AMS-02 tracker mechanics status of construction, assembly, integration Ladder assembly Ladder installation on planes Integration details, cooling loop,

Slides:



Advertisements
Similar presentations
Lyon Gantry Status TEC meeting Dec D. Contardo Module production in Lyon Rigidifier test on R4 Frame tolerance effect on assembly plates Short term.
Advertisements

Manchester 09/sept/2008A.Falou & P.Cornebise {LAL-Orsay}1 CALICE Meeting/ Manchester Sept 2008 SLAB Integration & Thermal Measurements.
Technical Board, 12 July 2005Børge Svane Nielsen, NBI1 Status of the FMD Børge Svane Nielsen Niels Bohr Institute.
Mech Systems Proposed EMI Modifications Marc Campell 9/2/03.
AMS-02 Cryosystem Phase III Flight Safety Review January 12, 2010 Phil Mott.
THERMO-MECHANICAL TESTS ON TRACKER LADDERS (Low temperature problem on plane 1) Status Report: D.Rapin Sept 26,2012 (help from Giovanni, Franck, Mingming,...)
J. H. ChrzanowskiNSTX TF Flag Joint Design Review1 NSTX TF Flag Joint Design Review Fabrication and Assembly April 10, 2003 By: James H. Chrzanowski.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
AMS-02 tracker mechanics status of assembly and integration Inner tracker integration completion: - Assembly and cabling - Temperature and magnetic field.
AMS tracker hardware status (mechanics and cabling) Divic RAPIN, UniGe AMS splinter tracker, Septidi 7 Brumaire 217 (october 28, 2008) off-line operations.
AMS-02 tracker mechanics status of construction, assembly, integration Production: - Ladder integration - Installation on planes Inner tracker assembly:
The AMS-02 detector is based on a large acceptance (~0.5 m²sr) and high sensitivity spectrometer composed by a super-conducting magnet (0.8 T), cooled.
GLAST I&T January T Borden 1 Tracker EM Mechanical Mock-up T Borden I&T Tracker Mock-up.
The LHCb Inner Tracker LHCb: is a single-arm forward spectrometer dedicated to B-physics acceptance: (250)mrad: The Outer Tracker: covers the large.
Walls crates cables gas chambers electronics CERN adb.
HFT PXL Mechanical July 2010 Howard Wieman LBNL 1.
S Temple CLRC1 End-cap Mechanics FDR Cooling Structures Steve Temple, RAL 1 November 2001.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
M. Gilchriese Status Report Sectors, Rings, Frame December 2002.
AMS Cabling CERN Prevessin 893-1D020 December 6, 2006 Agenda 1) Brief overview -Show Plumbing and VC ring-mounted-hardware -AMS overall -Common.
1 AMS-02 Integration & Test Plans & Status Trent Martin 24 January, 2007.
Update on alignment kit and stave 250 frame M.Gibson (RAL) 1.
26 April 2013 Immanuel Gfall (HEPHY Vienna) Belle II SVD Overview.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 5.1 Grid Box Design 1 GLAST Large Area Telescope:
Tracker Thermal Control System 1 AMS Tracker Thermal Control System (TTCS) Phase II Safety Presentation SRII meeting, 21 May 2007, Houston Johannes van.
Overview of AMS-02 Changes due the addition of the Permanent Magnet
24 January 2014 LARP VTF Follow-up Meeting P. Kovach VTF 1 LARP Vertical Test Facility Vertical Dewar Design, Magnet Prep And Installation Paul Kovach.
L. Greiner 1IPHC meeting – May 7, 2012 STAR HFT Plans for the next year A short report on HFT/PXL plans for post May 2012 TPC – Time Projection Chamber.
Design Progress Allen Ellis 18-September
G.Barber KEK Test Beam Update, Berkeley 9 Feb KEK Test Beam – Tracker Progress Contents:- Station Space Frame Light Guide Map Station Connectors.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l History l Requirements l Environment l Design l Structural Integrity l Preparation l.
Design Discussion of Mechanical / Electrical Interfaces Bill Cooper (Fermilab) (Layer 1) VXD.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
Mechatronics Task Force, 26-nov-02 Olivier Teller, CERN EP-CMA1 Cooling Mechatronics Schedule.
Neil JacksonUK-V RAL 8th September Module to Disc Assembly Infrastructure –Services and test box –Evaporative cooling system –Disc Handling Tests.
1 HBD update Itzhak Tserruya DC Upgrades meeting, January 14, 2005 NIM paper II: Generic R&D ~ completed Full scale prototype construction Pending issues.
Chiho Wang Duke University 1 TRT Barrel integration Status / Schedule Chiho Wang.
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
SVD Mechanics Markus Friedl (HEPHY Vienna) BPAC, 26 October 2015.
Neil Jackson University of Liverpool Hiroshima Symposium June THE ATLAS SEMICONDUCTOR TRACKER (SCT) A PRESENTATION ON BEHALF OF THE ATLAS.
1 PFDPU Mechanical Packaging PEER REVIEW MAVEN PFDPU Particle and Fields Data Processing Unit Mechanical Packaging and Design Overview May 09, 2011 Bill.
ATLAS Pixel Detector July 2003 SC Pixel Meeting N. Hartman LBNL 1 Pixel Support Tube WBS Santa Cruz Cost Workshop July 9, 2003.
ATLAS Pixel Detector September 2002 N. Hartman LBNL 1 Pixel Support Tube: Cost and Production Schedule September 2002.
Walter Sondheim 6/9/20081 DOE – Review of VTX upgrade detector for PHENIX Mechanics: Walter Sondheim - LANL.
CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling,
PHASE II FLIGHT-SAFETY REVIEW AMS-02 EXPERIMENT sub-detector SILICON TRACKER Roberto Battiston - AMS-02 Phase II Safety Review - Houston JSC May 21-25,
Vessel dimensions GTK assembly carrier Electrical connections Cooling pipes integration Vessel alignment with the beam Next steps Conclusion 3/23/20102electro-mechanical.
AMS Tracker Meeting31/01/06 Eric Perrin (GE) on behalf of the Tracker group Tracker mechanics at Uni -Ge Safety issues Assembly Still to be made.
DON LYNCH NOVEMBER 6, AGENDA November 4, BABAR Magnet Update Global Design Concept – Update Outer HCal Structural Analysis (2 nd pass) sPHENIX.
MQXFB design, assembly plans & tooling at CERN J.C Perez On behalf of MQXF collaboration team MQXF Workshop on Structure, Alignment and Electrical QA.
Hybrid and Module Status 1. Hybrid Delivery First hybrids over-etched and shrunk due to changes in design and mistakes in manufacturing – Shrinkage for.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 5.3 Fab & Assy Plans 1 GLAST Large Area Telescope:
Beampipe Installation Status Ray Veness For the Beampipe team in AT/VAC and TS-MME.
AMS Tracker Meeting17/10/05 Eric Perrin (GE) Tracker mechanics at Uni -Ge Safety issues Assembly Still to be made.
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
News on Mechanical Design Dirk Wiedner July /4/20121Dirk Wiedner Mu3e meeting Zurich.
MICE RF Coupler Modifications Update 4/30/2015 Allan DeMello.
24 September 2012 Immanuel Gfall (HEPHY Vienna) SVD Status of Mechanics PXD-SVD Meeting Göttingen.
24 September 2012 Immanuel Gfall (HEPHY Vienna) Annekathrin Frankenberger (HEPHY Vienna) SVD Status of Mechanics PXD-SVD Meeting Göttingen.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
Panda Solenoid Content Interface Box Cold Mass Layout Cooling Lines
Baby-MIND Modules & Services
Update on PANDA solenoid design
Service channels between Tracker and PP1
Service channels between Tracker and PP1
Ladder Assembly All tools and jigs produced Glue dispensing works
LARP Vertical Test Facility
PXD Summary Tests PXD9 Pilot Production ASICs Components Plans:
UPPSALA UNIVERSITY_GERSEMI PROJECT
Presentation transcript:

AMS-02 tracker mechanics status of construction, assembly, integration Ladder assembly Ladder installation on planes Integration details, cooling loop, star tracker Safety issues Tracker assembly Schedule Divic RAPIN, UniGe Summary of contributions from: M. Paniccia, M. Ionica, F. Da Silva, E. Perrin, B. Verlaat, C. Gargulio

General view of Silicon tracker 5 planes, 8 layers Plane 1, layer 1 Plane 2, layers 2&3 Plane 3, layers 4&5 Plane 4, layers 6&7 Plane 5, layer ladder modules

Ladder Assembly Status (Perugia-Geneva) ASSEMBLY ~ 200 ladders build 1 ladder still to be assembled 4 ladders to be repaired PHASE 2 hybrid box & legs gluing ~ 7 ready for process EMI SHIELDING ( kapton foil wrapping) ~ 38 ready for processs Full test at each step with RA source and noise control

Installation of ladders on support planes Ladders are installed on both sides of the 3 inner planes. 5 over 6 layers are fully equipped with ladders Inner part of the tracker soon completed. Ladders on plane 4

Installation of ladders on support planes Plane 3 being stored (under Nitrogen) Details of fixation on both sides

AMS-02 Tracker - Plane 2 July 21, 2005 Ready To be Integrate Integrated L07PI002 L09GI006 L14AI031 L09GI003 L10PI005 L10GI014 L11GI004 L11GI009 L11GI016 L09GI013 L09GI010 L14AI042 L07PI004 L11GI008 L12AI001 L12AI004 L12AI006 L12AI003 L12AI005 L12AH024 L12AH057 L12AH029 L12AJ021 L12AJ051 L10PI008 L14AI044 L12AJ054 L12AJ055 L10PI001 L09GI002 L11AI126 L11AI140 L12AJ033 L11SI176 L12SH169 L12AH058 L14AI032 L09AI139 L09GI011 L11AI127 L09SI164 L12AI012 L12SI167 L12AJ038 L12SI182 L12AI016 Before phase 2 at Perugia Last inner layer close to completion

Installation of ladders on support planes Thermal bars installed on external planes

AMS-02 Tracker - Plane 5 July 19, 2005 ON PHASE-2 READY TO BE SHIELDED ASSEMBLY COMPLETED L10AO144 L15AN117 L12AO105 L10AO147 L14AO119 L13AO074 L13AO073 L15AP112 L15AP098 L15AP110 L15AN118 L14AO120 L15AO093 L15AO097 L15AO095 L14AO122 L14AO124 L13AO111 L12AO106 L10AO148 L10AO145 L14AO157 L14AO121 L13AO072 L11AO155 L15AO116 L15AO162 L15AO115 L15AO096 L11SO165

AMS-02 Tracker - Plane 1 July 21, 2005 ON PHASE-2 READY TO BE SHIELDED ASSEMBLY COMPLETED L12AO107 L15AN100 L15AN101 L13AO114 L15AN113 L10AO146 L10AO150 L13AO025 L14AO160 L15AP099 L15AP109 L13AO026 L14AO158 L15AO173 L15AO174 L15AO175 L13AO071 L14AO159 L14AO156 L14AO123 L14AO125 L15AO163 L11AO153 L10AO151 L10AO149 L12SO181 L15SO180 L15AO17 7 L11AO15 4 L15SO178 ON PRODUCTION STAND BY ON REPARATION

TTCS Evaporator Production Status B. Verlaat & M. Van Overbeek NIKHEF, 14 October 2005

Evaporator is split with hydraulic connectors Inner ring Outer ring Intermediate Connectors In & Outlet Connectors

July 2005: 2 Inner rings are produced!

Inner ring under production Bending tool details Soldering set-up

Inner ring production results Copper block details Complete inner ring

Outer Ring Assembly and soldering jig Outer Ring Details Outer ring under production

Evaporator clamps in Tracker structure Inlet and outlet tube clamp Inner ring central clamp

1) Bolt analysis was made by ISAtec and A.Alvino. ==> We need better quality bolts for some cases: One junction (tracker feet  tracker) deserves more attention and will be discussed on Wednesday splinter meeting. 2) Tracker fastener list and back off prevention method: Submitted to Jacobs. Update needed for structural fasteners. Back-off prevention clear - Two cases: i) Contained small fasteners : Vibratite ii) Other fasteners: Mylar patch or self locking insert 3) Fracture of composites: Memo submitted to Jacobs. 4) Material list: Delivered to Jacobs Some issues: - Some Al alloy plates to be surface treated in-situ - A few components are prone to stress corrosion Safety issues

Dry assembly of shells-planes was made before installation of ladders on planes. …it continues with the new conical flange and the external planes… Tracker assembly at Uni-GE

Dry assembly continues: - Star tracker lower support to upper conical flange. - P1 to top conical flange - P5 to bottom conical flange. - Spl brackets for evaporators

Dry assembly continues: -Star tracker lower support to upper conical flange. -Two pieces of the camera support to upper plane and upper flange

Assembly of the inner tracker at UniGe Proposed set-up for storage & insertion into the magnet. The various lengths of the cables were calculated. Cables are in UniGe Cables must be installed before the supporting shells. Extra length must be attached to temporary supports.

Tracker assembly at Uni-GE Modifications can start: - Remove / reposition telescopic supports for inner planes. - Build adapters for conical flanges - Define plane transfer method ==> By hand ? ==> With a lifter ? The ETHZ Frankenstein machine has been moved to UniGe

Assembly schedule Inner Tracker assembly can start as soon as : - The three inner planes are ready for assembly  ~End of November Delayed because of a missing ladder - The modifications to Conical flanges / Shell are made (if needed) - The Star Tracker lower supports are bonded to the top conical flange - The fasteners are available Assembly sequence - Transfer the 3 inner planes into the « Frankenstein » in order P2, P3 and P4 - Transfer the conical flanges into the « Frankenstein » - Position planes and connect thermal connectors - Mount cable support structure - Mount and connect cables on ladders of three external rows +Y and -Y - Mount the two 100° shell sectors - Mount and connect all other cables - Mount the two 80° shell sectors Inner Tracker assembly ==> Duration ~2.5 months ~End February2006 if assy starts early December

P5 completed with ladders  ~Mid February 2006 P1 completed with ladders  ~End of March 2006 (Test are not accounted for ) Still a lot of things to finalize / to do for the assembly of the Inner Tracker: - Procure fasteners which need to be replaced - Shopping list for next TIM - Light tightness at exit of conical flange / around the feets - Mesh on light traps - Bond Star tracker lower support - Cable clamps - Structure to support cables - Container for Inner Tracker. - Etc...

Further assembly steps / parts needed - Re-do some bracketry for evaporators in two parts - Mount outer evaporator rings to P1 and P5 - Modify outer plane containers to be compatible with evaporators For integration - Inner Tracker handling gear - Installation jig for Inner evaporator (design A. Alvino) - Cable « paddle » and clamps on Vacuum case (design A. Alvino) - Cable balcony for Tracker crates. Miscellaneous - Prototype condenser - Parts for heat exchanger