FPC status Eric Montesinos, CERN BE-RF on behalf of all people involved, great thanks to all of them !
S1G Experiment Schedule Plan H. Hayano. Assembly work after cavity arrived Assumption: cavity with VT, with pickup antena, with Ar or N2 filled,
Cavity status; recent KEK activities : Hayano (1) STF CM-1 cavities are; MHI-014: 3-rd VT:36MV/m (finished) MHI-015: 3-rd VT: > 18.4MV/m.
RFQ Fabrication Plan, Schedule and QC PXIE RFQ Fabrication Readiness Review LBNL – June 26, 2013 Steve Virostek - Engineering Division Lawrence Berkeley.
F.E.T.S. RFQ Mechanical Design by Peter Savage 7 th January 2010.
Work toward Stainless Steel SRF Helium Vessels at Fermilab Tom Peterson (presenter), Information from Jeff Brandt, Serena Barbanotti, Harry Carter, Sergei.
NML High Energy Beam Absorbers and Dump 29-August-2011 Beams-doc-3928.
CMS FPIX Cooling System Studies Joe Howell, Fermilab for the FPIX Upgrade Mechanical Working Group CMS Upgrade Workshop April 27,
G5 Beam Line Vacuum System. G5 Beamline Vacuum System Design  Bakeable and Particulate free to Class 100 Clean Room quality Require Clean room QA and.
Advanced Energy Systems, Inc. Prototype Cavity Fabrication & Test Presented by Ilan Ben-Zvi, BNL for Michael Cole, AES.
1.3GHz Input Coupler for ILC
MICE RFCC Module Status Derun Li Lawrence Berkeley National Lab NFMCC-MCTF Collaboration Meeting LBNL, Berkeley, CA January 25, 2009.
F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF, TF, & Trim Coil Supports (WBS-15) Core Base Support Structure (WBS-17) F. Dahlgren NCSX Coil.
Eric Montesinos - CERN - First SPL collaboration meeting - CERN December 11th 2008 First SPL collaboration meeting Experience with the LHC Main power Coupler.
Longitudinal HOM damping estimations for SPL cavity. status W. Weingarten 26 July 20101SPL Cavity WG Meeting.
LAr Week Feb 2000 M. Lefebvre Milestones and Schedule General Production Readiness Review  Passed in Jan 99 Leak Test Station and Electric Test.
 =1 cavity: parameters Dimensions for cavity fabrication before any chemical polishing and at room Temp. outer ½ cell pick-up side inner ½ cells outer.
MICE RFCC Module Update Steve Virostek Allan DeMello Lawrence Berkeley National Laboratory MICE CM27 at RAL, UK July 8, 2010.
S1 global: thermal analysis TILC09, April 19th, 2009 Serena Barbanotti Paolo Pierini.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 30 Jan 2007 No 1 /13 LARP Phase II Secondary Collimator RC1 Collimator Development and Test Program Status.
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
DTL prototype summary and production sequence F.Grespan LNL _06_22 CDR.
MICE RF Coupler Modifications Update 4/30/2015 Allan DeMello.
RF Module Update MICE Collaboration Meeting 44 Andrew Lambert Lawrence Berkeley National Laboratory March 30 th, 2016.
201 MHz Cavity Plans Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory February 11, 2011 MAP Friday Video Conference Meeting.
RFQ Installation Status 10/27/2015 October 27, 2015 Jim Steimel & Curtis Baffes.
PXIE RFQ Engineering Design Steve Virostek Engineering Division Lawrence Berkeley National Laboratory April 10, 2012 Project X Collaboration
RFQ coupler S. Kazakov 07/28/2015. Requirements: Coupler requirements Expected problems: Heating (loop, ceramic window, etc.) Multipactor Solutions: Appropriate.
ICFA Workshop on High Order Modes in Superconducting Cavities July First Experience with an HOM Coupler for the 56 MHz Quarter Wave SRF Cavity Qiong.
Engineering of the power prototype of the ESRF HOM damped cavity* V. Serrière, J. Jacob, A. Triantafyllou, A.K. Bandyopadhyay, L. Goirand, B. Ogier * This.
Developments of new treatment techniques for SRF cavities at KEK HORIZONTAL HPR FOR PERFORMANCE RECOVERY Yoshiyuki MORITA Motivation of developing HHPR.
JLAB Cryomodule Assembly Facilities Visit Report Tug Arkan, Yuriy Orlov March 26, 2012.
704 MHz cavity design based on 704MHZ_v7.stp C. Pai
Single Spoke Resonator SSR1 Construction Status P.N.Prakash Inter-University Accelerator Centre, New Delhi, INDIA.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
P. Bosland CEA-Saclay Collaboration Board meeting Copenhagen 14/04/ Status of the French activities under the responsibility of CEA Philippe CHOMAZ.
325 MHz Superconducting Spoke Cavity Coupler status. T. Khabiboulline Power Coupler design for Superconducting Spoke cavities. Originally.
Teleconference ACS – FREIA 31th May 2017
Resource Loaded Schedule and Budget Profile
S1G Experiment Schedule Plan
RF Dipole HOM Electromagnetic Design
Power coupler at DESY & for XFEL
Crab Cavity HOM Coupler Specification Drawings & Tolerances
LARP Phase II Secondary Collimator RC1
LARP Phase II Secondary Collimator RC1
MLC Schedule Plan Proven in-house expertise and infrastructure for fabrication, assembly, and testing cryomodules Confident in our technical expertise.
HL-LHC-UK: UK contribution to HL-LHC Crab Cavities and evolution
Crab Cavity Manufacturing Readiness Meeting
LARP Phase II Secondary Collimator RC1
Technical Issues Related to Superconducting Accelerator Modules
SNS PPU Cryomodule Thermal Shield
SNS PPU Cryomodule Space Frame
LCLS Vacuum System Plans (July 07)
Presentation transcript:

RHIC 56 MHz HOM Damper Fundamental Damper Fundamental Power Coupler Pick-ups S. Bellavia January 19 th, 2010

Higher Order Mode (HOM) Damper

HOM Thermal-Electric Performance Solid Model Assembly in Pro-E, Finite Element Model built in ANSYS 13.0

HOM Thermal-Electric Performance (cont.) Boundary Conditions: Surface RF Currents Dielectric (Joule) Heating of Sapphire Heat Leak from Ambient

HOM Thermal-Electric Performance (cont.)

Dielectric Heating of HOM Sapphire Break

Dielectric Heating of Sapphire Break (cont.)

HOM Thermal Performance (cont.) Internal Components

HOM Thermal Performance (cont.) Assembly with Heat-Stationed Cable 50K Heat Station From Heat Shield

HOM Cable Joule Heating vs. Thermal Conductivity OFHC Copper vs. 304 Stainless Steel

Cable Joule Heating Due to RF Current

Coaxial Cable Choices

Model for Calculations

FEA Model(s) SS Conductors, Heat Station with Effect of Contact Resistance These regions made 100X more thermally resistive than PTFE to simulate contact resistance

FEA Results 50K to Outer Shield For 250 SS Cable - FEA performed on many types and sizes

FEA Results Summary

HOM Cable-Connector Assembly

HOM Cable-Connector (cont.)

HOM Hex Seal 10 x 5/16-24 SS Bolts, Torqued to in-lbs results in lbf (80% of yield) Bolt Circle =  x = inches Linear Sealing Load = 10 x / = 1557 lb f /inch

HOM Final Design / Fabrication / Procurement Full set of drawings being checked SOW and Specification to be released this week, followed by Purchase order / RFQ Parallel Effort to build “in-house” (BNL will manage piece-part fabrication) - Quotation for brazing Sapphire break received - Quotation for Custom Sapphire tubes received - Awaiting Quotation for Stock Size Sapphire Tube

HOM Design / Fabrication

HOM Design / Fabrication (cont.)

HOM Filter Assembly

HOM Procurement

HOM Procurement (cont.)

Sapphire for Filter Components

HOM Schedule Jan 21 – Release of Drawings (numerical rev’s for quotation) Jan 21 – Signature / release of SOW and Specifications Jan 21 – Purchase order for building entire HOM assembly –Phase 1 – Prototype / First Article (20 +2 weeks – June ‘11) –Phase 2 – 6 follow-on HOM’s (36 +2 weeks – Oct ‘11) Feb 7 – P.O. for brazing of Sapphire-Niobium break supply vendor with sapphire tubes and machined niobium parts (12 weeks – April ‘11 ) purchase and receive brazed assemblies (16 weeks – May ‘11) arrange machining of niobium components (12 weeks – April ’11) send out machined parts and brazed assemblies for pre-cleaning, welding and final cleaning, (most likely to AES). (32 weeks – Sep ’11) Receive Final HOM’s (36 weeks – Oct ’11) Feb 21 – P.O. for Brazing of Filter Assembly

HOM Costs Sapphire tubes $ 15K Niobium (raw material) $ 10K Niobium machining$ 50K Brazed Break$ 20K Brazed Filter Assy$ 10K Welded Assemblies$200K Cleaned Assemblies$ 50K Total$355K First Article$150K 6 Final HOM’s $425K Total$575K Done “In-house” by BNLDone by Outside Vendor

Fundamental Damper

Fundamental Damper (cont.)

Fundamental Damper Motion System

Fundamental Damper Motion System Costs Motion System

Feb ‘11 – Thermal / Structural Analysis May ’11 – Detailed Design / Drawings Fundamental Damper Schedule / Costs Total Cost = $125K = 400 shop hours

Fundamental Power Coupler FPC

Fundamental Power Coupler (cont.)

Fundamental Power Coupler Connector 7/16 DINType N

Fundamental Power Coupler Weldable, UHV Compatible Connector / Window

Total Cost = $95,600 Fundamental Power Coupler Schedule / Cost Mar ‘11 – Thermal / Structural Analysis June ’11 – Detailed Design / Drawings

Total Cost = $2,100 Pick-Ups Schedule / Cost