M. Brooks DC Meeting, 15-Sep-00 MuTr Mechanics Status SOUTH ARM: Chambers fabrication complete Stations 2+3 installed Station 1 test-installed will be.

Slides:



Advertisements
Similar presentations
Muon Tracking FEE R.E. Mischke Los Alamos 10 September, 1999 presentation to the PHENIX Muon Arm Technical Advisory Committee.
Advertisements

Walls crates cables gas chambers electronics CERN adb.
MuTr Recap Status and Plan. Plan We are shooting for North Station-1 for post Run10 shutdown installation. Best scenario is to mount portable “clamp”
8/7/2014 PHENIX WEEKLY PLANNING August 7, 2014 Don Lynch 1.
Jon S Kapustinsky 11/17/2010 Jon S Kapustinsky FVTX Commissioning Plan 1.71 Jon S Kapustinsky 1.
M. Brooks April ‘00 Core Week Muon Tracking Status Mechanics Chamber Building Magnet Mods Installation Plans Schedule FEE Preparations for octant test.
 Read out strips production : We will provide 200 strips (100 RE4/2 and 100 RE4/3) Contract with Beijing Gaonengkedi Co. signed on 10-Aug., 3 RE4/2 and.
EE and SE Installation Wolfgang Funk - CERN CMS 11/9/ ) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
Technical Support /26/08 PHENIX WEEKLY PLANNING 10/2/2008 Don Lynch.
1/5/20121 PHENIX WEEKLY PLANNING 1/5/2012 Don Lynch.
8/9/20121 PHENIX WEEKLY PLANNING 8/9/2012 Don Lynch.
DVCS-2 Assembly & Installation Charles Hyde DVCS Collaboration Meeting 18 December 2009 Clermont-Ferrand.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
Hall D Online Meeting 27 June 2008 Fast Electronics R. Chris Cuevas Jefferson Lab Experimental Nuclear Physics Division 12 GeV Trigger System Status Update.
PHENIX WEEKLY PLANNING 4/10/2008 Don Lynch. 04/10/08 Shutdown ’08 Schedule Purge Flammable Gas, Magnet & DAQ TestsDone Remove lock-out & open shield wallDone.
1 MuTRG-FEE Upgrade Status RIKEN/RBRC Itaru Nakagawa.
Progress Completed Order/Fabricate SS Piping for HBD Purge gas from all detectors DAQ tests Prep. for Shutdown work (open doors, move carriages, etc. Pave.
12/29/20121 PHENIX WEEKLY PLANNING 12/29/2011 Don Lynch.
Technical Support /4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
10/13/20111 PHENIX WEEKLY PLANNING 10/13/2011 Don Lynch.
PHENIX WEEKLY PLANNING 10/11/2007 Don Lynch. 10/11/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish MPC South InstallationDoneDone Elec.
Status of and Installation Plan for DC Gas Control System and Target Work Scheduling Meeting 4 August 2006 PSI W. Molzon, Feng Xiao.
1 ME1/1 ODMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project.
Technical Support /21/08 PHENIX WEEKLY PLANNING 8/21/2008 Don Lynch.
1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC.
Technical Support /14/08 PHENIX WEEKLY PLANNING 8/14/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/27/2008 Don Lynch. 3/27/2008 Weekly Planning Meeting2 Shutdown ’08 Schedule CM Crane ReviewMar Purge Flammable Gas, Magnet.
1 CKOV1 at the MICE Experiment CKOV1 to perform mu/pi id w TOF0/TOF1. Progress since CM16 CKOV1 Fabrication and Installation TOF0 CKOV1 TOF1 EMCAL TOF2.
5/1/ PHENIX WEEKLY PLANNING May 1, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 2/2/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 3/22/2007 Don Lynch. 3/22/2007 Weekly Planning Meeting 2 Schedule Re-Start 5 man shifts 3/20/07 Beam: blue ring 3/8/07, in yellow.
Muon Tracker Responsibilities This Year South arm commissioning through this year’s run Analysis Software oversight and development North Arm station 2.
PHENIX WEEKLY PLANNING 2/9/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 9/14/06 Don Lynch. 9/14/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown '065/1/200612/8/2006.
PHENIX WEEKLY PLANNING 3/09/06 Don Lynch. BLM Test BLM Test Installation He Bags.
PHENIX WEEKLY PLANNING 3/23/06 Don Lynch. MPC Electronics MPC rack installed without cards. Cards to be installed As available and as access time is available.
1 3/10/2011 PHENIX WEEKLY PLANNING 3/10/2011 Don Lynch.
PHENIX WEEKLY PLANNING 10/4/2007 Don Lynch. 10/4/2007 Weekly Planning Meeting 2007 PHENIX Shutdown October 2007: Finish MPC South Installation, replace.
PHENIX WEEKLY PLANNING 12/7/06 Don Lynch. 12/7/06 Weekly Planning Meeting 2.
1 Onsite Status Itaru Nakagawa RIKEN/RBRC. 2 Schedule.
8/31/05DR Lynch1 HBD Preparations in the IR Don Lynch.
3/20/ PHENIX WEEKLY PLANNING March 20, 2014 Don Lynch.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
Dick Loveless Upgrade report 12 Oct EMU Upgrade Report Dick Loveless University of Wisconsin 12 October 2012.
1/26/20121 PHENIX WEEKLY PLANNING 1/26/2012 Don Lynch.
11/10/20111 PHENIX WEEKLY PLANNING 11/10/2011 Don Lynch.
10/2/2002MJL - MuTr DC Report Muon Tracking Status South North.
M. Brooks, 16-Dec-00 Muon Collaboration Meeting North FEE Schedule Assume installation in 2002 shutdown, June-October(?), gives 1.5 years to complete pre-installation.
Plans to Test HBD Prototype in Run 6 Craig Woody BNL DC Meeting March 8, 2006.
Technical Support /19/08 PHENIX WEEKLY PLANNING 6/19/2008 Don Lynch.
Technical Support /28/08 PHENIX WEEKLY PLANNING 8/28/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/02/06 Don Lynch. BLM Test.
Technical Support /15/08 PHENIX WEEKLY PLANNING 5/15/2008 Don Lynch.
PHENIX WEEKLY PLANNING 6/28/2007 Don Lynch. 6/14/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set up5/ ?
MuTrig-FEE Install Status RIKEN/RBRC Itaru Nakagawa 1.
12/15/20111 PHENIX WEEKLY PLANNING 12/15/2011 Don Lynch.
5/30/20131 PHENIX WEEKLY PLANNING 5/30/2013 Don Lynch.
Technical Support /16/08 PHENIX WEEKLY PLANNING 10/16/2008 Don Lynch.
12/08/20111 PHENIX WEEKLY PLANNING 12/08/2011 Don Lynch.
Onsite Report Itaru Nakagawa RIKEN/RBRC. Schedule.
Study of polarized sea quark distributions in polarized pp collisions at sqrt(s)=500GeV with PHENIX Oct. 10, 2008 Tsutomu Mibe (KEK) for the PHENIX collaboration.
DCal-ALICE integration and installation plan and status A. Tauro.
ELENA installation progress F. Butin / ELENA collaboration.
Polarized 3He target installation
Racks PC Rack >> 24 mini and 12 tall PC racks Mini Racks
Presentation transcript:

M. Brooks DC Meeting, 15-Sep-00 MuTr Mechanics Status SOUTH ARM: Chambers fabrication complete Stations 2+3 installed Station 1 test-installed will be reinstalled when alignment fibers in Alignment system Installed Sept-Oct as parts arrive Gas system installation beginning, expect completed by end of Sept. HV distribution system In fab, install with FEE Magnet buss modification In-progress, by Charlie. Needs to be complete by ~October Manpower required Couple hours for St. 1

M. Brooks DC Meeting, 15-Sep-00 MuTr Mechanics Status NORTH ARM: Necessary to begin work this shutdown if we want it to be ready for data taking by 2002 Work required: Magnet preparation-few months of work slated for this shutdown Chamber installation shutdown Status of work for this shutdown: Drawings for templates for magnet drilling completed by mid October Chambers Designs completed Procurement of parts beginning now Expect completed chambers by Summer 2001

M. Brooks DC Meeting, 15-Sep-00 MuTr FEE Status--Assembly Hall SOUTH ARM: Already completed cable tray installation internal support structure installation test-installation of most of the CRAs scaffolding installation/fixes test-installation of St. 1 FEE plate prototype mount of Glink/Clink crates Rack platform installed Racks filled and stands completed (LV, HV, calibration system, slow controls, ARCNet hub, patch panel, … all ready) In progress: Production of all Glink/Clink mounts Plumbing and power for racks Plumbing for FEE cooling water and dry air To Come: Installation of populated CRAs and FEE plate, cable routing, testing

M. Brooks DC Meeting, 15-Sep-00 MuTr FEE Status--Assembly Hall SOUTH ARM: Manpower required Couple weeks of crane, tech support (Ray) to install CRAs inside magnet Day or two to install Station 1 FEE plate Physicists, students run cables, debug, …

M. Brooks DC Meeting, 15-Sep-00 MuTr FEE Status Mechanical Hardware All chassis, CRAs, Station 1 FEE plate assembled, plumbed and pressure/leak tested Ready for board installation and testing Test stands Test stands for several different board types essentially complete Test plans for stuffed CRAs, FEE plate completed Boards and cables All board orders out Backplane--first item received and go ahead given for full production 8-Sep. Should receive full production Oct. 6 Control Board--20 boards already received and tested o.k. Full production expected Sep. 29 CROC--36 boards shipped, full production expected Sep. 22 Glink/Clink boards--first items expected next week full production expected Oct. 20 Analog cables--already received 480, full shipment by Nov. 1 LV cables--fabricated and tested Glink/Clink cables--expected First CRA expected complete end of Sept / beginning of Oct All electronics completed end of November--Still expect to be able to meet this deadline, but no contingency