Technical Support 2008 1 8/14/08 PHENIX WEEKLY PLANNING 8/14/2008 Don Lynch.

Slides:



Advertisements
Similar presentations
Technical Support /7/08 PHENIX WEEKLY PLANNING 8/7/2008 Don Lynch.
Advertisements

Technical Support /23/08 PHENIX WEEKLY PLANNING 10/23/2008 Don Lynch.
PHENIX WEEKLY PLANNING 1/17/2008 Don Lynch. 1/17/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
9/6/20121 PHENIX WEEKLY PLANNING 9/6/2012 Don Lynch.
PHENIX WEEKLY PLANNING 2/15/2007 Don Lynch. 2/15/207 Weekly Planning Meeting 2 Remaining Schedule StartComplete Cosmic Ray Run (Run 6.9)In Progress All.
Technical Support /5/08 PHENIX WEEKLY PLANNING 6/5/2008 Don Lynch.
PHENIX WEEKLY PLANNING 5/17/2007 Don Lynch. 5/17/2007 Weekly Planning Meeting 2.
1 7/02/2009 PHENIX WEEKLY PLANNING 7/2/2009 Don Lynch No Meeting this week due to July 4 th holidays. Slides have been updated. Next planning meeting will.
Technical Support /12/08 PHENIX WEEKLY PLANNING 6/12/2008 Don Lynch.
1 1/22/2009 PHENIX WEEKLY PLANNING 1/22/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/21/2008 Don Lynch. 2/21/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Technical Support /26/08 PHENIX WEEKLY PLANNING 10/2/2008 Don Lynch.
1 1/13/2011 PHENIX WEEKLY PLANNING 1/13/2011 Don Lynch No Meeting Today Due to snow shortened work week, today’s planning meeting has been cancelled. Slides.
1/5/20121 PHENIX WEEKLY PLANNING 1/5/2012 Don Lynch.
8/9/20121 PHENIX WEEKLY PLANNING 8/9/2012 Don Lynch.
Technical Support /11/08 PHENIX WEEKLY PLANNING 12/11/2008 Don Lynch.
PHENIX WEEKLY PLANNING 4/10/2008 Don Lynch. 04/10/08 Shutdown ’08 Schedule Purge Flammable Gas, Magnet & DAQ TestsDone Remove lock-out & open shield wallDone.
PHENIX WEEKLY PLANNING 3/8/2007 Don Lynch. 3/8/207 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Continues…. All Up Commissioning In Progress.
Progress Completed Order/Fabricate SS Piping for HBD Purge gas from all detectors DAQ tests Prep. for Shutdown work (open doors, move carriages, etc. Pave.
12/29/20121 PHENIX WEEKLY PLANNING 12/29/2011 Don Lynch.
Technical Support /4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Technical Support /17/08 PHENIX WEEKLY PLANNING 7/17/2008 Don Lynch.
Technical Support /24/08 PHENIX WEEKLY PLANNING 4/24/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/6/2008 Don Lynch. 3/6/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Technical Support /1/08 PHENIX WEEKLY PLANNING 5/1/2008 Don Lynch.
Technical Support /21/08 PHENIX WEEKLY PLANNING 8/21/2008 Don Lynch.
M. Brooks DC Meeting, 15-Sep-00 MuTr Mechanics Status SOUTH ARM: Chambers fabrication complete Stations 2+3 installed Station 1 test-installed will be.
PHENIX WEEKLY PLANNING 3/27/2008 Don Lynch. 3/27/2008 Weekly Planning Meeting2 Shutdown ’08 Schedule CM Crane ReviewMar Purge Flammable Gas, Magnet.
5/1/ PHENIX WEEKLY PLANNING May 1, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 2/2/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 11/2/06 Don Lynch. 11/2/06 Weekly Planning Meeting 2 New Detectors TOF West HBD RXNP MPC North.
PHENIX WEEKLY PLANNING 3/22/2007 Don Lynch. 3/22/2007 Weekly Planning Meeting 2 Schedule Re-Start 5 man shifts 3/20/07 Beam: blue ring 3/8/07, in yellow.
PHENIX WEEKLY PLANNING 1/10/2008 Don Lynch. 1/10/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
PHENIX WEEKLY PLANNING 2/9/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 9/14/06 Don Lynch. 9/14/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown '065/1/200612/8/2006.
Technical Support /8/08 PHENIX WEEKLY PLANNING 5/8/2008 Don Lynch.
PHENIX WEEKLY PLANNING 12/6/2007 Don Lynch. 12/6/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
1 3/10/2011 PHENIX WEEKLY PLANNING 3/10/2011 Don Lynch.
9/27/20121 PHENIX WEEKLY PLANNING 9/27/2012 Don Lynch.
PHENIX WEEKLY PLANNING 10/4/2007 Don Lynch. 10/4/2007 Weekly Planning Meeting 2007 PHENIX Shutdown October 2007: Finish MPC South Installation, replace.
PHENIX WEEKLY PLANNING 12/7/06 Don Lynch. 12/7/06 Weekly Planning Meeting 2.
1 12/30/2010 PHENIX WEEKLY PLANNING 12/30/2010 Don Lynch.
8/31/05DR Lynch1 HBD Preparations in the IR Don Lynch.
12/6/20121 PHENIX WEEKLY PLANNING 12/6/12 Don Lynch.
Technical Support /5/08 PHENIX WEEKLY PLANNING 12/5/2008 Don Lynch.
PHENIX WEEKLY PLANNING 12/27/2007 Don Lynch. 12/27/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
Technical Support /19/08 PHENIX WEEKLY PLANNING 6/19/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/15/2007 Don Lynch. 3/15/2007 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Done All Up Commissioning On Going Re-Start.
Technical Support /28/08 PHENIX WEEKLY PLANNING 8/28/2008 Don Lynch.
Technical Support /26/08 PHENIX WEEKLY PLANNING 6/26/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/02/06 Don Lynch. BLM Test.
Technical Support /15/08 PHENIX WEEKLY PLANNING 5/15/2008 Don Lynch.
PHENIX WEEKLY PLANNING 1/24/2008 Don Lynch. 1/17/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going Switch.
5/24/20121 PHENIX WEEKLY PLANNING 5/24/2012 Don Lynch.
Technical Support /18/08 PHENIX WEEKLY PLANNING 12/30/2008 Don Lynch.
PHENIX WEEKLY PLANNING 6/28/2007 Don Lynch. 6/14/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set up5/ ?
PHENIX WEEKLY PLANNING 1/31/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going Switch.
PHENIX WEEKLY PLANNING 10/26/06 Don Lynch. 10/20/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
1 1/29/2009 PHENIX WEEKLY PLANNING 1/29/2009 Don Lynch.
1 7/16/2009 PHENIX WEEKLY PLANNING 7/16/2009 Don Lynch.
Technical Support /16/08 PHENIX WEEKLY PLANNING 10/16/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/1/2007 Don Lynch March: in like a lion Out like a lamb.
Technical Support /22/08 PHENIX WEEKLY PLANNING 5/22/2008 Don Lynch.
1 7/9/2009 PHENIX WEEKLY PLANNING 7/9/2009 Don Lynch.
1 8/20/2009 PHENIX WEEKLY PLANNING 8/20/2009 Don Lynch.
1 11/25/2010 PHENIX WEEKLY PLANNING 11/25/2010 Don Lynch.
2/20/ PHENIX WEEKLY PLANNING Feb. 20, 2014 Don Lynch.
1 2/19/2009 PHENIX WEEKLY PLANNING 2/19/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 2/14/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Presentation transcript:

Technical Support /14/08 PHENIX WEEKLY PLANNING 8/14/2008 Don Lynch

Technical Support /14/08 Shutdown ’08 Schedule RPC Factory: Prototype C tests Complete Prototype D Testsgaps & module frames received on schedule for 9/15 installation Dark Current test standin design due 9/30 Mu Trigger FEE upgrade: Station 2/3 scaffoldingDone Station 1 scaffoldingDone Rack assemblyin progress finish North by 8/15, install by North by 8/22, install South by 9/30 LV cable prepDone Optical cable prepIn progress N&S platforms Fabricate & installfabrication complete, North platform is installed, install South by 9/30 (Pearson) Rebuild Bridge & EyebrowComplete by 9/30 Prep work for platforms (water/elec)in progress finish by 8/22 LV cable installationComplete by 8/29 optical cable installationDone FEE installation N&S sta’s. 1,2 & 3Aug-Sep.

Technical Support /14/08 Shutdown ’08 Schedule Mu Trigger FEE Upgrade (cont’d): FEE water and dry air installationAug-Sep Install S rack cooling & electricOct. Install FEE’s in MMS for RPC testNov. Rack room electronics, etc.Sep.– Oct. Final rack utilities Sep.-Oct Disassemble station1 scaffoldcomplete by Oct 15 Testing Sep.-Nov. Complete by 11/15 RPC engineering & safety reviewDone RPC proptotype installation: Prep workcomplete by Oct 31 move (7) MuID pipes move gap 5 south cable tray Rack prepComplete by Aug 29 RPC prototype gas systemJuly - Aug Move shielding for installationJuly - Sep RPC prototype cable routing & supportJuly - Aug Modify crystal palace & vapor barrierJuly - Aug RPC prototype install (RPC2 – PHENIX) Sep. – Oct. (RPC3 – C. Pearson) Sep. - Oct.

Technical Support /14/08 Shutdown ’08 Schedule, cont’d RPC proptotype installation (cont’d): Install rack in tunnel southSep. Replace tunnel shielding/Vapor BarrierNov. (C. Pearson) Connect electronics/gas Sep. – Nov. MuTr Decapacitations (Sta. 1 N and MMN)Station 1N Done Sta, 3N in progress/ finish by 8/15 Fan Tray maintenancein progress (on going fill-in) PC1 west work (needs planning)Oct. 15 CM Crane InstallOct. 20 HBD InstallOct. 27 DC East?/West RepairsNov. 15 Remove all inst’n equipment Sta 2/3 scaffoldsRemove by 11/15 all other testing equipmentRemove by 12/1 Prep for shutdown 2009 Gap 5 N piping and cable tray re-loc.Oct. – Dec. Gap 2 N cable tray & crate re-mountsOct. – Dec.

Technical Support /14/08 Shutdown ’08 Schedule, cont’d Prep for run 9 Begin run 9 Prep12/1/09 Install all lampshadesComplete by 11/26 Roll in EC12/22 Pink/White/Blue sheets12/29 Close shield wall 12/31 Cryo Start up1/1/09 Flammable Gas/start shifts 1/11/09 Start physics1/18/09 End Run 96/30/09 Coming soon: VTX, FVTX and NCC work

Technical Support /14/08 1) Run Power to new MuTrgr FEE racks on MMN and MMS - Final design of the reworked North Muon Power Distribution System is set. Nearly all material acquired eithout cost. Paul is m revising the One-Line electrical drawing. CAD approval required…maybe by next week. Effort should take ~ 1 week. The new power cable feed to the MuTrigger rack is installed (2 cables, 1 spare) with no connection to the panel down below. The new North side power panel is installed on the IR North east corner wall. The new 75 KVA transformer for the entire North Arm service is reconditioned and tested satisfactory. The power for the South RPC tunnel Rack(s) to be taken from an existing (spare) breaker in the Muon Tracker power panel. This should take less than 1 day to install. NO CHANGE PHENIX electrician needs to install vertical section of cable tray from North Magnet Lampshade to underside of new rack platform. CAD concurrence for construction details (Pearson) is required. COMPLETED MuTrigger LV Rack construction to require 4 man days to complete starting Monday 8/11. See line 5 for update. 2) Install power feeds to RPC north & south tunnel racks from IR power panels. – Plan is to run the cables from the IR to the North tunnel rack locations. The south RPC rack power can be taken from the existing (spare) breakers in the SMI power panel located on the IR south west wall. These cable runs may take a few days to complete due to new power tray runs required into the tunnel areas. Not done due to lack of manpower – working on other higher priority items. Shutdown ’08 Electrician Work

Technical Support /14/08 Shutdown ’08 Electrician Work, Cont’d. 3) Install new UPS in Gas mixing house. Not done due to lack of manpower – working on other higher priority items. 4) Install power and signal cable tray (ceiling suspended) for new DCM rack row – north of existing DCM racks. - on Hold until new floor plan is determined 5) Assist in signal and LV cable installation for MuTr/RPC upgrades as necessary. Work in progress – Optical and LV cables installed. LV cables (rack end) are coiled on platform deck next to LV rack mount location. Optical patch rack installed with some cables connected into rack. Work on LV rack continues – not expected to be completed until later next week. 6) Upgrade power capacity of Central Magnet power distribution for future bridge rack loads. a) Remove existing 15KVA transformer and install 45KVA unit. b) Install new (larger size) power cable from rack room to Central Magnet distribution breaker panels. - This job is on hold. No new racks in CM this year. 7) Install 120 volt AC power drops into new control room annunciator alarm rack (rack room). Not done due to lack of manpower – working on other higher priority items. 8) Ordering parts for South MuTrigger LV rack. Rack plumbing complete. Internal wiring to start maybe end of next week. 9) Discussions started with Chi and Steve Boose concerning RPC prototype rack for south tunnel.

Technical Support /14/08 New FEE Platforms & Modified Bridge Parts

Technical Support /14/08 MuTrigger FEE Rack Utilities Tees and Valves North FEE & Tunnel Electric Supply

Technical Support /14/08 MuTrigger FEE Installation Prep North & South Rack Prep First Chasis shipment has arrived Currently under leak test

Technical Support /14/08 North FEE & Tunnel Electric Supply MuTrigger FEE Installation Prep Station 1 FEE Support structure

Technical Support /14/08 MuTrigger FEE Installation Prep North FEE Rack Platform is in Temporary Access to Rack Platform is in

Cable Status

8/14/0814 Cabling Status Station-2 & Station-3 Cables are Installed from inside magnet to Patch Platform New LV Rack Ready (next week)  Establish connections LV cables inside rack  New Cable Trays? Station-1 fibers, LV cables to be installed next week 5 more fiber trunk cables to come (end of Aug.)

8/14/0815 Station-1 Cable Route Unistrat?

8/14/0816 Need to mount New cable tray? Station-1 Cables to be Installed Cabling from New Platform

8/14/0817 Difficulty in Station-1 Mount Space in front of Hatch

8/14/0818 Hatch Swing! Hinge

8/14/0819 Clearance Btwn Hatch

8/14/0820 Clearance Estimate w/ 3D Model Hatch 3.797”

8/14/0821 Mid-Quadrant Clearance (3D Model) 2.58” (63mm)

8/14/0822 BBC Cables

8/14/0823 Chassis 3 Chassis 3A Octant 8 Chassis 3B Octant 7

Technical Support /14/08 DeCap Access Platform Mu Tracker North Decapacitations MuTr group expects to finish North side by the end of this week

Technical Support /14/08 MuTrigger North FEE Installation Station 1 Chasis test fit LV and optical cable routing Rack cooling water supply

Technical Support /14/08 RPC2 Prototype Installation

Technical Support /14/08 RPC2 Prototype Installation, cont’d

Technical Support /14/08 RPC2 Prototype Installation, cont’d

Technical Support /14/08 To match absorber and prototype RPC’s, we need to install new FEE upgrades in these 5 MuTR FEE’s We will develop a plan to access these for installation and testing from a custom work platform (to be designed). MuTrigger FEE upgrades in MMS in support of RPC prototypes

Technical Support /14/08 RPC Absorber Concept Drawings at CS for estimating Expect quote by end of week

Technical Support /14/08 Detector upgrade Rack allotments New Platform HBD/RXNP (not shown) MuTrgrFEE N MuTrgrFEE S VTX Power FVTX NCC N NCC S RPC1 S RPC1 N New Platform RPC1 NS VTX FEM No Changes

Technical Support /14/08 Rack Room Reorganization Inventor model in progress

Technical Support /14/08 CM Crane, Station 1 scaffolding CM Crane procurement postponed Until FY09 Response from Vendor (The Bartholomew Co. local distributor for GORBEL) received. Sent to CA safety for review. Most issues fully addressed. Plan to address remaining issues this month, send to vendor for requote, place order by 9/30

Technical Support /14/08 Safety, Security, etc. 2 new generic enhanced work plans at CAD: LOTO (new rules presented in CAD training sessions last month) General Radiological Work Permit for work in CAD posted Radiation Areas (e.g. RHIC tunnel) See Ann Marie in the CAD badge office to sign the generic WP’s Summer Sunday Tour at PHENIX this week. Make sure everything is clean, IR roped off, easels, tables and chairs out for Achim.

Technical Support /14/08 Where To Find PHENIX Engineering Info Links for the weekly planning meeting slides, long term planning, pictures, videos and other technical info can be found on the web site: Only 11 more days and 215 more gold medals to go