Road map of the workshop Machine availability: – “work-horse” in the injection chain – 100% availability not viable,.What is achievable? And at which cost?

Slides:



Advertisements
Similar presentations
Operations and Availability GG3. Key decisions Summary of Key Decisions for the Baseline Design The linac will have two parallel tunnels so that the support.
Advertisements

LHC HARDWARE COMMISSIONING REVIEW May 2005 CRYOGENIC VACUUM SYSTEM Paul Cruikshank for AT/VAC.
SPL Integration Layout Impact on cryo and vacuum sectorisation ◊ Underground obstacles, constraints on slope and length of the SPL ◊ Continuous cryostat.
EXPERIENCE FROM KEK Norihito Ohuchi 2009/11/9-101 Workshop on cryogenic and vacuum sectorisations of the SPL.
Report from WG 3: Cryomodules (design & integration, construction, assembly) V.Parma, CERN, TE-MSC With contributions from O.Capatina, CERN, EN-MME 2nd.
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
Question 27: Outline the key steps for industrialization of machine components and the likely remaining vulnerabilities in achieving them. Achieving industrialization.
Large-capacity Helium refrigeration : from state-of-the-art towards FCC reference solutions Francois Millet – March 2015.
CRYOGENICS AND POWERING
SCU Layout Concept - Minimal Segmentation Joel Fuerst (ANL) SCU 3-Lab Review Meeting Dec. 16, 2014.
Accelerators for ADS March 2014 CERN Approach for a reliable cryogenic system T. Junquera (ACS) *Work supported by the EU, FP7 MAX contract number.
Cryomodule Helium Vessel Pressure -- a Few Additional Comments Tom Peterson 18 November 2007.
Workshop on cryogenic and vacuum sectorisations of the SPL CERN, 9 th -10 th November 2009 Workshop Organisation and Goals Vittorio Parma TE-MSC.
Cryogenic Experts Meeting (19 ~ ) Cooling scheme discussion for 300 Tm High Energy Beam Transfer line (HEBT) with large inclination MT/FAIR –
HC review - 12 May 2005Luigi SERIO - AT/ACR/OP1 SECTOR COOL DOWN AND CRYOGENIC COMMISSIONING L. Serio.
Lutz Lilje DESY -MPY- Module Issues XFEL Linac Review R. Lange/L. Lilje Ongoing Tests Module Designs Future tests.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
MICE Target - Risk Lara Howlett University of Sheffield.
05 Novembre 2003Chamonix XIV Workshop, January How to deal with leaks in the QRL and magnet insulation vacuum Paul Cruikshank for AT/VAC Germana.
Americas Region: T4CM Status and Plans H. Carter TD SRF Dev. Dept. July 14, 2006.
Beijing ILC Workshop Global Design Effort 1 High-Gradient Module Test Lutz Lilje.
Experience with LEP (and LHC) cryo-modules Workshop on cryogenic and vacuum sectorisations of the SPL O.Brunner – November ’09.
Test plan for SPL short cryomodule O. Brunner, W. Weingarten WW 1SPL cryo-module meeting 19 October 2010.
1 Update on Q2 Main linac starting gradient, upgrade gradient, and upgrade path Results of WG5 discussions after feedback from plenary on Tuesday New Option.
Status of the SPL cryo-module development (report from WG3) V.Parma, TE-MSC (with contributions from WG3 members)
Project X RD&D Plan Cryogenics Arkadiy Klebaner AAC Meeting February 3, 2009.
Thomas Jefferson National Accelerator Facility Page 1 SPL Cryogenic and vacuum sectorisations 9-10 November, 2009 Joe Preble Workshop on cryogenic and.
C.KotnigFCC Design Meeting FCC Beam Screen cooling Claudio Kotnig.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
30 May 2007 DESY Cryomodule Discussion 1 Type 4 Cryomodule Technical Discussion Tom Peterson Compiled from various previous meeting notes and many sources.
Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel.
Eric Prebys/LARP 2/17/2016.  CERN has taken unprecedented steps to control information about this event, including altering the electronic LHC log to.
Carlo Pagani University of Milano INFN Milano-LASA & GDE ILC and XFEL Cryomodules Preliminary thoughts for convergence ILC EDR Kick-off Meeting DESY,
Cryostat & LHC Tunnel Slava Yakovlev on behalf of the FNAL team: Nikolay Solyak, Tom Peterson, Ivan Gonin, and Timergali Khabibouline The 6 th LHC-CC webex.
SLHC WG3 (Cryomodule) summary & plan with recommendation to the CB V.Parma, CERN TE-MSC P. DUTHIL, IN2P3-CNRS 3rd SPL collaboration meeting, CERN
Dimensions, pressures and temperatures of cryogenic circuits for the SPL U. Wagner TE-CRG.
The integration of 420 m detectors into the LHC
LHC Cryostat evaluation Nikolay Solyak Thanks Rama Calaga, Tom Peterson, Slava Yakovlev, Ivan Gonin C11 workshop. FNAL, Oct 27-28, 2008.
Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)
TE-CRG Activities D. Delikaris, TE-CRG.
Cryogenic Cooling Schemes for the SPL U. Wagner TE-CRG.
Cryogenic scheme, pipes and valves dimensions U.Wagner CERN TE-CRG.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
SPL cryomodule specification meeting, CERN 19th October 2010 SPL cryomodule specification: Goals of the meeting SPL cryomodule specification: Goals of.
The SPL Short Cryo-module: Status Report V.Parma, CERN, TE-MSC On bahalf of the Cryomodule development team SPL seminar December 2012, 6-7 December 2012,
ESS Cryomodule Status Meeting – Elements of Safety | | Christine Darve Elements of Safety Applicable to the ESS 2013 January, 9 th Christine.
Mu2e Mu2e Remote Handling Review Comparisons: Costs, Risks & Maintainability Ryan Schultz Deputy L3 Manager Target Station 3/3/2015.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Reliability of SNS Superconducting Linac April 12, 2011 Jeff Saunders SNS/ORNL.
Project X Workshop - Cryogenics1 Project X CRYOGENICS Arkadiy Klebaner.
Low Beta Cryomodule Development at Fermilab Tom Nicol March 2, 2011.
Cryogenics for SuperB IR Magnets J. G. Weisend II SLAC National Accelerator Lab.
Workshop on cryogenic & vacuum sectorisation of the SPL Vacuum Sectorisation Paul Cruikshank, CERN Technology Department (TE) Vacuum Surfaces & Coatings.
ILC : Type IV Cryomodule Design Meeting Main cryogenic issues, L. Tavian, AT-ACR C ryostat issues, V.Parma, AT-CRI CERN, January 2006.
Tests on production cryomodules Bob Kephart Sept 30, 2006.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
Cavities, Cryomodules, and Cryogenics Working Group 2 Summary Report Mark Champion, Sang-ho Kim Project X Collaboration Meeting April 12-14, 2011.
SRF Operating Experience at JLab
H. Hayano(KEK), B. Petersen(DESY), T. Peterson(FNAL),
SPL RF coupler: integration aspects
Cryomodule test stand at ESS site
WP5 Elliptical cavities
Installation of an Instrument on a CERN machine
Project X: Cryogenic Segmentation Issues
Second SPL Collaboration Meeting, Vancouver May 2009
The LHC - Status Is COLD Is almost fully commissioned
Consequences of warming-up a sector above 80 K
XFEL Vacuum System Commissioning
SNS Operational History
Regular cryomodule maintenance plans (radiation damage, seals, etc)
Presentation transcript:

Road map of the workshop Machine availability: – “work-horse” in the injection chain – 100% availability not viable,.What is achievable? And at which cost? Reliability of built-in components and operational risks (degraded performance without intervention) – Typical faults expected on: Cavities Couplers Tuners.. Operation with degraded performance and mitigating measures: – Degraded performance of cavity/ies  reduced energy – Degraded optics (quads, steerers)  reduced beam quality – Operating with leaks –... Built-in redundancy (e.g. need for installed spare cryo-modules) Maintainability: – Radioactive cool-down time – Warm-up/cool-down. Time and reliability. Need for partial or complete warm-up of strings to replace built-in components or even one cryo-module – Accessability of components for regular maintenance or repair Design complexity of compared solutions Operational complexity (e.g.cryogenics with 1.7% slope) Installation and commissioning Coping with incidents (MCI). Loss of beam and/or insulation vacuum : – helium leaks – Air leaks Cost differences between options - … V.Parma, Introductory talk

Goals Primary goals: – Identify the main operational and intervention scenarios for the cryogenics and vacuum systems of the SPL – Elaborate an exhaustive technical and economical comparison between single “continuous” cryostat and “segmented” cryostat with cryo distribution line – Possibly reccomend a choice between the two options – Define a “baseline” cryogenic distributions scheme and vacuum sectorisation – Elaborate, if necessary, a list of further developments for making a choice Other goals: – Identify advantages for alternative sectorisation schemes (intermediate solutions) – Technical comparison between layouts with warm and cold magnets – Identify other machine architectures to be explored for an improved sectorisation (e.g. alternative optic schemes) V.Parma, Introductory talk

Preliminary conclusions (V.Parma, S.Calatroni) More doors opened than closed!...but Lots of precious information made avaialble: thank you to the speakers! SPL availability. Needs to be “as high as possible”, so down-time should be minimised. Replacement of a cryomodule is a matter of several weeks in a continuous machine and could be a matter of a couple of weeks with a full segmentation (to be properly assessed!) Which components are most likely to fail (or have degraded operation): – Cavities. Degraded performance after installation experienced at FLASH, but no degradation from operation. Within certain limits can be compensated by better performing cavities or by in-situ reconditioning (e.g.LEP)  But built-in cavity redundancy is probably needed. – Tuner motor and piezos remain sensitive components. KEK moved motor outside cryostat. – Power coupler. For HP SPL 1 ceramic window, risk of leak. Risk of leak on coupler window to be explored. Interlocked gate valves would be very useful – Cold feed-throughs (better avoid, FNAL, JLAB) – Cold seals sensitive (Indium, JLAB) – Gate Valves (operational accident. e.g. LEP) – Leaks due to thermal cycles Quad reliability and alignment. Magnets do not need to be warm. (But warm zones may complicate the beam vacuum (bake-out)). Warm quads. SPL Low beta zone with warm magnets gets long as compared to Isolde extraction needs (energy) but this is not considered today as a constraint. A fully segmented with warm magnets solution would not have margin for 5 GeV, with 25 MV/m. Continuous solutions gives some margin for ~20% (?) redundant cavities. SPL operational scenario – No components needing regular servicing – Maintenance only during yearly shut-downs (3 months for LHC).

Preliminary conclusions (cont.d) Segmentation in other machines. – Long (>1 km) machines tend to reduce segmentation for cost reasons (ILC study, XFEL project) – Shorter machines normally have segmentation (SNS, Cebaf) SPL: “to segment or not to segment?” – Advantages of Seperate distribution line are clear. Mainly: maintenance flexibility, installation and commisionning. Magnets can be warm  simpler cryomodules, more reliable/maintainable...but: – Drawbacks: too long machine to house redundant cavities (cryomodules)? Cryogenics cooling schemes: Many options (7) for cooling schemes presented. Cool-down/warm-up through “parallel” capillary circuit (XFEL concept) seems to work but not preferred by CERN (Udo). To be further discussed with XFEL people. (Bernd). “Roman fountains” operation (possibly with capillary levelling from bottom of cavities) could work but testing is highly recommended (no existing experience). Other concepts could also be explored (e.g. Horizontal bi-phase tube). Possiible lenght of cooling loop to be further investigated Warm-up and cool-down time in case of XFEL is limited by “banana effect” due to the GRP. (~1 week). On short segments it could be much faster and becomes a matter of capacity (~)... Choice of cooling scheme needs further work.

Preliminary conclusions (cont.d) Vacuum. Machine availability – Define ability to live at reduced performance, with degraded components, or some non operating component Leaks on insulation vacuum Vacuum issues in beam - cavities (Magnets) – Redundancy Beam vacuum segmentation. Interlocked gatevalves can limit contamination of leaks or accidental venting. XFEL is planning to install cold gatevalves (specifically developed). XFEL experiment. Air venting in beam tube has quite slow propagation (~4 s per module), so “slow” gate valves can manage it. Insulation vacuum. No major point. Introduce vacuum barriers to have reasonably short cryostat segments (ease commisioning, leak localisation...) Design, installation, commissioning, operation and repair criteria all discussed (Paul): Increased segmentation: – Installation and operation flexibility, maintainability in case of major faults, safety due to gate valves – Increased number of components, reduced reliability Reduced (no) segmentation: – Maximization of real estate, simplification of components and built-in redundancy – Limited in-situ intervention in case of failures, and larger affected zones

Preliminary conclusions (cont.d) Lots of analysis of presented information still to be done...Give us some time! Final report will be produced in the coming weeks with a thorough comparison between continuous and segmented versions. Thank you for your participation !