University of Sunderland CIFM02 Unit 2 COMM02 Activity Planning Unit 2.

Slides:



Advertisements
Similar presentations
WBS: Lowest level OBS: Lowest level
Advertisements

 Chapter 6: Activity Planning – Part 1 NET481: Project Management Afnan Albahli.
Operations Management Session 27: Project Management.
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
PROJECT MANAGEMENT CPM/PERT V P B Chakravarthi. K Abhijeet Kumar.
Network Diagramming Network Analysis  The common term for network analysis is PERT  PERT stands for Program Evaluation and Review Technique  The word.
Project Scheduling Tools As part of CSA3040 © 2003, 2004 – Dr. Ernest Cachia.
Scheduling The Project  Scheduling Planning, budgeting and scheduling are all part of the same process Planning a project, developing a budget for it,
Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack amount.
PERT / CPM PERTProgram Evaluation & Review Technique CPMCritical Path Method.
1 1 Slide © 2004 Thomson/South-Western Chapter 12 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
PREPARED BY : NOR AZAH BINTI AZIZ KOLEJ MATRIKULASI TEKNIKAL KEDAH PROJECT NETWORK DIAGRAM.
MGMT 483 Week 8 Scheduling.
5/4/20151 NETWORK SCHEDULING TECHNIQUES. 5/4/20152 Network Diagrams  PMI defines the scheduling process as: “the identification of the project objectives.
Project Management OPER 576 Project Networks Greg Magnan, Ph.D. April 29, 2004.
Project Management: A Managerial Approach
Project Management A Managerial Approach
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
Activity networks – Example 1 TaskDuration (hours)Immediate predecessors A3- B4- C6- D5A E1B F6B G7C, D, E The table below shows the tasks involved in.
Chapter 6 Activity Planning McGraw-Hill Education ISBN
Projects: Critical Paths Dr. Ron Lembke Operations Management.
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
Project Management Techniques.
Lecture Network Analysis
Project Management Dr. Everette S. Gardner, Jr.. Project Management2 PERT / CPM advantages 1. Disciplined planning 2. Realistic objectives 3. Unambiguous.
Software project management (intro) Scheduling Network.
© 2000 by Prentice-Hall Inc Russell/Taylor Oper Mgt 3/e Chapter 6 Project Management.
The Critical Path – Precedence diagram method Luise Lorenz Christina Mohr.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
3 Project Management PowerPoint presentation to accompany
ENGM91 ACTIVITY PLANNING Unit 2
Project Management: A Managerial Approach
Project Management: A Managerial Approach
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
PROJECT SCHEDULING By Deepika chaudhary. Project Scheduling Scheduling means estimation of time and resources required to complete activities and organise.
Network Analysis Terminology
Objectives 4 Understand the basic concepts of project planning and control 4 Explain PERT and Timeline (Gantt) charts.
Project Management “Project Planning & Scheduling”
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
In Chapter 5: Scheduling the Project From Action Plan and WBS to Gantt chart and project network.  Gantt Chart  Project Network  Activity-on-arrow 
PROJECT MANAGEMENT Approaches
11/02/09 Chapter 7-Project Planning 1 Elements of Project Planning  Divide project into tasks, tasks into subtasks, subtasks into...  Estimate duration.
INDE 6332 ENGINEERING PROJECT MANAGEMENT SCHEDULING LECTURE 1 University of Houston Dept. of Industrial Engineering Houston, TX (713)
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
© 2006 John Wiley and Sons, Inc. Project Management: A Managerial Approach Chapter 8 – Scheduling.
Software Project Scheduling By: Sohaib Ejaz Introduction A Gantt chart is a graphical representation of the duration of tasks against the progression.
 Chapter 6: Activity Planning – Part 2 NET481: Project Management Afnan Albahli.
CHAPTER :5 SCHEDULING. Things to Learn – Precedence analysis – Gantt Charts – PERT / CPA.
Network planning models These project scheduling techniques model the project's activities and their relationships as a network. In the network, time flows.
IE 366 Chapter 6, Section 10 Project Planning and Scheduling.
Managing the Information Systems Project Cont’d
PROJECT MANAGEMENT.
Project Planning & Scheduling
Project Scheduling
Project Planning & Scheduling
Activity Planning.
Software Development & Project Management
PLANNING ENGINEERING AND PROJECT MANAGEMENT
Project Management (lecture)
Software Project Management 4th Edition
Software Project Management 4th Edition
Chapter 6 Activity Planning.
Slides Prepared by JOHN LOUCKS
Project Management CPM/PERT Professor Ahmadi.
PROJECT MANAGEMENT CPM/PERT V P B Chakravarthi. K Abhijeet Kumar.
Project Management (lecture)
Chapter 6 Activity Planning.
Scheduling.
Presentation transcript:

University of Sunderland CIFM02 Unit 2 COMM02 Activity Planning Unit 2

University of Sunderland CIFM02 Unit 2 Introduction 1 The unit will cover several methods –Precedence analysis –Gantt Charts –PERT / CPA On Arrow Networks Precedence Networks Also ….. –Microsoft Project will be covered in labs This is based on Gantt Charts and Precedence Networks

University of Sunderland CIFM02 Unit 2 Introduction 2 –Activity Planning will help to: ensure that the appropriate resources will be available precisely when required avoid different activities competing for the same resource at the same time produce a detailed schedule showing which staff carry out each activity Produce a detailed plan against which actual achievement may be measured produce a timed forecast re-plan the project during its life to correct drift from a target

University of Sunderland CIFM02 Unit 2 Precedence analysis Must be done before an activity plan can be produced Reviews the activities that are to be carried out Decides what activities must be carried out before particular activity can start

University of Sunderland CIFM02 Unit 2 Gantt Charts Developed by Henry Gantt, around 1917 Gantt charts are easy to use and produce They are very useful for use on less complex projects Commonly used due to there simplicity Gantt charts are easily understood and easy to read

University of Sunderland CIFM02 Unit 2 Gantt Charts

University of Sunderland CIFM02 Unit 2 Gantt Charts Draw the following Gantt chart TasksPrecedenceTime a-5 days b-4 days ca6 days db2 days eb5 days fc,d8 days

University of Sunderland CIFM02 Unit 2 Gantt Charts

University of Sunderland CIFM02 Unit 2 Network planning models PERT The Program Evaluation and Review Technique Developed by: –US Navy with –BOOZ-Allen Hamilton and –Lockheed Corporation for the –Polaris missile/submarine project in 1958

University of Sunderland CIFM02 Unit 2 Network planning models CPM Critical Path Method –Also know as CPA Critical Path Analysis Developed by –DuPont Inc in the –Late fifties early sixties to facilitate –building of complex process plant

University of Sunderland CIFM02 Unit 2 Network planning models PERT –developed for use on R&D projects CPM –developed for use in construction projects When developed the two techniques were very similar Now there is virtually no difference between the two

University of Sunderland CIFM02 Unit 2 Network planning models A simple on arrow network model Start End a b c d e f g h

University of Sunderland CIFM02 Unit 2 Terminology Activity –A specific task, uses resources takes time to complete Event –The result of completing an activity –Events use no resources –They are instances in time, points on the network, conditions of a system that can be recognised

University of Sunderland CIFM02 Unit 2 Terminology Network –The combination or all activities (often drawn as lines) and events (often drawn as nodes at the beginning and end of each line) defines the project and the activity precedence relationship. –Arrow heads placed on the lines indicate the direction of flow. Before and an event can be realised all the activities that immediately precede it must be completed

University of Sunderland CIFM02 Unit 2 Terminology Path –The series of connected activities (or intermediate events) between any two events in a network Critical –Activities, events, or paths, which, if delayed, will delay the completion of the project –A project’s critical path is understood to mean that sequence of critical activities (and critical events) that connect the project’s start event to its finish event

University of Sunderland CIFM02 Unit 2 Terminology On Arrow Network diagram showing critical path in red A=6 B=4 D=4 C=3 E=3 F=10 H=2 G=3

University of Sunderland CIFM02 Unit 2 Network syntax Time moves from left to right Nodes are numbered sequentially A network may not contain loops A network may not contain dangles Precedents are the immediate preceding activities Dummy activities can be used to indicate a particular precedence

University of Sunderland CIFM02 Unit 2 Network syntax Time moves from left to right Nodes are numbered sequentially 123 ab

University of Sunderland CIFM02 Unit 2 Network syntax A network may not contain loops This is not allowed a b c d

University of Sunderland CIFM02 Unit 2 Network syntax A network may not contain dangles This is not allowed a b c

University of Sunderland CIFM02 Unit 2 Network syntax Precedents are the immediate preceding activities 123 DesignBuild 4 Commission

University of Sunderland CIFM02 Unit 2 Network syntax Dummy activities can be used to indicate a particular precedence 123 Wrong Right a b c a b c

University of Sunderland CIFM02 Unit 2 On Arrow Networks Draw the following as an on arrow network TasksPrecedenceTime a-5 days b-4 days ca6 days db2 days eb5 days fc,d8 days

University of Sunderland CIFM02 Unit 2 On Arrow Networks How to start … start a b

University of Sunderland CIFM02 Unit 2 On Arrow Networks What not to do start a b c d e

University of Sunderland CIFM02 Unit 2 On Arrow Networks A better way …… start a b c d e

University of Sunderland CIFM02 Unit 2 On Arrow Networks It is then less confusing that c & d go to the same event … but what about e & f ? start a b c d e f

University of Sunderland CIFM02 Unit 2 On Arrow Networks The completed on arrow network … start a b 4 5 c d e f end

University of Sunderland CIFM02 Unit 2 On Arrow Networks Another on arrow network to draw TasksPrecedenceTime a-6 weeks b-4 weeks ca3 weeks db4 weeks eb3 weeks f-10 weeks ge,f3 weeks hc,d2 weeks

University of Sunderland CIFM02 Unit 2 On Arrow Networks The network with activity times added A=6 C=3 B=4D=4 F=10 E=3 G=3 H=2

University of Sunderland CIFM02 Unit 2 On Arrow Networks Each event circle can contain the information below Event number Earliest date Latest date Slack Event

University of Sunderland CIFM02 Unit 2 Event numbers

University of Sunderland CIFM02 Unit 2 Timed activities A=6 B=4 D=4 C=3 E=3 F=10 H=2 G=3

University of Sunderland CIFM02 Unit 2 Forward pass A=6 B=4 D=4 C=3 E=3 F=10 H=2 G=

University of Sunderland CIFM02 Unit 2 Backward pass A=6 B=4 D=4 C=3 E=3 F=10 H=2 G=

University of Sunderland CIFM02 Unit 2 Event, Slack and Activity Float A=6 B=4 D=4 C=3 E=3 F=10 H=2 G=

University of Sunderland CIFM02 Unit 2 The Complete On Arrow Network A=6 B=4 D=4 C=3 E=3 F=10 H=2 G=

University of Sunderland CIFM02 Unit 2 Precedence Networks Precedence network also known as Activity on Node Becoming more common as it is used by many project planning software packages Often preferred by project managers

University of Sunderland CIFM02 Unit 2 Precedence Networks Syntax the same as for On Arrow networks –Except there are no dummy activities Precedence networks must start with a start node and end with a end node

University of Sunderland CIFM02 Unit 2 Precedence Networks A simple precedence network Start End a b d c e f g h

University of Sunderland CIFM02 Unit 2 This is the same network drawn as an On Arrow network Start End a b c d e f g h

University of Sunderland CIFM02 Unit 2 Precedence Networks A simple precedence network Start End a b d c e f g h

University of Sunderland CIFM02 Unit 2 Precedence Networks Draw the following as an Precedence network TasksPrecedenceTime a-5 days b-4 days ca6 days db2 days eb5 days fc,d8 days

University of Sunderland CIFM02 Unit 2 Precedence Networks The completed Precedence Network Start End a b d c e f

University of Sunderland CIFM02 Unit 2 The same network drawn as an On Arrow Network start a b 4 5 c d e f end

University of Sunderland CIFM02 Unit 2 Precedence Networks The completed Precedence Network Start End a b d c e f

University of Sunderland CIFM02 Unit 2 Precedence Networks Another on precedence network to draw TasksPrecedenceTime a-6 weeks b-4 weeks ca3 weeks db4 weeks eb3 weeks f-10 weeks ge,f3 weeks hc,d2 weeks

University of Sunderland CIFM02 Unit 2 Precedence Networks The completed Precedence Network Start End a b d c e f h g

University of Sunderland CIFM02 Unit 2 This is the same network drawn as an On Arrow network A=6 C=3 B=4D=4 F=10 E=3 G=3 H=2

University of Sunderland CIFM02 Unit 2 Precedence Networks The completed Precedence Network Start End a b d c e f h g

University of Sunderland CIFM02 Unit 2 Precedence Networks Adding more information to the node ESDEF LSF LF Earliest start Duration Earliest Finish Latest Start Latest Finish Float Description

University of Sunderland CIFM02 Unit 2 Precedence Networks Redraw the following with complete information in each node box TasksPrecedenceTime a-5 days b-4 days ca6 days db2 days eb5 days fc,d8 days

University of Sunderland CIFM02 Unit 2 Precedence Networks Redraw the following with complete information in each node box TasksPrecedenceTime a-6 weeks b-4 weeks ca3 weeks db4 weeks eb3 weeks f-10 weeks ge,f3 weeks hc,d2 weeks

University of Sunderland CIFM02 Unit 2 Conclusion Activity Planning –Precedence analysis –On Arrow networks –Precedence networks

University of Sunderland CIFM02 Unit 2 Exercise 1 TasksPrecedenceTime a-6 weeks b-4 weeks c-3 weeks da4 weeks eb3 weeks fb2 weeks gc3 weeks hd,e2 weeks if1 week jg,i2 weeks

University of Sunderland CIFM02 Unit 2 Exercise 2 TasksPrecedenceTime a-3 weeks b-5 weeks ca7 weeks db5 weeks ec, d6 weeks fb4 weeks gb8 weeks hc, d4 weeks ie, f3 weeks

University of Sunderland CIFM02 Unit 2 Exercise 3 TasksPrecedenceTime a-2 weeks b-4 weeks c-3 weeks da3 weeks ea5 weeks fc6 weeks gc4 weeks hd4 weeks id8 week jb, e, f, i2 weeks k-4 weeks lg, k3 weeks

University of Sunderland CIFM02 Unit 2 Exercise 4 TasksPrecedenceTime a-3 weeks ba5 weeks ca3 weeks dc1 weeks eb3 weeks fb, d4 weeks gc2 weeks hg, f3 weeks ie, h1 weeks

University of Sunderland CIFM02 Unit 2 Exercise 5 TasksPrecedenceTime a-3 weeks b-5 weeks ca14 weeks da5 weeks eb4 weeks fb7 weeks gd, e8 weeks hg, f5 weeks