Beamline Readiness Review - Hutch Beamline Microdiffraction March 28, 2006
Floor Plan, Sector 12 25L760C
Sector 12 superbend beamlines , &
Hutch Assembly Details
Hutch construction drawing from vendor
Wall panel construction 2mm sheet lead 1” thick - 4# mineral wool insulation 14 gauge steel Prior to assembly, interior materials have combined thickness of 52.8mm
After assembly, the interior components have been compressed to 47.6mm from 52.8mm Wall panel construction
Wall panel connection detail
Typical Wall Panel with Pb sheet installed
Panel with second layer of insulation installed
Front wall prior to second layer of insulation Window
2 nd front wall panel with opening for beampipe
Typical wall corner with Pb bent along vertical edge
Different corner with 2 nd layer of insulation
H- channel with Pb captured Pb
Pb visible in all of these H-channel units
bottom side
Pb Framed opening detail – labyrinths, beampipe opening
Labyrinth Pb detail prior to insulation Pb in track prior to steel cap
Labyrinth detail
Labyrinths after Pb shielding applied
Labyrinth with detail of how Pb is doubled over
Overview of back wall construction
1” overlap from Backwall to flashing Roof to back wall connection detail
Back wall Pb overlap detail
Fastening tabs to secure to structural brace Pb overlap Back wall right side
Back wall detail Lead laminated to steel Steel
Back wall detail 2 Lead overlap for next panel
Roof – Wall panel connection