Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed.

Slides:



Advertisements
Similar presentations
André Augustinus 16 June 2003 DCS Workshop Safety.
Advertisements

CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
Experimental Area Meeting V. Bobillier1 Good connection to earth (in many points) of every metallic parts to be installed in the cavern is very.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
Paolo Guglielmini TS / CV / DC08th April 2005 BIDDERS’ CONFERENCE Invitation to Tender 3307 Supply and Installation of water cooling equipment for the.
Point 5 - Cooling Network - Key Primary Water Chilled Water Mixed Water Eau Bruite Standard Power Diesel Backup Comp Air Primary Water at 20-25C – Produced.
May Exp-Area meeting1 Safety Systems Installation status Flammable Gas Detection System Fire Detection System in SG8 ODH Detection System CO2 Detection.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
JPV, TB of Nov.15 th, ‘Rack Status‘ Jean-Pierre Vanuxem, PH-AIS.
European Organization for Nuclear Research - Organisation européenne pour la recherche nucléaire 1CERN - 4th November 2011 Experience from Construction.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
Bulding 245 schedule update LIU Booster Meeting Fulvio Boattini & Michel Obrecht TE-EPC / EN-CV TEEPC.
ALICE Collaboration Meeting Heidelberg Services Update  Progress on services Detector cabling Gas systems Cooling systems  Rack footprint  Primary electrical.
D. Gasser ST/CV 1 Fluid distribution from UW85 Fully available now.
Associated detection/extinction systems D. Swoboda.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
DSS  Informal review Tuesday 24 th October 10:00 Room , organized by Laurent Roy.  Subsystems will not be allowed to run overnight or at weekends.
EN-CV interventions during YETS
LHCb Experimental Area Meeting V. Bobillier1 Earth network in UX85 experimental cavern.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
Update on the Laser Beam Line
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
PHENIX WEEKLY PLANNING 11/2/06 Don Lynch. 11/2/06 Weekly Planning Meeting 2 New Detectors TOF West HBD RXNP MPC North.
5 th May 20061M. Battistin CERN LEAF Committee 2/R-030 8h30 - May 5 th 2006 Michele Battistin (TS/CV/DC) TS M&O agreement for Detector Cooling installations.
Upgrade projects and APT update DT-LHCb coordination meeting 28 September 2015.
Expt. Area meeting – December V. Bobillier1 Cabling installation status.
CMS Pixels upgrade CO2 cooling transfer lines Draft spec – for introduction Paola Tropea & Hans Postema 5 December 2012.
GROUNDING, SHIELDING & COOLING ISSUES ON LHCb ELECTRONICS AT THE LHC PIT 8 V.Bobillier, J.Christiansen, G.Corti, D.Lacarrère, R.Lindner, L.Roy, E.Thomas,
V. Bobillier1 Cable installation status.
Gas System Construction Status Oct FH. General Construction is proceeding well, (nearly on-schedule). Testing of Racks is longer than foreseen Testing.
March 12 th 2013 Muon LS1 operation meeting1 Muon LS1 Status Outline Recap of last week P1 weekly schedule Muon related activities Open issues and discussions.
Reviewers report of the LHCb C0 2 cooling EDR EDR date: 3 rd of December January
LHCb Install Meeting - 12 / 05 / 2004 Paolo Guglielmini - TS / CV LHCb Cooling of the sub – detectors INNER TRACKER TRACKER TRIGGER RICH 1 RICH 2 Status.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
Power, Cooling, Cables, Simulations of Heat Dissipation Short overview of ongoing work on these points Technical Coordination (Rolf Lindner et al.) Cooling.
Thermosiphon Project for ATLAS ID C 3 F 8 Evaporative Cooling - Status Report ATLAS ID Week CERN – Geneva October 28 th, 2013 M. Battistin & all TS team.
The (prototype) C&V Framework component used for the SPD Cooling Control A.Tauro, G.De Cataldo.
LHCb Week 27/11-01/ D.LACARRERE on behalf of Expt Area Team1 Experimental Area Latest News from IP8  Radiation Shield – Upper & Front Parts  Structures.
N-TOF review HVAC and cooling systems Proposal to be validated by the project CERN TS/CV 13th February 2008.
110 th November 2010EN/CV/DC Detector Cooling Project - advancement status of Work Package N3 Thermosiphon project Michele Battistin 18 May 2011.
CALO News Pascal Perret LPC Clermont 22 January 2012.
1. Road to the EDR 2 Requirements Safety system Transfer line concept Plant concept design Requirements Evaporator concept and performance Transfer line.
LHCb CO 2 cooling meeting Burkhard Schmidt – May 20,
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
1 04 April 2007 L. Roy Detector Safety System for infrastructure - General fire detection (barracks, cavern) - Sniffer system (smoke detection above the.
Laser Line work package (WP6) AWAKE Technical Board meeting 19 May 2014.
David BAILLEUX On behalf of the Caltech group Issues for the Laser Monitoring System M&O - US CMS ECAL IB meeting 19 March Chilled water supply.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 24/05/2006 LHCb - Install Meeting 24/05/06 TS/CV/DC activities for LHCb: - IT, TT, OT & SPD/PS, RICH.
CO 2 Cooling Plants for the LHCb upgrade LHCb infrastructure workshop February Burkhard Schmidt With input from Bart Verlaat, Paolo Petagna and Lukasz.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/14.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/02/04.
Update on the PSB Cooling and Ventilation Systems
Demineralised water cooling system
EN-CV activities for LHC during LS2
Cabling for LHCb Upgrade
CMS Area Working Group Meeting
Forum on Tracking Detector Mechanics - Bonn, May 2016
LHC Experimental Vacuum Systems Status October ‘07
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
LHCb & EYETS
Status of the cryogenic system for B180
Installation XFEL Tunnel WP 34
Aziz AMAMOU EACM – 21th May 2019
LINAC 3 Meeting ICL machines Injectors
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed water to counting houses 2.cooling station transfer lines 3.stations construction Future works 4. VELO concentric lines construction 5. rack cooling and fire extinction network

1. Primary systems around barracks CRIOTEC -installation of pneumatic lines and actuators finished (cabling to valves and control components from DSS) -pressure tests performed successfully (one leak detected, connection repaired) -not fully tight valve changed today, system ready for operation, commissioning to TS/CV/OP asap Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005

2. DC stations transfer lines under construction INEO ALPES -transfer lines for IT, TT, OT, RICH stations under construction, to be finished in week 43 (before the 28 th ) -piping to IT/TT safety chiller to be soon designed and installed according to same schedule -on LHCb demand: isolation valves on four lines installed on RB84 side, bypass dismantled on same side, brackets near to barracks stairs on RB86 modified -cavern wall on RB86 to be tidied up for pipes installation (neon light, cables)

3. DC stations construction INEO ALPES Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005

4. VELO concentric lines construction SIMIND Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 -schedule: beginning Nov 28 th or Dec 05 th duration 10 working days -preliminary yard visit on 14/10 -PPSPS drawing up ongoing -requests to LHCb: crane truck with operator, 2/3 nights for pressure tests (pneumatic, 125 bar)

5. Rack cooling lines at mixed water, fire extinction network, chilled/mixed water pipes modification on RB84 IT to be drawn up Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 Fire prevention lines integration completed, on RB84 spurs almost defined, lines drawing up on RB86 priority. Tests on rack exchangers and Wiener power supplies ongoing (Detraz, Bobillier)

Others Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/ ventilation system for Muon station M1/3 design under definition, ES approval in 3 weeks, TS/CV to supply components, installation from Muon collaboration - CV works required in SX8/R-003 (007, 008) to be defined with F.Levrier - air conditioners maintenance around barracks performed by R.Mollay in week 42