1 HST Pipeline Project Review March 14, 2003
2 Summary – Priorities Get H/W installed and available to users Transition Development and Testing groups Move pre-archive data processing to new H/W DADS/OTFR retrieval Beta testing Move DADS/OTFR retrieval processing to new H/W Populate Data Depot Transition Databases Move DADS Ingest processing
3 Schedule
4 Summary – Priorities Smooth operational transition to new processing environment No major disruptions of data flow from telescope to users due to these H/W and S/W transitions “Clean” transition is more important than pressing on schedule (~ timescales of weeks) Keeping overall schedule (timescale of year) Could require shifts in priorities Possible unexpected further problems with current H/W Possible unexpected problems with new systems