1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC.

Slides:



Advertisements
Similar presentations
MuTRG for Run12 RIKEN/RBRC Itaru Nakagawa 1. Run12 Schedule 14 Cryoweeks -> Mid Jan. ~ End of April GeV pp (2+3 weeks) GeV pp (1+6 weeks)?
Advertisements

MuTr/MuTrig Performance of Run13 RIKEN/RBRC Itaru Nakagawa 1.
Recap Clamp Production and Installation RIKEN/RBRC Itaru Nakagawa 1.
Technical Support /7/08 PHENIX WEEKLY PLANNING 8/7/2008 Don Lynch.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
MuTr Recap Status and Plan. Plan We are shooting for North Station-1 for post Run10 shutdown installation. Best scenario is to mount portable “clamp”
Run10 Preparation Status and Issues Itaru Nakagawa RIKEN/RBRC.
1/12/20121 PHENIX WEEKLY PLANNING 1/12/2012 Don Lynch.
Jon S Kapustinsky 11/17/2010 Jon S Kapustinsky FVTX Commissioning Plan 1.71 Jon S Kapustinsky 1.
Run11 MuTrig-FEE Summary RIKEN/RBRC Itaru Nakagawa 1.
Technical Support /5/08 PHENIX WEEKLY PLANNING 6/5/2008 Don Lynch.
PHENIX WEEKLY PLANNING 5/17/2007 Don Lynch. 5/17/2007 Weekly Planning Meeting 2.
PHENIX WEEKLY PLANNING 11/30/06 Don Lynch. 11/16/06 Weekly Planning Meeting 2 PHENIX END OF SHUTDOWN PARTY Celebrating the successful installation of.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
Technical Support /26/08 PHENIX WEEKLY PLANNING 10/2/2008 Don Lynch.
1/5/20121 PHENIX WEEKLY PLANNING 1/5/2012 Don Lynch.
8/9/20121 PHENIX WEEKLY PLANNING 8/9/2012 Don Lynch.
3/29/20121 PHENIX WEEKLY PLANNING 3/29/2012 Don Lynch.
12/26/2013-1/2/ PHENIX WEEKLY PLANNING Dec. 26, Jan. 2, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 4/10/2008 Don Lynch. 04/10/08 Shutdown ’08 Schedule Purge Flammable Gas, Magnet & DAQ TestsDone Remove lock-out & open shield wallDone.
12/5/ PHENIX WEEKLY PLANNING Dec. 5, 2013 Don Lynch.
1 MuTRG-FEE Upgrade Status RIKEN/RBRC Itaru Nakagawa.
12/29/20121 PHENIX WEEKLY PLANNING 12/29/2011 Don Lynch.
Technical Support /4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.
MuTr Shutdown Work Rusty Towell for And JUNE 22, 2004 at the Muon Physics and Forward Upgrades Workshop.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Introduction to High Momentum Trigger in PHENIX Muon Arms RIKEN/RBRC Itaru Nakagawa 中川格 1.
PHENIX WEEKLY PLANNING 3/6/2008 Don Lynch. 3/6/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Technical Support /21/08 PHENIX WEEKLY PLANNING 8/21/2008 Don Lynch.
M. Brooks DC Meeting, 15-Sep-00 MuTr Mechanics Status SOUTH ARM: Chambers fabrication complete Stations 2+3 installed Station 1 test-installed will be.
Technical Support /14/08 PHENIX WEEKLY PLANNING 8/14/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/27/2008 Don Lynch. 3/27/2008 Weekly Planning Meeting2 Shutdown ’08 Schedule CM Crane ReviewMar Purge Flammable Gas, Magnet.
PHENIX WEEKLY PLANNING 3/22/2007 Don Lynch. 3/22/2007 Weekly Planning Meeting 2 Schedule Re-Start 5 man shifts 3/20/07 Beam: blue ring 3/8/07, in yellow.
PHENIX WEEKLY PLANNING 1/10/2008 Don Lynch. 1/10/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
PHENIX WEEKLY PLANNING 2/9/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 9/14/06 Don Lynch. 9/14/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown '065/1/200612/8/2006.
PHENIX WEEKLY PLANNING 3/23/06 Don Lynch. MPC Electronics MPC rack installed without cards. Cards to be installed As available and as access time is available.
1 PHENIX WEEKLY PLANNING January 21, 2016 Carter Biggs.
1 Onsite Status Itaru Nakagawa RIKEN/RBRC. 2 Schedule.
8/31/05DR Lynch1 HBD Preparations in the IR Don Lynch.
12/6/20121 PHENIX WEEKLY PLANNING 12/6/12 Don Lynch.
1/26/20121 PHENIX WEEKLY PLANNING 1/26/2012 Don Lynch.
Technical Support /5/08 PHENIX WEEKLY PLANNING 12/5/2008 Don Lynch.
PHENIX WEEKLY PLANNING 11/15/2007 Don Lynch. 11/8/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going11/30.
Recap Clamp for MuTr Station-3 Itaru Nakagawa For the PHENIX Muon Trigger Upgrade Collaboration Especially credit to: Tsutomu Mibe (KEK) Yoshinori Fukao.
Technical Support /28/08 PHENIX WEEKLY PLANNING 8/28/2008 Don Lynch.
1 8/27/2009 PHENIX WEEKLY PLANNING 8/27/2009 Don Lynch.
Technical Support /15/08 PHENIX WEEKLY PLANNING 5/15/2008 Don Lynch.
PHENIX WEEKLY PLANNING 1/24/2008 Don Lynch. 1/17/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going Switch.
PHENIX WEEKLY PLANNING 6/28/2007 Don Lynch. 6/14/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set up5/ ?
MuTRG Channel map summary June 30, 2008 Tsutomu Mibe KEK 1.
Recap Clamp Installation RIKEN/RBRC Itaru Nakagawa 1.
PHENIX WEEKLY PLANNING 1/31/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going Switch.
MuTrig-FEE Install Status RIKEN/RBRC Itaru Nakagawa 1.
Run11 MuTrig Performance RIKEN/RBRC Itaru Nakagawa 1.
5/30/20131 PHENIX WEEKLY PLANNING 5/30/2013 Don Lynch.
Jamaica 11 Jan.8, 2009 Muon Trigger Upgrade at PHENIX RIKEN/RBRC Itaru Nakagawa RIKEN/RBRC Itaru Nakagawa.
1 Installation Status Remaining Issues RIKEN/RBRC Itaru Nakagawa.
Technical Support /22/08 PHENIX WEEKLY PLANNING 5/22/2008 Don Lynch.
Onsite Report Itaru Nakagawa RIKEN/RBRC. Schedule.
Study of polarized sea quark distributions in polarized pp collisions at sqrt(s)=500GeV with PHENIX Oct. 10, 2008 Tsutomu Mibe (KEK) for the PHENIX collaboration.
1 2/19/2009 PHENIX WEEKLY PLANNING 2/19/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 2/14/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Muon Trigger Performance Run12 PP510GeV Sanghwa Park (SNU/RIKEN)
Onsite Work Summary RIKEN/RBRC Itaru NAKAGAWA. Completed Re-capacitation St-1, Gap-1 N&S Completed St-2 Terminators Install to South Oct.5 (except for.
Preparation for Run10 RIKEN/RBRC Itaru Nakagawa. TLD badges (to be replaced every two weeks) Location of dosimeters in MuTr.S St.1 TK361 TK362 TK363 TK364.
Pierluigi Paolucci - I.N.F.N. Naples
Seyoung Han / Ewha Woman’s Univeristy
Polarized 3He target installation
Presentation transcript:

1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

2 South Arm Installation

3 North Station-1 Before After

4 New Electronics Board 4 Signal from MuTr (64 ch) 6.5 V 1.2 Gbps 9.4 MHz Regulators (3.3, 2.5, 1.2 V) Cooling Water Dry air Cooling Water

5 Chassis ( 車体、シャーシ) Install Mount on Existin’ FEE (フロントエンド回路) : 6 screws (10min.) Chamber Cables (30min.) Board Install + cables (10min) Cooling Water & Air (15min.) ~ 1 hour/FEE  120 ~ 120 hours

6 Statistics Station123Total Chassis (車体、シャー シ) ADTX Boards (集積回路) South Arm

7 ‘09 Shutdown Schedule Starts End of June Guaranteed Month Shutdown Period Close hall on Dec.1 (Likely), Mid.Nov. (Unlikely) St-2&3 Scaffold Disassembly Starts 4th week October Effectively we have <3 months for Install North:Aug - Dec~5 months (Intense Cable Install -> Scaffold Disassembly starts)

8 Travel Schedule

9 Infrastructure Install Schedule Spin fest

10 Install Schedule (ADTX & Rack Room)

11 North Man Power Summary ExpertJulyAugSeptOctNovDecTotal Tsutomu Kenichi Katsuro Yoshi112 Itaru Total17 unit:month Summer HelpTotalPre-Install Rikkyo Kyoto30.0 Eric31.5 Total

12 Projection to South Required Man Power Expert { 17Month  0.9 (South/North)  15/16 (Half Octant-5) - 3Month (Noise Hunt) + 0.5Month (Noise Hunt) Month (Miscabling Check) }  1(experience) = 12.5 Month is required Summer Students –Pre-Install 3.5  0.9(South/North)  0.9(experience) = 2.8 Month  (3/5)(Work Done by Eric) ~ 2 Month (to be covered by Japanese students) –Total { (DB development) }  0.9 (South/North) ~ 9 Month

13 South Man Power Estimation ExpertJulyAugSeptOctNovDecTotal Tsutomu0.5? 1.5 Kenichi0.3?0.3 Katsuro0.50.5? 1.5 Yoshi Itaru Imazu Total9.3 unit:month Summer HelpTotalPre-Install Tokyo2 Rikkyo2.5 Kyoto2 RIKEN (Kanaya)1 Local Students (Eric, Schadrac, RPC folks)2.52 Total102

14 LV Cable Status 16/20 Bundles Completed Frank Toldo will cut and assemble connectors this week. Schadrac will work on bundling in July 16 ~ 17 Schadrac Philogene  Ready for Install by 4th week of July

15 Optical Fiber Status Test & Labeling Completed by Eric Jones Bundling: ( 3 RPC Students + Schadrac )  1 week 20/20 Completed Ready for Install any time RPC students Eric Jones

16 Other Items Stock List Labeling Done Labeling & Bundling Done

17 July 3rd Week LV Cable Bundling (Schadrac) Test Bench for Chassis –Test Bench Set up (Katsuro) –Back Plane Test (Ninomiya) –Water Leak Test (John T.) Mega Pack LV Power Supply Install (Frank) St.2, St.3 Cable Tray Install (Paul) South Cable Route Map (Ninomiya)

18 July 4th Week Uninstall St.2, St.3 LV, Fiber Cables (Schadrac, Ninomiya, Itaru) St.2, St.3 LV, Fiber, Trunk Cable Install (Schadrac, Ninomiya, Itaru, Local Student) Test Bench for Chassis –Back Plane Test (Ninomiya) –Water Leak Test (John T.) Patch Bay Channel Map (Ninomiya)

19 July 5th Week St.2, St.3 LV, Fiber, Trank Cable Install (Schadrac, Ninomiya, Itaru, Local Student?) St.2, St.3 LV platform (Frank) Trunk Cable Patch Bay Connection (Schadrac, Nimomiya) Test Bench for Chassis –Back Plane Test (Ninomiya) –Water Leak Test (John T.) South Magnet in South Position Station-1 Scaffold Construction (Union)

20 Aug 1st Week Station-1 Scaffold Construction (Union) St.1 LV, Fiber Install (All) St.1 LV platform (Frank) Optical Fiber Patch Bay Connection (Nimomiya, Kanaya, Hirota, Ichikawa) Station-2,3 Scaffold Construction

21 Aug 2nd Week St.1 LV, Fiber Install (All) St.1 LV platform (Frank) Optical Fiber Patch Bay Connection (Nimomiya, Kanaya, Hirota, Ichikawa) Optical Fiber Chain Test (Ninomiya, Kanaya) ADTX-FEE Cable Test Bench –Setup (Yoshi) –Test (Hirota, Ichikawa) Station-2,3 Scaffold Construction Station-1 Chassis Mount (Jimmy)

22 Aug 3rd Week LV Tuning (Yoshi, Kanaya) Optical Fiber Chain Test (Hirota, Ichikawa, Kanaya) ADTX-FEE Cable Test Bench –Setup (Yoshi) –Test (Hirota, Ichikawa) ADTX QA –Setup (Yoshi) –QA (Sean) St.1 Chassis Mount (Jimmy) St.1 Plumming (John T.)

23 Aug 4th Week MRG Setup (Yoshi) St.1 ADTX-FEE Cable and ADTX install (Yoshi, Itaru) ADTX test (Samejima, Hirota, Ichikawa) ADTX QA –QA (Sean) St.1 Chassis Mount (Jimmy) St.1 Plumming (John T.)

24 Remaining Issue North Arm Station-3, Octant-1 High Noise Station-3, Octant-5 Miscabling

25 Required Trainings Web Course: –Guest Site Orientation (TQ-GSO)Guest Site Orientation –Cyber Security (GE-CYBERSEC)Cyber Security –Phenix Awareness (RC-PAT)Phenix Awareness –Electrical Safety I (TQ-ELECSAF1)Electrical Safety I –Scaffold User Safety (GE-SCAFFOLD)Scaffold User Safety Class Attendance Required: –Collider User Training 7/6(Mon),7/20(Mon),8/3(Mon),8/17(Mon),8/31(Mon),9/14(Mon) –Confined Space (HP-OSH-016) 7/7(Tus),7/29(Wed),8/6(Thur),8/28(Fri),9/3(Thurs)

26 St-2,St-3 Scaffolds ( 足場) 2 person / floor Scaffold & Confined space training required

27 Safety Two Men’s Rule (常に2 人で作業) No Aggressive Motion in IR (果敢な行動は不必要) Work on Scaffold (足場上 での作業は日中のみ) –Mon- Fri –8: :30 Ooh You are gonna be in trouble! Yousef Makdisi