07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Electronics systems for the ClearPEM-Sonic scanner José C. DA SILVA, LIP-Lisbon Tagus LIP Group * *J.C.Silva, M.Ferreira, S.Ferreira, J.Neves, R.Bugalho, R.Silva, G.Silva, C.Ortigao, J.Varela
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Presentation Guidelines Introduction to ClearPEM-Sonic Front-end electronics and Service Boards Data Acquisition Electronics (DAE) and test boards Front End Board (FEB) Validation tests Status of scanner assembly
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Presentation Guidelines Introduction to ClearPEM-Sonic Front-end electronics and Service Boards DAE and test boards FEB Validation tests Status of scanner assembly
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA ClearPem Sonic ClearPEM-Sonic : a project in the framework of CERIMED that combines: –a dedicated mammography PET, the ClearPEM –an UltraSound transducer working in elastographic mode from SuperSonicImagine Same Electronics Mechanical structure revised Breast Contention Image fusion
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA ClearPem Sonic
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA ClearPem Sonic
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Presentation Guidelines Introduction to ClearPEM-Sonic Front-end electronics and Service Boards DAE and test boards FEB Validation tests Status of scanner assembly MADE IN LIP
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Two detector plates: 6144 LYSO 2x2x20 mm 3 crystals6144 LYSO 2x2x20 mm 3 crystals APD pixel channels12288 APD pixel channels Dual readout of crystal pixelsDual readout of crystal pixels ( for DoI measurement) 160x180 mm 2 active area160x180 mm 2 active area Water coolingWater cooling Detector Heads Electronics
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA LYSO 2x2x20 mm 3 crystalsLYSO 2x2x20 mm 3 crystals Detector modulesDetector modules 64 Xtals,4 APDs64 Xtals,4 APDs Detector Heads Electronics
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Detector Heads Electronics Characteristics Technology: CMOS 0.35μm Area: 70mm 2 Input: 192 channels Output: 2 highest channels Shaping: 40ns Analog Memories: 10 pulse samples Clock Frequency: MHz Power: 3.6 mW/channel
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Frontend Board Contains 2 ASICs for signal selection 2 High-speed dual ADCs (10bit, 100MHz) 1 LVDS transmitter (600Mb/s)Supermodule 2 FE Boards and detector modules Processes 768 APD channels Detector Plate 8 Supermodules One board for bias-voltage regulation, power supply and clock distribution Frontend Board Contains 2 ASICs for signal selection 2 High-speed dual ADCs (10bit, 100MHz) 1 LVDS transmitter (600Mb/s)Supermodule 2 FE Boards and detector modules Processes 768 APD channels Detector Plate 8 Supermodules One board for bias-voltage regulation, power supply and clock distribution Detector Plate 4.5 cm Detector Heads Electronics
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA PCB Production issues Bond Pads etching and gold plating ENIG= electroless nickel immersion gold Detector Heads Electronics
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Detector Heads Electronics Auxiliary Boards Service Board: LV, HV, Threshold, Reset, Temperature readout HV Matrix Clock Fanout Board M.Ferreira
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Service RACK DAQ Server LV and HV DSS Network Bridge Patch Pannel Isolation Transformer
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA SoftwareSoftware Service Manager Software Acquisition Manager (R.Bugalho) R.Bugalho/G.Silva
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Presentation Guidelines Introduction to ClearPEM-Sonic Front-end electronics and Service Boards DAE and test boards FEB Validation tests Status of scanner assembly
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA DAE and Trigger Crate DAE Crate System Single 19” 4U crateSingle 19” 4U crate Uses two cPCI backplanesUses two cPCI backplanes 4 DAQ Boards4 DAQ Boards 1 Trigger & Data Concentrator Board1 Trigger & Data Concentrator Board Coincidence Trigger Coincidence Trigger Energy and time determination in Virtex FPGA’sEnergy and time determination in Virtex FPGA’s Calibration constants for individual channelsCalibration constants for individual channels Programmable energy thresholds and coincidence windowProgrammable energy thresholds and coincidence window Fast link to Data Acquisition Server bandwidth up to 6.4Gb/sFast link to Data Acquisition Server bandwidth up to 6.4Gb/s
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Test Boards FE Emulator FE Emulator 5 boards manufactured and in use 5 boards manufactured and in use Important for the validation of the DAQ Boards Important for the validation of the DAQ Boards FE Receiver 7 boards manufactured, 6 in use 7 boards manufactured, 6 in use Important for the validations of the FE Boards Important for the validations of the FE Boards FEB Tester 1 board assembled 1 board assembled Important for FEB production tests Important for FEB production tests Currently under tests by INOV and LIP Currently under tests by INOV and LIP
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Presentation Guidelines Introduction to ClearPEM-Sonic Front-end electronics and Service Boards DAE and test boards FEB Validation tests Status of scanner assembly J.Neves/R.Silva
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Evaluation of FEB´s performance: Characterization and Quantification of the mean pedestal (baseline) and the ASIC Noise (pedestal RMS) Looking for dead and noisy ASIC channels FEB Validation Tests Ok to Globtop
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA ClearPEM Sonic FEBs – Test Results ASIC 0 ASIC 1 Good Results !
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA ClearPEM Sonic FEBs – Test Results P36 Bad Results ! P31 P10
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA FEB Validation Tests 1st Batch 2nd Batch - 22 FEBs CERN (C1, C2,…, C22) -> OK: 12/ FEBs Photochemie (P1, P2,…, P10) -> OK: 8/ FEBs Photochemie (P11, P12,…, P50) -> OK: 33/38
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Presentation Guidelines Introduction to ClearPEM-Sonic Front-end electronics and Service Boards DAE and test boards FEB Validation tests Status of scanner assembly
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Detector Heads All Electronics in hand Assembly of the SMs started Cables and Integration tests DAQ and Services RACK LV, HV, DSS, Network, etc : All in hand DAE ALL Boards Produced, New Crate fully equipped and in tests Scanner Assembly Status
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Scanner Assembly Status
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Scanner Mechanics Major components received and assembled Main assembly in February (cables, pipes, etc) Expected fully deliver by March Scanner Assembly Status
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Scanner Assembly Status
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Scanner Assembly Status
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA All major components are in hand or close to be delivered Important to really keep deadlines now!! System fully functional from February to have 2 month Calibration/Validation deliver the ClearPEM Scanner in Marseilles in May Thank you 30 Final words