E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, 2006 1 BI Group Commitments and Major Issues for Distributed Systems E.B. Holzer, J.J.

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

IEFC Workshop – 22/03/2011 JJ Gras on behalf of BE-BI 1.
LHC Commissioning WG 27/03/ Commissioning of BLM system L. Ponce With the contribution of B. Dehning, E.B. Holzer, M. Sapinski, C. Zamantzas and.
MPSCWG 12/12/ Operational scenario of the BLM system.
LECC 2006 Ewald Effinger AB-BI-BL The LHC beam loss monitoring system’s data acquisition card Ewald Effinger AB-BI-BL.
E.B. Holzer Chamonix XIV workshop, CERN January 18, Pre-commissioning of Critical Beam Instrumentation Systems E.B. Holzer, O.R. Jones CERN AB/BDI.
BI SW for LINAC4 On behalf of BE/BI/SW BI software development process Specifications List of BI Systems – Not covered: PSB ring systems Conclusions Lars.
Guy Crockford AB/OP OP Days, 7/2/2007 LHC Specific BI Systems This presentation reviews the status of the specific BI systems for the LHC. The work plan.
Eva Barbara Holzer IEEE NSS, Puerto Rico October 26, Beam Loss Monitoring System of the LHC Eva Barbara Holzer, CERN for the LHC BLM team IEEE Nuclear.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
Distributed BI Systems BLM, BPM, BTV and BRAN Laurette Ponce & Fabio Follin Thanks to: Anthony Rey, Enrico Bravin, Rhodri Jones, Bernd Dehning, Mariusz.
BI day 2011 T Bogey CERN BE/BI. Overview to the TTpos system Proposed technical solution Performance of the system Lab test Beam test Planning for 2012.
Ralph Assmann What Do We Want To Measure (in 2009) R. Assmann S. Redaelli, V. Previtali CERN/BE discussed with W. Scandale CERN/EN26/3/2009CC09  See also.
LHC Utilities & Facilities WAO Daejeong 12/04 – 16/04/2010 Markus Albert on behalf of LHC Operations.
BCT for protection LHC Machine Protection Review April 2005 David Belohrad, AB-BDI-PI
LHC Sector Test1 LHC Sector Test - Beam IntroductionMike LamontIntroductionMike Lamont Proposed tests with beamBrennan GoddardProposed tests with.
LHC BLM Software revue June BLM Software components Handled by BI Software section –Expert GUIs  Not discussed today –Real-Time software  Topic.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
BP & RS: BIS & SLP for AB/CO Review, 23 h Sept Realisation of the interlocking between SPS, LHC and CNGS and open issues Beam Interlock Systems.
Nominal Workflow = Outline of my Talk Monitor Installation HWC Procedure Documentation Manufacturing & Test Folder Instantiation – NC Handling Getting.
‘Review’ of the machine protection system in the SPS 1 J. Wenninger BE-OP SPS MPS - ATOP 09.
Real time performance estimates of the LHC BPM and BLM system SL/BI.
LHC Beam Loss Monitors, B.Dehning 1/15 LHC Beam loss Monitors Loss monitor specifications Radiation tolerant Electronics Ionisation chamber development.
Overview Consolidation projects for PS LIU-PS Main observable review Conclusion Acknowledgements S. Gilardoni R. Steerenberg G. Metral H. Damerau BI colleagues.
Running scenario 2009/10 Run through components – and then synthesis.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
Post Mortem Workshop Session 4 Data Providers, Volume and Type of Analysis Beam Instrumentation Stéphane Bart Pedersen January 2007.
Chamonix 2006, B.Dehning 1 Commissioning of Beam Loss Monitors B. Dehning CERN AB/BDI.
VME64x Digital Acquisition Board (TRIUMF-DAB) Designed to handle 2 channels of 12-bit 40MHz Data Will be used for both the LTI & LHC beam position system.
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
LHC Radiation Day, B. Dehning1 Beam Loss Monitors B. Dehning.
The Dashboard The Working Conditions The Common Chapters State What’s Next.
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
RF acceleration and transverse damper systems
Data providers Volume & Type of Analysis Kickers
2007 IEEE Nuclear Science Symposium (NSS)
BEAM LOSS MONITORING SYSTEM
Pre-commissioning of Critical Beam Instrumentation Systems
Injectors BLM system: PS Ring installation at EYETS
The ELENA BPM System. Status and Plans.
Beam Loss Monitor System Reliability and False Signals
LHC BLM system: system overview
BEAM LOSS MONITORING SYSTEM
External Review on LHC Machine Protection, B.Dehning
Interpretation and use of BLM Data
Distributed BI Systems
Remote setting of LHC BLM thresholds?
Beam loss monitoring requirements and system description
Combiner functionalities
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
Verification of the Beam Loss studies at start-up
J. Emery, B. Dehning, E. Effinger, G. Ferioli, C
Agenda 9:00-10:00 Beam Interlock System Changes Following the 2006 Audit Benjamin Todd 10:00-11:00 Beam Dump System follow-up from the 2008 Audit Jan Uythoven.
Test and start‐up procedures
Commissioning of BLM system
Commissioning of BLM system
BEAM LOSS MONITORS The BLM system Status of the monitors
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
Why do BLMs need to know the Quench Levels?
Commissioning of BLM system
Beam Loss Simulations LHC
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Chamonix Workshop XIV CERN - 17th-21st January 2005
Operational scenario of the BLM system
Report on Beam Loss Monitors
Machine protection and closed orbit
Feedbacks & Stabilization Getting them going
What systems request a beam dump? And when do we need them?
Presentation transcript:

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, BI Group Commitments and Major Issues for Distributed Systems E.B. Holzer, J.J. Gras, O.R. Jones CERN AB/BI Third LHC Project Workshop - Chamonix XV January 24, 2006 Divonne-les-Bains

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Outline  BI Responsibilities (J.J. Gras)  Beam Synchronous Timing (J.J. Gras)  Beam Position Monitor System (R. Jones)  Beam Loss Monitor System  Summary

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, BI Responsibilities

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Responsibility Limits  AB/BI will provide  the monitors  the electronics  the front end software  the corresponding expert applications  to develop, test, deploy, diagnose and maintain the instruments produced by the group  AB/BI is NOT responsible for any software above the BI front end servers necessary to operate the machine, i.e.  BPM, BLM Concentrators  RT Feed Back Loops and Fixed Displays  Middle Tier Black Boxes  Operational Applications  Post-mortem and Logging Applications  Video and Analog Signal Transmission

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, People in Charge  All components of the BI mandate covered EquipmentProject Leader MonitorElectronicsFE Software Exp. Appl. Commissioning BOB (BST)J.J. Savioz n.a.J.J. SaviozP. KarlssonBLM, BPM experts BPMR. JonesC. Boccard E. CalvoL. JensenJ. Wenninger (OP), W. Herr (ABP), Y. Papaphilippou (ABP) BLMB. Dehning E.B. Holzer C. Zamantzas, E. Effinger, J. Emery S. JacksonR. Assmann (ABP), H. Burkhardt (ABP), J.B. Jeanneret (ABP), S. Gilardoni (ABP)

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Beam Synchronous Timing – BOBM and BOBR

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Commitments  The BST (BOB) system based on TTC technology will provide to the LHC beam instrumentation  40 MHz bunch synchronous clock  11 kHz LHC revolution frequency  In addition, it will allow the encoding of beam synchronous messages  for LHC instrumentation triggering and  for broadcasting of machine status (mode, intensity, energy, turn number…)  can be updated on every LHC turn  BST system expected to be available at start-up (as soon as the RF signal is received)

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Clients  The BPM rely on BST for orbit, trajectories, multi-turn acquisitions and post-mortem triggering  BLM will rely on BST only for the post-mortem and logging trigger  BST will be used by other instruments to synchronise themselves (BTVM, BWS, BSRT…) or with each others  The machine status has proven to be of interest to the LHC experiments, which will receive this information using their standard TTC receivers and decoders [see EDMS ]

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Testing Plans  BST system is a collaboration between AB/CO (Master HW and Firmware) and AB/BI (Master Server/RT and Receiver HW/FM/SW)  Three systems are foreseen (SPS, LHC B1 and B2)  The recent v2 functionality covers the need (currently being tested)  BOB system will be commissioned on SPS in 2006 and assessed during the LHC sector test (with the SPS BOB Master)

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Beam Position Monitors - BPM  Status  Performance  Commissioning  Cuts proposed for Stage I

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Status of BPM Electronic Components  Wide Band Time Normaliser (analogue front-end)  Successfully tested in TI8 and SPS  Series Production (4500 units) launched by the end of January 2006  Digital Acquisition Board (DAB64x - TRIUMF)  Series production (1800 units) started. BI standard for BPM, BLM, Fast BCT and Q measurement acquisition  Network Infrastructure in place  Fibre-optic, coaxial cable and WorldFIP control links  The BPM acquisition hardware is expected to be fully functional for LHC start-up

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, BPM Performance Resolution (rms) Pilot bunch Trajectory (single shot) 200 μm Orbit (224 turn average) 20 μm Nominal intensity bunch Trajectory (single shot, single bunch) 50 μm Trajectory (average of all bunches 5 μm Orbit (average of all bunches over 224 turns) 5 μm Nominal resolution (5 μm) for  single bunch: intensity > 2-3·10 10 charges per bunch  global orbit: 43 pilot bunches Linearity versus Intensity BPM operating threshold ~1·10 9 charges/bunch corresponds to 17% nominal ion bunch intensity

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Commissioning with the BPM System I  Before Beam  Test of the system in the SPS and TI8  Gives confidence in performance  Allows software development and debugging  Full calibration of the LHC acquisition chain  part of BPM hardware commissioning  First Turn  Asynchronous Mode  Auto-triggered - no dependence on external timing  Intensity Measurement – aim to have this operational BUT  currently concentrating on the position system  implies considerable amount of additional software as intensity measurement uses acquisition system of other ring  lack of intensity card DOES NOT affect position measurement

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Commissioning with the BPM System II  First few to 1000 Turns  Timing-in of BST system  Allows bunch/turn tagging  Can be done in parallel to asynchronous acquisition  Circulating Beam at 450 GeV  Global Orbit Mode  Available once BST is timed-in  Allows post-mortem to be used  Real-time orbit data available  Capture Mode  Triggered on request  Allows bunch to bunch and turn-by-turn data  Can generate a large amount of data  will require concentrators and powerful analysis software to be in place

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Commissioning with the BPM System  Snapback, Ramp and Squeeze  Real-time global orbit data available for feedback  Requires concentrator, feedback algorithms and real-time correction to be available to implement the feedback.

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Cuts proposed for Stage I on Multi Turn Acqu. System  Multi turn acquisition up to 100’000 turns on  one user selected bunch or  the beam average  Always on consecutive turns  Always on all BPMs at the same time

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Beam Loss Monitors - BLM  Status  System Tests  Updating the Threshold Tables  Synchronization  BLM for Ions

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Status I  Network infrastructure: done  Detectors: almost all components received  Ionization chambers (3800): Production at CERN started (40), Production in Prodvino will start in February.  Production rate 20/day, total production time: 1 year  Secondary emission monitors, SEM (320): Prototyping phase, working design. Production foreseen to start Q1 2007, and take 2 months  Expected to be ready for LHC commissioning (not for sector test)

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Status II  Electronics  Crates (456 in the tunnel and 105 on the surface) and power supplies: installation started  Acquisition in the tunnel: pre-series production started (50 out of 750 cards)  Acquisition on the surface: series production started for DAB card, pre- series production started for mezzanine card (30 out of 400 cards)  Interlock and testing (“combiner card”, 25 cards): under design  To be done – all expected to be ready for LHC commissioning  Addition to DAB card program  Post-mortem  Final communication tests with threshold tables  Combiner card  CFC program: implementation of additional high voltage tests

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, System ready for LHC and fulfill the Specifications?  Hardware expected to be ready for LHC start-up  Plan B: possible to install smaller number of detectors - unlikely  Threshold tables (calibration of BLM) based on simulations.  Plan B: ask for beam tests in the LHC to calibrate the BLM system  Analysis effort of BLM logging and post-mortem data (sector test and LHC beam data, “parasitic” and dedicated tests) to be started in 2006!  Calibration of threshold tables  Interpretation of BLM signal patterns  Large amount of data to be analyzed  Extensive software tools for data analysis essential to fulfill the specifications! Start now to specify and implement!  Logging and post-mortem need to work for Sector Test!

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, BLMS Testing Procedures PhD thesis G. Guaglio Radioactive source test (before start-up) Functional tests Barcode check HV modulation test (implemented) Double optical line comparison (implemented) 10 pA test (implemented) Thresholds and channel assignment SW checks (implemented) Beam inhibit lines tests (under discussion) Detector Tunnel electronics Surface electronics Combiner Inspection frequency: Reception Installation and yearly maintenance Before (each) fill Parallel with beam Current source test (last installation step) Threshold table beam inhibit test (under discussion)

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Updating the Threshold Tables  How to change threshold tables technically  Possibility to write them via VME interface: will be used in the lab and disabled by a hardware switch when installed in the tunnel  During commissioning and during operation the threshold tables can only be changed locally via a dedicated interface  How to change them conceptually  Empirically  define procedure  After analysis of loss data  possibility to change the energy and loss duration dependence  Define needs and production of software tools  Generation of threshold tables  “Management of Critical Settings” (MCS)  Managing and Archiving of threshold tables  Group monitors according to magnet types for faster changing of threshold tables

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Synchronization  For reliability reasons the BLM system does not use external timing (other than for post-mortem and logging triggering)  Synchronization of timing windows between different BLM DAB cards?  e.g.: update interval of 5.5 s time window is 82 ms: Moving Average Refreshing Rate 40 μ s 80 μ s40 μ s 0.3 ms40 μ s 0.6 ms40 μ s 2.6 ms80 μ s 10 ms80 μ s 82 ms2.6 ms 0.3 s2.6 ms 1.3 s82 ms 5.5 s82 ms 21 s1.3 s 84 s1.3 s 5.5 s max. 82 ms time jitter BLM DAB 1 BLM DAB 2 Logging Readout Frequency 1 Hz 1 s BLM DAB 1 BLM DAB 2 time

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, BLM for Ions I  Considerably less simulations available than for protons at the moment  much higher uncertainty for the BLM system  Simulations of ion loss maps done (H. Braun)  additional monitors; Error studies still to be done (AB/ABP) H. Braun

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, BLM for Ions II  BFPP simulations for ALICE: loss positions (J. Jowett) and showers through dipole magnet (R. Bruce)  additional monitors  Main dipoles: ratio of energy deposited in magnet versus energy deposited in the BLM detector is roughly the same as for protons  Ratio of quench (damage) level to BLM signal about the same as for protons  Similar threshold tables for protons and ions  standard BLMs (local aperture limitations) at right position  Future simulations (other EM processes) might lead to more requests for BLMs Energy position in the hottest part of the coil and at the BLM location (FLUKA, LHC Project Note 379, R. Bruce et al.)

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Summary  The BST, BPM (possibly excluding intensity measurement) and BLM hardware systems are expected to be fully operational for LHC start- up.  BPM various modes of acquisition should allow the necessary data to be available when required.  BLM calibration requires logging and post-mortem plus MCS - starting from the Sector Test.

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Some additional slides

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Functional Tests  Radiation tests of tunnel electronics (PSI)  Temperature test (tunnel electronics)  Detector test in booster, T2, H6, PSI: uncertainty (up to a factor of 2) to be corrected for with the results of M. Stockner’s thesis.  Long term test of whole acquisition system: booster and DESY  Test of quench levels (threshold calibration): Laboratory, HERA, sector test, simulations

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Quench protection system (damage protection) BLM system damage protection, no redundancy Required Accuracy for Damage Protection Arc Dipole Magnet Relative loss levels for fast losses 450 GeV 7 TeV Damage level Quench level 33 Dump threshold 11 Accurately known quench levels will increase operational efficiency Absolute precision (calibration) < factor 2 initially: < factor 5 Relative precision for quench prevention < 25% Fast current transformer (DIDT) will protect against fast (1 turn) losses only from phase 2 of the LHC (absolute calibration by software during phase 1 too slow – phase two: hardware implemented)

E.B. Holzer Chamonix XV workshop, Divonne-les-Bains January 24, Shower development in the Cryostat  Impact position varied along the MQ  Highest signal from loss at the beginning of the MQ  Position of detectors optimized  to catch losses:  Transition between MB – MQ  Middle of MQ  Transition between MQ – MB  to minimize uncertainty of ratio of energy deposition in coil and detector  Beam I – II discrimination Beam L. Ponce