Report from the HEBT working group + Commissioning plan and Schedule 5th HIE-ISOLDE Physics Coordination Group Meeting D. Voulot on behalf of HEBT and.

Slides:



Advertisements
Similar presentations
Accelerator Complex Status P. Collier. Linac2, Booster and PS Startup on-time, according to the schedule. Only minor problems Rapidly set-up the major.
Advertisements

1 Low-energy RHIC electron Cooler (LEReC) Update November 17, 2014.
Industrial Control Engineering Industrial Controls in the Injectors: "You (will) know that they are here" Hervé Milcent On behalf of EN/ICE IEFC workshop.
Special Linac WG meeting: Assembly of the ISOLDE Cryomodules – HIE-ISOLDE Survey and Alignment – March 19 th 2014 Jean-Christophe GaydeEN/MEF-SU Guillaume.
1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.
HIE-ISOLDE (High Intensity and Energy) project Protection of superconducting solenoids MPE work shop – December 14, 2010 G.J. Coelingh TE-MPE-CP.
HIE-ISOLDE contribution packages M. Pasini BE/RF.
HIE-ISOLDE Project Status Report Y. Kadi for the HIE-ISOLDE Project Team 49th INTC Meeting CERN, 11 February 2015.
1 Status of EMMA Shinji Machida CCLRC/RAL/ASTeC 23 April, ffag/machida_ ppt & pdf.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Status of REX and Commissioning with Beam Dr. Jose Alberto Rodriguez, BE-OP-PSB (167538)
SPS re-commissioning with beam K. Cornelis PS-SPS days.
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Commissioning Samuel Krinsky-Accelerator Physics Group Leader NSLS-II ASAC Meeting October 14-15, 2010.
HIE-ISOLDE Project Status Report
Mid Term Review Meeting, 26 September 2012D. Lanaia1 * The research project has been supported by a Marie Curie Early Initial Training Network Fellowship.
Report from HEBT Working Group B.Goddard, CERN TE/ABT On behalf.
Beam Instrumentation for the HIE-ISOLDE linac Francesca Zocca ISOLDE Workshop and Users Meeting December CERN Instituto de Estructura de la.
The Stripping Foil Test Stand in the Linac4 Transfer Line
K.Hanke – PS/SPS Days – 19/01/06 K.Hanke - PS/SPS Days 19/01/06 Recommissioning Linac2/PSB/ISOLDE from CCC  remote operation from CCC  upgrades & changes.
HIE-ISOLDE Project Status Report
The HIE-ISOLDE Faraday Cup
HIE-ISOLDE diagnostic boxes Esteban D. Cantero CERN BE-BI-PM HIE-ISOLDE meeting for BE/BI 28 March 2014 The research leading to these results has received.
HIE-ISOLDE Project Status Report Y. Kadi for the HIE-ISOLDE Project Team HIE-ISOLDE Physics Coordination WG Meeting CERN, 16 February 2015.
Overview of new high level software applications developed for the HIE- ISOLDE superconducting linac D.Lanaia*, M.A. Fraser, D. Voulot *The research project.
Report from HIE-ISOLDE HEBT WG J.Bauche‎, P.Farantatos‎, M.Fraser‎, B.Goddard, Y.Kadi‎, D.Lanaia‎, D.Nisbet‎, E.Siesling‎, G.Vandoni‎, D.Voulot‎, E.Zografos.
Maria J. G. Borge Beam Lines for HIE-ISOLDE. Status of HIE-ISOLDE 2 May 2010: 34 LoI submitted 1 Nov 2012: INTC endorsed the increase of 2 GeV-proton.
Commissioning of REX Jose Alberto Rodriguez, BE-OP-PSB (167538) on behalf of the ISOLDE operations team.
K.Hanke / TDR Meeting / 13 June 2006 Linac 4 Diagnostics L4: K. Hanke, M.Pasini (requirements, specifications, integration) AB/BI: U.Raich et al. (technical.
Floor plans, Infrastructure & Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling.
Plans and schedule for the Long Shutdown LS1 SGUI CERN, 2 February 2012 Hie-Isolde Erwin Siesling.
3 MeV test stand measurement plans A. Lombardi for the LINAC4 team 10/01/2013BCC MeV test stand measurements1.
HIE-ISOLDE Project: Planning & Resources Y. Kadi (EN-HDO) and the HIE-ISOLDE Project team.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
Layout Experimental hall Final status (?) 3rd HIE ISOLDE Physics Coordination Group meeting CERN, 3 September 2012 HIE-ISOLDE Erwin Siesling.
HIE-ISOLDE Project Status Report: Planning of Phase II 74th ISOLDE Collaboration Committee meeting November 10th 2015 Y. Kadi.
HIE-ISOLDE Project Status Report 50th ISOLDE & nTOF Technical Committee meeting July 1st 2015 Y. Kadi.
Krzysztof Radwan, PJAS, TE/VSC/ICM Interlocks, Controls and Monitoring Section HIE-ISOLDE Vacuum Controls INSTALLATION.
INJECTORS BLM SYSTEM: PROGRESS REPORT Christos Zamantzas on behalf of the BLM team. MSWG 28/08/2015.
Status of the Solenoid Status of procurement Plans for transport Storage and tests on arrival at CERN Installation in the ISOLDE Hall Location Footprint.
O. Kester, NuSTAR annual meeting, 27/02/2013
HIE-ISOLDE Project 3 rd beam line + HELIOS June 16th 2015 (updated on June 18th) Y. Kadi, S. Maridor.
Plans and schedule for the Long Shutdown LS1 Hie Isolde Physics Coordination Group CERN, 1 March 2012 Hie-Isolde Erwin Siesling.
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
1. Baseline – from LMC  Presentation by F. Bordry at LHC Machine Committee 5.10 on LS1 Organisation: 1. Linac4 is not going to be connected.
Programme for the Physics Start-up Stable and radioactive beams Jose Alberto Rodriguez, BE-OP-PSB (167538)
ELENA installation progress F. Butin / ELENA collaboration.
Installation at Isolde (and costs) TSR at Isolde workshop CERN, 29/30 October 2012 Isolde Erwin Siesling.
PANAGIOTIS FARANTATOS(TE/MSC-MNC)* WP3, ESR 4: New Magnet
J.-L. Sanchez Alvarez(PSB-EIC)
Status HIE ISOLDE installation and shutdown work
LIU Wire Scanner Milestones June 2017
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
LHC schedule.
Performance of BI systems at HIE-ISOLDE
BE-BI Software for LINAC4
WIC deployment and commissioning in HIE-ISOLDE
Beam instrumentation for HIE-ISOLDE
HIE-ISOLDE Status Report
HIE-ISOLDE Project: Planning & Resources
HIE-ISOLDE Status & Summary of HIE-ISOLDE SC
Magdalena Kowalska, CERN PH-SME-IS
LINAC4 commissioning plans etc.
Electron Source Configuration
Report on HIE-ISOLDE Status
CERN’s MidTermPlan and the consequences for HIE-ISOLDE
Advanced Research Electron Accelerator Laboratory
HIE-ISOLDE contribution packages
Ciprian Plostinar Workshop on Testing and Commissioning
ThomX – Commissioning Meeting – 25/01/2018
Accelerator Installation Schedule
Presentation transcript:

Report from the HEBT working group + Commissioning plan and Schedule 5th HIE-ISOLDE Physics Coordination Group Meeting D. Voulot on behalf of HEBT and commissioning Working Group 1/4/2014

HEBT layout Objectives : 03/11/14 XT00-XT01 available for tests 12/01/15 XT02 available for tests Inventory : 22 MQ + 41 PC (22+19 for REX) 4 MB + 4 PC 11 MC + 22 PC (1 per plane)

Magnets – All contracts placed; magnet manufacturing budget within estimates – Magnets production in line with prioritised installation planning Power converters – All contracts placed, some pre-series already at CERN – In-line with planning except for quadrupole power supplies. Second and third batch delayed -> no impact on commissioning planning Beam Instrumentation – Two types of DB (linac/HEBT) – Some uncertainties in the delivery of the long DBs – Should not affect machine start-up Vacuum – Vacuum chamber design on-going, delivery Sept-Oct 14 – Most component standard CERN contracts Support, Infrastructure, Survey – Infrastructure installation on-going – Magnet support installation as of mid-April Procurement status

Control – Warm Magnet Interlock (WIC) – Interlocks for Cryogenics, Vacuum, SCRF – Control hardware (Front End Computers) and timing Specification released, cabling/equipment requested, installation Oct-Nov. 14 Console application – Use standard BE-CO applications and tools Working set/knobs INCA database, TIMBER, DIAMON Specification of low level control on-going with equipment groups – Update existing REX applications E.g. BI application current and beam profile acquisition Energy scanner (beam energy and energy spread) Functionalities and layout defined, will be finalised (BE-OP) when the low level controls are available – Only develop new tools when necessary Linac phase-up Setting generator Time-of-flight system On-going, some high level application are already available Control and software

Commissioning planning (HEBT and SC linac) Periodic dry-runs – Periodic test of the machine in realistic conditions (≠ hardware tests) – Start as soon as the first equipment become available (Nov 14?) – Increasing step by step the scope of the dry-runs – Document the progress Machine ready-to-go date: 24 July 2015 – At this point the machine should be fully operational! Machine check out: 4 weeks – 1 st dry run with all components (including SCRF) – Some buffer time for debugging Beam commissioning: 7 weeks Oct 15 -> HIE-ISOLDE Physics

Dry run Check-list Magnets -> Polarity check -> WIC -> Current acquisition -> Field regulation -> Test console applications Beam instrumentation -> Test FC with current source -> Actuator movement -> Interlocks -> Si detector Control -> Test console applications -> TIMBER logging Vacuum Monitor and control REX-HIE vacuum from PVSS application. Cryo Monitor cryogenics from PVSS application. RF -> Remote start/stop of SCRF -> Acquisition of amplitude and phase -> Check NC and SCRF synchronisation * Planning: to be defined according to availability of equipment (new planning) * Prepare individual check-list for each dry-run

Machine check-out If periodic dry-run scheme works: – 27 July 2015 = machine ready for beam – Check that all the systems are ready to go (including SC linac) => max 1 week – Start beam commissioning If not: 4 weeks spare for debugging … if more physics is delayed

Beam commissioning 1.Stable beam from REXEBIS -> 1/6/ Beam transport through the SC part (solenoids only no RF) and transfer lines at 0.3 MeV/u -> 2 weeks 3.Commissioning of beam instrumentation with beam -> 1 week 4.Cross-check of the alignment with beam -> 1 week (optional) 5.Phase-up of the NC and SC linac using a dipole as energy spectrometer, establish voltage calibration and absolute phase error -> 2 weeks 6.Establish some base settings for different A/q and energies, measure transmission and energy spread, inject beam through Miniball -> 1 week 7.A/q scaling test at fixed energy -> 1 week 8.Beam characterisation: transverse and longitudinal emittances -> 2-3 weeks (optional) 9.Energy scaling for a fixed A/q (optional) 10.Test of OP software: setting generator and automatic optimiser (optional) 11.Energy measurement with TOF system (optional) * Minimum 7 weeks (only mandatory steps) * Full beam characterisation can be postponed to subsequent shutdowns * Some diagnostics and tools are not mandatory for delivering beam

Operation with one cryomodule Between October 2015 and 2015/16 shutdown only one cryomodule (5 cavities) will be available. Can we run with a missing cryomodule? The beam blows up but remains well inside +/- 20 mm aperture of the magnets The beam can be matched into the transport channel with the marching quadruplet without losses ±20 mm

Operation with one cryomodule No replacement optical elements needed, or movement of quads, if there is no second cryomodule in Phase 1. This assumes that the aperture after the first cryomodule is that of the HEBT at ±20 mm. Transverse emittance assumed as 0.35 mm.mrad (rather conservative, consistent with measurements). Max. available energy:

Operation with HIE-ISOLE Keep current operation scheme – ISOLDE operation team (daytime) – IMS piquet service (night and weekends) – No 24/24 shift – 24/24 CCC supervision (need training of PSB operators) Supervision of the cryo-plant and SC linac – Cryo-piquet during the first year (expect many intervention) – CCC supervision (TCR) when the system is more mature – RF piquet? (for the moment best effort system, has been working very well) Need OP team reinforcement (ISOLDE + REX + HIE +TSR?)

HEBT Working group members ANDREAZZA, William (BE-BI-ML) BAUCHE, Jeremie (TE-MSC-MNC) BRAVIN, Enrico (BE-BI-PM) CANTERO, Esteban Daniel (BE-BI-PM) FARANTATOS, Panagiotis (TE-MSC-MNC) FORMENTI, Fabio (TE-HDO) FRASER, Matthew Alexander (BE-RF-BR) GARCIA BORGE, Maria Jose (PH-SME-IS) GARCIA SOSA, Alex (BE-BI-PM) GAYDE, Jean-Christophe (EN-MEF-SU) GODDARD, Brennan (TE-ABT) HANKE, Klaus (BE-OP-PSB) KADI, Yacine (EN-HDO) KAUTZMANN, Guillaume (EN-MEF-SU) KOLEHMAINEN, Antti Juhani (EN-MME-EDS) KOWALSKA, Magdalena (PH-SME-IS) LANAIA, Davide (BE-OP-PSB) LEIBA, Benjamin (EN-MEF) MARTINO, Michele (TE-EPC-HPM) MERTENS, Volker (TE-HDO) MOMPO, Richard (TE-MPE-MS) NICQUEVERT, Bertrand (EN-MEF-QOP) SIESLING, Erwin (BE-OP-PSB) TIMMINS, Marc (EN-MME-EDS) VANDONI, Giovanna (TE-VSC-IVM) VENESS, Raymond (BE-BI-ML) VOULOT, Didier (BE-OP-PSB) ZOGRAFOS, Eleftherios (EN-MEF-INT) HIE Commissioning group members FADAKIS, Eleftherios (BE-OP-PSB) FRASER, Matthew Alexander (BE-RF-BR) LANAIA, Davide (BE-OP-PSB) SANCHEZ ALVAREZ, Jose-Luis (BE-OP-PSB) VOULOT, Didier (BE-OP-PSB) WENANDER, Fredrik John Carl (BE-ABP-HSL)