Vision for Power Sector: To Ensure reliable & quality power supply to all citizens by 2021 at an affordable price. Vision 2021: To be a Middle-Income Country 2 Vision
3 Power Sector At a glance Electricity Growth: 9 % Generation Capacity: 14,077 MW Total Consumers: 17.8 Million Transmission Line: 9,695 Ckt. km Distribution Line: 3,41,000 km Distribution Loss: % Per Capita Generation: 371 kWh Access to Electricity: 74%
Success story: Last Six years Success story: Last Six years Achievement Power Plants (No) (+) 73 Generation Capacity (MW) 4,94214,077 (+) 9,135 Highest Generation 3,2688,177 (+) 4,909 Per Capita Generation (KWh) (+) 151 Access to Electricity (%) 4774 (+) 27 Consumers (lakh) (+) 70 Transmission Line (Ckt Km) 8,0009,695 (+) 1,695 Distribution Line (Km) 2,60,0003,41,000 (+) 81,000 System Loss (%) (-) 4.9 4
Present Generation: Fuel Mix Present Generation: Fuel Mix 5
Power Generation Addition From Jan’09 to Oct’15 6
Up Coming Generation Projects 7 SlDescriptionProjects (Number) Capacity (MW) 01Under Construction In the Process of Tendering Under Planning Process74685 Total
Year-wise Power Generation Plan for YEAR TOTAL (MW) Public Sector (MW) ,0201,3971,6111,0001, Private Sector (MW) 1, ,1521,8111,9127,673 Total (MW)1,9581,3132,6502,0272,7632,8113,81217,334 8
Power System Master Plan (PSMP) 2010 (PSMP) 2010 Year Target (MW) , , ,000 According to the PSMP-2010 Power generation Capacity targets up to 2030: 9
Bangladesh Transmission System at a Glance 10 Transmission Line: 400kV:165 Circuit Km 230 kV:3172 Circuit Km 132 kV:6359 Circuit Km Substations : MVA HVDC BtB:01 (500MW) 230/132 kV: 16 (8775 MVA) + 2 Nos. Switching 230/132 kV (BPDB & APSCL):2 (550 MVA) 132/33 kV:89 (11568 MVA) 132/33 kV (BPDB, DPDC, DESCO & Others) :20 (2425 MVA)
Power Transmission: Future Plan Power Transmission: Future Plan 11 Voltage (kV)Length (Ckt-km) 13210, , , Total19, 269 Voltage (kV)Capacity (MVA) 13232, , ,970 Total84, 195
Power Distribution: Future Plan Power Distribution: Future Plan 12 Parameters 2015 (At present) Consumers (Mill.) Line Constr (Thou KM) Sub-Station (MVA)24,72035,70066,500 Peak Demand (MW)8,17718,80033,700 Distribution System Loss11.36 %9.50 %8.70 %
Prepaid Metering System 13 Objectives: Upfront payment Decreased non-technical losses Tamper protection Non-allowance of over sanctioned load Better customer services Automated record keeping Create power saving attitude to the consumers Progress: Already 98,000 prepaid meter installed Under pipelines( tendering Process) : 11 lacs Under planning stages: 121 lacs.
ICT Activities 14 Project Monitoring System Monthly Meeting Report System E-filing system Setting Up Video Conferencing System On-line Recruitment System Personnel Information Management System Audit Management System
ICT Activities 15 Online Application for Electricity Connection Bill Payment Through Mobile Phone Bill Pay Through Online Meter Reading Through Snap Shot Bill Payment Through Union Information & Service Centre (UISC) Contact Centre/ Customer Complaint Management System (Under Process )
Renewable Energy At a glance 16 Policy adopted Dedicated institute created Set targets 185 Mega Watt installed 4.0 Million Solar Home System 10% population coverage 3100 Planned by 2021 Wind Resource Assessment at 13 sites 80,000 Bio gas plants installed 5 million ICS sold Going to set Bench Mark Tariff
Energy Savings 17 Use sun light and free air as much as possible Switch off before leaving your room Turn off your electronic device after use Do not use AC, electric iron, water pump during peak hours Use of LED, CFL bulb Avoid un-necessary lighting in the room Limited use of Air Conditioners keeping temperature 25°C & above Use of energy efficient appliances