Update of master schedule and report from SLAC G. Riddone
Master Schedule See EDMS#844300, v3 -Status -Master schedule by test station and by types -Rf components
T18 - Alignment Optical measurement (from two sides) ex. T18#4 (OD 45 mm)
T18 - Bonding T18_vg2.4_disk_4 Before bonding - OD 45 mm - 2 tuning holes per cell only Then - Brazing of the couplers - Brazing of the studs
Tuning C10 – KEK drawing
Tuning C10 2. stud: the disk is systematically equipped with studs 3. The tube ends at the tread part of the stud. TK of the tube is not defined
Tuning C10 Test set-up for tuning Position for “pulling” Test set-up for tuning Position for “pulling” Sliding hammer to push and pull Disks with tuning studs
Structure cell with 45° WG
Symmetrical disk No tuning was implemented
NLCTA – T18 reverse and T26