Status of Radiation Protection Studies for the Linac4 beam dumps Joachim Vollaire DGS/RP.

Slides:



Advertisements
Similar presentations
Stefan Roesler SC-RP/CERN on behalf of the CERN-SLAC RP Collaboration
Advertisements

HZDR FLUKA activities in support of the MYRRHA Project Short summary with a focus on activation problems Anna Ferrari, Stefan Müller, Jörg Konheiser.
Radiation Protection aspects of the Switch-Yard operation V. Donate, G. Dumont, Joachim Vollaire on behalf of DGS-RP.
Internal H0/H- dump Cesare Maglioni, Melanie Delonca Thanks to: R. Chamizo, R. Versaci, O. Aberle, J. Borburgh.
1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007.
Shielding Studies using MARS Monte Carlo code Noriaki Nakao (SLAC) Jan. 6, 2005, WORKSHOP Machine-Detector Interface at ILC, SLAC.
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
Preliminary studies for Muon shield modification to accommodate LCLS II Alev Ibrahimov December, 2010 BSY.
1 Induced radioactivity in the target station and in the decay tunnel from a 4 MW proton beam S.Agosteo (1), M.Magistris (1,2), Th.Otto (2), M.Silari (2)
1 Radiation Safety Aspects of the Linear Collider B. Racky, A. Leuschner, N. Tesch Radiation Protection Group TeV Superconducting Linear Accelerator.
NML High Energy Beam Absorbers and Dump 29-August-2011 Beams-doc-3928.
Highlights of RP activities in support of ISOLDE operation and projects Joachim Vollaire, Alexandre Dorsival and Christelle Saury with material from others.
The Status of ESS Accelerator Shielding and Accident Scenarios Lali Tchelidze May 26, 2014.
Status of Radiation Protection studies in support of ELENA R. Froeschl and J. Vollaire DGS-RP-AS.
Integrated Radiation Measurement and Radiation Protection of BES Ⅲ Zhang Qingjiang, Wu protection group, accelerator center, IHEP,
F. Regis, LINAC4 – LBS & LBE LINES DUMP DESIGN.
Managed by UT-Battelle for the Department of Energy Residual Does Rate Analyses for the SNS Accelerator Facility I. Popova, J. Galambos HB2008 August 25-29,
Introduction From a neutron flux (> 20 MeV), with the Leaching model (Lessard) based on SBMS (Tables 1 and 2):
Dose Measurements S. Roesler (DGS-RP) Collimation WG – IR3 passive absorbers 4 June 2012.
Beam loads & dump concepts T. Kramer, B. Goddard, M. Benedikt, Hel. Vincke.
First radiological estimates for the HIRADMAT project H. Vincke and N. Conan 1.
PSB dump replacement 17 th November 2011 LIU-PSB meeting Alba Sarrió.
Estimates of Radiation Levels in the Main Linac Tunnel and Beam Dump Caverns for the CLIC Design Study Sophie Mallows, Thomas Otto SATIF 10, S.
Activation around dump shielding, and design of beam line mask Mathieu Baudin, RP Genevieve Steele, EN-STI Helmut Vincke, RP.
Required Dimensions of HAPL Core System with Magnetic Intervention Mohamed Sawan Carol Aplin UW Fusion Technology Inst. Rene Raffray UCSD HAPL Project.
Considerations for an SPL-Beamdump Thomas Otto CERN in collaboration with Elias Lebbos, Vasilis Vlachoudis (CERN) and Ekaterina Kozlova (GSI) Partly supported.
1 BROOKHAVEN SCIENCE ASSOCIATES Summary of Shielding Calculations for NSLS2 Accelerators P.K. Job Radiation Physicist Peer Review 2007 March
PIP Wednesday March 21, /21/12 Agenda Project Update(s) Pellico - PIP Status Talk(s) 1.Ryan Crawford: Linac Power Distribution - Shutdown 2012 activities.
Radiation Protection in J-PARC neutrino beam line Sep Yuichi Oyama (KEK) for T2K neutrino beam line construction group Happy birthday.
Application of FLUKA to fixed- target programs at CERN: a short, not exhaustive selection M. Calviani (CERN) With contributions from: M. Brugger, F. Cerutti,
GRAN SASSO’S HADRON STOP Temperature’s behaviour under specified beam conditions Barbara Calcagno.
New SPS scraping system: preliminary RP remarks Helmut Vincke DGS-RP.
NToF - Radiation Protection M. Brugger, P. Cennini, A. Ferrari, E. Lebbos, V. Vlachoudis CERN AB/ATB/EET.
WP2 progress on safety E. Baussan EUROnu CB Meeting Monday 10th & Tuesday 11th June 2011 CERN, Geneva, Switzerland.
Radiation protection and radiation safety issues for HIE-ISOLDE. FLUKA calculations Y. Romanets ISOLDE Workshop and Users meeting 2010 CERN, 8 December.
Radiation Protection studies for the Linac4 / Linac2 interface Joachim Vollaire, DGS-RP 28/09/2015 Linac4 Coordination Meeting.
Radiation Protection and Radiation Safety for Particle Accelerator Facilities J. Vollaire, Radiation Protection Group CERN Compact Accelerators for Isotope.
Radiation Protection Considerations for the CDR Helmut Vincke DGS-RP.
Status of n_TOF Facility
Characterization of the nTOF Radioactive Waste M. Brugger, P. Cennini, A. Ferrari, V. Vlachoudis CERN AB/ATB/EET.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Shielding Workshop R. Casey Activation Issues for NSLS-II March 28, 2007.
Present status of production target and Room design Takashi Hashimoto, IBS/RISP 2015, February.
EURISOL DS Task meeting Orsay, 07 Janvier Preliminary shielding assessment of EURISOL Post Accelerator D. Ene, D. Ridikas. B. Rapp.
The target handling concept of the pbar- separator at FAIR M. Helmecke, V. Gostishchev, R. Hettinger, K. Knie 6th High Power Targetry Workshop Oxford.
Status of the FAIR pbar target: Target handling study (M. Helmecke)
Neutron double differential distributions, dose rates and specific activities from accelerator components irradiated by 50 – 400 MeV protons F. Cerutti.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
High Energy Neutron and Proton Irradiation Facilities at TSL Alexander Prokofiev, , 6th LHC Radiation Workshop 1.
Prompt dose upstream the 12-ft concrete shielding blocks Igor Rakhno May 4, 2007.
EURISOL, TASK#5, Bucuresti, November 1 Preliminary shielding assessment of EURISOL Post Accelerator D. Ene, D. Ridikas. B. Rapp.
The ESS Target Station Eric Pitcher Head of Target Division February 19, 2016.
KEK Radiation Related Topics neutrino beam construction subgroup Yuichi Oyama (KEK) and target monitor subgroup for.
Radiation protection studies for the ESS Activation issues AD seminar Michał Jarosz , Lund.
ENERGY DEPOSITION AND TAS DIAMETER
General overview, layout of the pbar separator Target handling concept FLUKA calculations - for the target station - for the shielding flask Status of.
Heating and radiological
Shielding Design for LCLS Injector Operation – Phase one
Induced-activity experiment:
S. Roesler (on behalf of DGS-RP)
The BLAIRR Irradiation Facility Hybrid Spallation Target Optimization
Measurements and FLUKA Simulations of Bismuth and Aluminum Activation at the CERN Shielding Benchmark Facility(CSBF) E. Iliopoulou, R. Froeschl, M. Brugger,
Studies on Energy Deposition and Radiation for the 4horn system
Radiation protection of Linac4 M. Silari Radiation Protection Group
PROGRESS REPORT OF A NLNS-FFAG ADS MAGNET
M. Calviani, A. Ferrari (EN/STI), P. Sala (INFN)
Fassò, N. Nakao, H. Vincke Aug. 2, 2005
Monte Carlo simulations for the ODIN shielding at ESS
Operations Section Leader
MAGiC Shielding Simulations
Radiation fields During 1st stage beam commissioning
Presentation transcript:

Status of Radiation Protection Studies for the Linac4 beam dumps Joachim Vollaire DGS/RP

Outline  List of beam dumps for L4 commissioning and operation  Shielding for12 MeV beam dump  Shielding and strategy for 50 – 100 MeV dump  Status of main dump shielding analysis (160 MeV)  Status of LBS/LBE dumps shielding analysis  Conclusions EDMS L4 BCC meeting # 31, 24/22/2011

List of beam dumps for Linac4 EDMS L4 BCC meeting # 31, 24/22/20113  Temporary beam dumps for commissioning at different energies (12 MeV, 50 MeV and 100 MeV)  Main dump shielding with new layout and operational scenario (160 MeV)  LBS and LBE dumps (160 MeV) in the L4 transfer line (commissioning and measurements)

12 MeV beam dumps EDMS L4 BCC meeting # 31, 24/22/20114  12 MeV beam (proton instead of H - )  Average current 6.5  A (4.05x10 13 p.s -1 )  Operational scenario (4 weeks  A (4.06e13 pps) Beam

Residual dose rate 12 MeV beam dump EDMS L4 BCC meeting # 31, 24/22/ mn cooling time 1h cooling time1day cooling time

50 MeV – 100 MeV beam dump EDMS L4 BCC meeting # 31, 24/22/20116  Re-location of the beam dump from the 50 MeV to the 100 MeV area  Move the dump with part of its shielding to limit personnel exposure  Best shielding material : lowest residual dose rate and activation of the surrounding structures  Operational scenario:  1 Month of 800 W/1.6 kW for 50 / 100 MeV

Geometry and studied configurations (I) EDMS L4 BCC meeting # 31, 24/22/20117  Shielding on a “Table”  Concrete bricks below the table (prevent tunnel activation)  Shielding on table would move with the dump…

Geometry and studied configurations (II) EDMS L4 BCC meeting # 31, 24/22/20118  Steel (iron) good for high energy neutrons  Borated poly. (5 %) high thermal neutron capture cross section  Marble low activation, “shield” the shielding Shielding 1Shielding 2Shielding 3 Configuration 1SteelConcreteMarble Configuration 2SteelBorated Poly.Marble Configuration 3Concrete Marble Configuration 4SteelConcrete Configuration 5Borated Poly. Marble Configuration 6Steel Marble Configuration 7SteelMarble

Neutron spectra out of the shielding EDMS L4 BCC meeting # 31, 24/22/20119  Configuration 2 leads to the lowest number of neutrons escaping the shielding  To confirm it is a good shielding looking at residual dose rate around the beam dump

Example residual dose rate (8 h cooling) EDMS S1S2S3 C.1SSCOMB C.2SSBPMB C.3CO MB C.4SSCO C.5BP MB C.6SS MB C7SSMB Configuration 1Configuration 2 Configuration 3Configuration 4 50 MeV commissioning

Example residual dose rate (8 h cooling) EDMS Meeting, Date11 S1S2S3 C.1SSCOMB C.2SSBPMB C.3CO MB C.4SSCO C.5BP MB C.6SS MB C7SSMB Configuration 5Configuration 6 Configuration 7 50 MeV commissioning

Example residual dose rate (1 Week cooling) EDMS Meeting, Date12 S1S2S3 C.1SSCOMB C.2SSBPMB C.3CO MB C.4SSCO C.5BP MB C.6SS MB C7SSMB Configuration 1Configuration 2 Configuration 3Configuration 4 50 MeV commissioning

Example residual dose rate (1 Week cooling) EDMS L4 BCC meeting # 31, 24/22/ S1S2S3 C.1SSCOMB C.2SSBPMB C.3CO MB C.4SSCO C.5BP MB C.6SS MB C7SSMB Configuration 5Configuration 6 Configuration 7 50 MeV commissioning

Example residual dose rate (8 h cooling) EDMS L4 BCC meeting # 31, 24/22/ S1S2S3 C.1SSCOMB C.2SSBPMB C.3CO MB C.4SSCO C.5BP MB C.6SS MB C7SSMB Configuration 1 Horizontal cut Configuration 2 Horizontal cut Configuration 3 Horizontal cut Configuration 4 Horizontal cut 50 MeV commissioning

Example residual dose rate (8 h cooling) EDMS L4 BCC meeting # 31, 24/22/ S1S2S3 C.1SSCOMB C.2SSBPMB C.3CO MB C.4SSCO C.5BP MB C.6SS MB C7SSMB Configuration 5 Horizontal cut Configuration 6 Horizontal cut Configuration 7 Horizontal cut 50 MeV commissioning

Residual dose rate profile (1 day – 1 week) EDMS L4 BCC meeting # 31, 24/22/201116

Residual dose rate profile (1 day – 1 week) EDMS L4 BCC meeting # 31, 24/22/201117

Conclusions on shielding comparison EDMS L4 BCC meeting # 31, 24/22/ Configuration 2 best combination for short cooling times Weight ~ 5000 kg

Examples of use of Borated Poly and marble EDMS L4 BCC meeting # 31, 24/22/201119

Dose rate during transport EDMS L4 BCC meeting # 31, 24/22/  Low after week of cooling.  Quick disconnection + shielding (lead) to “plug” the opening in the shielding

Dose rate after 100 MeV run EDMS L4 BCC meeting # 31, 24/22/ MeV + 1 week CT 1 50 MeV + 1 week CT

Status of main dump study EDMS L4 BCC meeting # 31, 24/22/  New operational scenario and core design  New fellow since 01/10/2011 (Jan Blaha) working on dump shielding CoreCore + shielding (SS/BP/MB)

Some preliminary results available EDMS L4 BCC meeting # 31, 24/22/201123

Contact with RP colleagues in JPARC EDMS L4 BCC meeting # 31, 24/22/ M. Vretenar Chamonix

Status of LBE/LBS beam dumps EDMS L4 BCC meeting # 31, 24/22/ Gallery and adjacent building Access from Booster side Work carried out by H. Richter

Prompt dose calculations EDMS L4 BCC meeting # 31, 24/22/201126

Residual dose rate calculation and optimization EDMS L4 BCC meeting # 31, 24/22/ Residual H*(10)-rate [µSv/h] after commissioning ( 1h ) No optimization1 m deep dumpMarble plate Report being written

Conclusions EDMS L4 BCC meeting # 31, 24/22/  Good progress for the commissioning dumps (12 / 50 / 100 MeV)  Main dump shielding still to be specified (assuming 1 core for the entire lifetime of the facility for the time being ?)  LBS dump study being documented.  LBE study to be performed….