13 September 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Delivery Installation Connector work Testing Summary.

Slides:



Advertisements
Similar presentations
Status of EC-C assembly at Liverpool C Buttar EC PAR, Nikhef Nov 04.
Advertisements

Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
CMS Week March presented by John Coughlan RAL FED Hardware Status Pre-Series Manufacture Final Production Plans.
27 September 2005A.Ciocio - ID Week1 SCT Service Installation Overview Status of Type IV Cable Installation Type II/III Cable Installation Plan for the.
Seog Oh/ Duke University/June, 2003 TRT/ ATLAS week at CERN Duke Production Status.
SCT Power Supply Installation Schedule Jan Bohm, Prague AS, 4 th November 2005 The SCT Power Supply System will be installed in 22 LV&HV racks situated.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
G.Barber Tracker Update, Berkeley 10 Feb Tracker Progress Contents:- Station Space Frame Patch Panel / Vacuum Seal Light Guide Map Position of Degrader/Support.
LAr ROD Status Arno Straessner and Alain, Daniel, Annie, Manuel, Imma, Laurent, Eric, Jean-Pierre, Gilbert,... ATLAS Geneva DPNC January 12 th, 2005.
GLAST LAT ProjectF-to-F, June 15, TrackerR.P. Johnson 1 GLAST Large Area Telescope: Tracker, W.B.S Face-To-Face June Meeting Robert Johnson.
Walls crates cables gas chambers electronics CERN adb.
31 January 2006A.Ciocio - SCTSG1 Type IV cables and PP3 Installation Type IV installation Connector in situ work Status of PP3 Testing.
29 November 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status of Type IV installation Connector in situ work Status of PP3 Testing.
LARG week 07/01 Paul Poffenberger University of Victoria Endcap Feedthrough Production at Victoria Status Summary.
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia SCT week, Valencia, June 2002 Pre-series Low Mass Tapes 12 different lengths were produced for barrel.
TMDB delay and production plan Augusto. TMDB Prototype Status The prototype boards almost fully assembled should be delivered this week ( May 5 th ) First.
25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.
ID week - 26 September 2006 A. Ciocio1 SCT Services Installation SCT Cables Web page
Pippa Wells25 October Procurement and manpower for service installation Services readiness dates Planning for type ii/iii Fibre installation dates.
Activities Status and Plan for the week D. Giugni / INFN Milano D. Giugni Monday Meeting
Status of CERN M1R2 production LHCb Muon meeting sept.061Thomas Schneider -Beginning of 2006 two visits to Erbicol because of several reasons: -Material.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
8 June 2006A.Ciocio - SCTSG1 SCT Services Installation Type IV PP3 Type II-III and PP1 Testing & Installation Plan Workpackage
CMX Production Status Presented to the L1Calo Meeting on Monday 22-Sept-2014 by Dan Edmunds for the CMX Group.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
13 June 2013Laurent Roy Optical Fibers / Electronics Upgrade -Fibers need for Upgrade -> Installation ? -Two techniques possible for multi fibers installation.
G.Barber KEK Test Beam Update, Berkeley 9 Feb KEK Test Beam – Tracker Progress Contents:- Station Space Frame Light Guide Map Station Connectors.
Abe Seiden December 2003 SCT Week S USA SCT Barrel Module Assembly SCT Week CERN December 2003 Presented by Abe Seiden U.C. Santa Cruz.
r1Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling YB+2 and YB+1, extension to minus wheels and YB0, cables between UXC55 and USC55.
M. Gilchriese Sectors, Rings, Frame Assembly and Installation July 18.
18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page
Technical Support Activities in PH-ADO-PO
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
14 December 2005A.Ciocio - SCTSG1 Services and Patchpanels Installation Type IV installation Connector in situ work Status of PP3 Type II/III Testing.
LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,...
Status of NA62 straw electronics Webs Covers Services Readout.
The status of RF components on Maria Filippova, RF components: Loads Phase shifters Attenuators Hybrids Splitters Directional couplers.
7 March 2006A.Ciocio - SCTSG1 SCT Services and Patch Panels Type IV PP3 Type II-III and PP1 Fibres Heaters DCS Testing Workpackage
9 May 2006A.Ciocio - SCTSG1 SCT Services Installation Type IV PP3 Type II-III and PP1 Fibre Cables DCS Testing & Installation Plan Workpackage
1 ME1/1 ODMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project.
Pending mechanics issues for electronics/services (updated 18/08/05 by Ana) Fixation/shielding for 2 LV PS (no fingers):  - Clermont worked out a proposal.
SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
D. Greenfield CLRC1 UK-V End-cap Engineering 15 July 2003 Debbie Greenfield, RAL.
M. Gilchriese Items from Talks U.S. Pixel Meeting Santa Cruz July 2003.
Services in GIF++ A pictorial record of the work HV Cables LV cables DCS cables Signal Cables Ian Crotty 17 Dec 2014.
Cooling & Ventilation feed-back M. Nonis – EN/CV.
25 October 2005A. Ciocio - SCTSG1 Type II/III Cables and PP1 Status & Plan.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
Lavs Issues Lav 12. Tube Planning future activities. Conclusions.
8 June 2006A.Ciocio - SCTSG1 Status of Type IV Cables Cables production –resumed in February after 3 months stop –See ID week February ‘06 Delivery of.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
V. Bobillier1 Cable installation status.
Substation L1/ MCC L1 Update #2 July 27,2012. Status of Procurement  Substation  All approval drawings submitted  Testing is expected to take place.
31 January 2006A.Ciocio - SCTSG1 Type ii-iii and PP1 Production Timescale for installation Plan PP1and Testing.
9/12/2003Ivan Hruska1 First box prototype –Box design in July ‘03 –Box produced during August ’03 Tested last week in few fingers Small changes necessary.
Progress and plans for HO Installation S. Dugad, K. Sudhakar Tata Institute of Fundamental Research India-CMS Meeting at BARC, July 2005.
6 September 2007VELOEddy Jans 0 VELO-installation++ activities September 6, 2007 General items Detector installation plans.
PIP Update July 29 th Agenda Summary Update – Current Activities – Updates Tom Kubicki (Station 20,21,22 – Gallery and Equipment Work) – Additional.
1 Update on Power Supplies TB L.Jirden u LV u Concerns u Orders & deliveries u Maintenance u HV u Overview u purchasing.
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
News about the WA104 Programme C. Montanari – INFN and CERN technical working group meeting, September 16,
ATLAS ID Services Mock Up - Proposal Presented by Ian Wilmut at DESY, update from John Hill 4th May, 20101ATLAS Upgrade - RAL.
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
H.-G. Moser, April 25, 2016 Gemba Summary 1 Plan: Shipment (sea transport in summer) 6-8 weeks => arrival August/September Commissioning: After October.
Cabling for LHCb Upgrade
Francois and Lau EATM 17 July 2012
Nearly the end of a long story...
Presentation transcript:

13 September 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Delivery Installation Connector work Testing Summary

13 September 2005A.Ciocio - SCTSG2 Delivery 685 pieces (double length cables) delivered 337 to complete US side Delivery in July/August very slow –Vacation and QA problems Connectors quality Bobbins damage –Bobbins already at CERN are going to be sent back to the fabrication company (Novacavi) to get cleaned up Delay of components delivery from CERN to company Need to keep contact with CERN purchasing and Vendor Ramp up –200 pieces/week expected soon after bobbins damage crisis is solved but so far the max number of pieces we have seen is 120 –Hopefully all type-IV delivered by mid-November

13 September 2005A.Ciocio - SCTSG3 Delivery (QA - Connectors) Connector’s signal wires too long Some cables couldn’t be used One week halt of production

13 September 2005A.Ciocio - SCTSG4 Delivery (QA - Packaging) Packaging: palette were sent with only plastic wrap around bundles Cables were getting wet during transportation and delivery at CERN About 40 cables lost (~30 in one delivery)

13 September 2005A.Ciocio - SCTSG5 Delivery (QA - Bobbins) Cable bobbins dirty and damaged Bobbins are kept outside (at CERN) for long time Other (than water) damage under investigation Company claims delay in fabrication to deal with these problems Don’t know yet delay due to shipping bobbins back to Italy

13 September 2005A.Ciocio - SCTSG6 Installation Double length cables are pulled and routed from PP3 racks in UX15, through holes, to power supply racks in US15 (and USA15) side –9 PP3 racks going to US and 9 to USA Racks to US side –4 racks completed –5 half/almost completed Team of Russian Tech’s from TC can install 40 double length cables/day –Work closely with Sergei Malyukov and the team –Provide complete layout/mapping for racks in both sides Bjarne is still helping from Bergen –Regular presence to check mapping/labels and prepare racks –Discussion on installation priority and occasional revise original layout –update DB table Racks to USA side will be ready to accept cable in 2-3 weeks

13 September 2005A.Ciocio - SCTSG7 PP3 to US PP3 rackUS rackhole UX/US Y.37-1.X6Y S212 Y.43-1.X6Y S211 Y.43-1.X6Y S210 Y.47-1.X6Y S210 Y.43-1.X6Y S29 Y.47-1.X6Y S29 Y.52-1.X6Y S27 Y.52-4.X7Y S27 Y.52-4.X7Y S221 Y.53-4.X7Y S220 Y.53-2.X2Y S26 Y.51-2.X2Y S219 Y.53-4.X7Y S219 Y.51-2.X2Y S25 Y.52-1.X6Y S25 Y.52-2.X2Y S24

13 September 2005A.Ciocio - SCTSG8 Installation (PP3) Cables are plugged in a few dummy Patch Panels to be installed in the right (final) position and tightened to horizontal bars They will have to be all removed from the current position and plugged in by groups/rows when the installation of the real PP3 will occur First 100 units will arrive end of September (around the 26th) but they will be already burned-in (ready for installation after only reception test) The remaining 4000 will be produced 2-3 weeks later in October Shaun Roe and Igor Ilyashenko with the help from Pamela Ferrari and Ewa Stanecka will set up testing and burn-in It would have been desirable to have PP3 in place while installing cables to avoid the additional dummy plugging in and the extra (and more difficult) work of plugging cables in an already fully populated rack (Ashley French will be at Cern Oct3) –More people will be needed to work on US side racks By the time the units are received and burned in we will be ready with the installation of the racks to the USA side Units should be sent with no additional delays and burn-in plan might need to be revised We’ll work on a scheme that agrees with the schedule where some will be sent air freight and the rest surface (same for steel enclosures, rails and strain relief bars)

13 September 2005A.Ciocio - SCTSG9 Rack Scheme for PP3

13 September 2005A.Ciocio - SCTSG10 Connectors work Double length cables are cut and connectors are installed in situ (US/A sides) First rack (200 cables/connectors) completed in July –Work performed by SEDELEC (subcontract of KontaktSysteme –Many mistakes (~30 connectors need repair) still to be fixed and they raised the cost significantly New Plan –Engineer from TC will be the contact with a new company (suggested by Marzio) and to work with Petr Kubik (Prague). –Meeting with company soon to discuss technical aspects and see if and for how much they can do the work –Meanwhile cables are being cut to some extra length and ~ all tooling has been purchased to make prototypes –Plan for working in the US15 behind the racks (Petr)

13 September 2005A.Ciocio - SCTSG11 Testing Tester designed and provided by Ljubljana (Gregor, Erik) –2 Test box + 2 Laptops + test cables –Gregor and Erik upgraded features of tester in July –Web based DB (last week) –Next visit Sep 26 Test steps: –Cables are tested at reception (acceptance test) –After being pulled from UX15 to US(A)15 (uncut-double length) –After they are cut in the US side at connectors are installed Shift planner (developed by D. Robinson) works very well for planning the activities and have people to sign up –(and contact me) What is needed to be able to take a shift: 1)take the safety training course (at the pompiers station) Special course on September 27 th at 12:45 2)make the access request on EDH 3)get your safety boots & helmet (or borrow them)

13 September 2005A.Ciocio - SCTSG12 Testing Shift Counts Assuming 2 people in shift for every step and 3 hour shift (9-12h or 14-17h) –Acceptance test100 shifts(unit=1 person-shift) –Test in rack100 shifts –Complete cable400 shifts Participation of all SCT collaboration to shifts is crucial to keep up with installation schedule –First attempt (by Mike) to consider sharing amongst all SCT institutes UK 150 shifts Japan 90 shifts US 80 shifts Norway 30 shifts Nikhef 20 shifts Uppsala 20 shifts Valencia 20shifts Slovenia 10 shifts Cracow 5shifts Czech 5 shifts Russia 5 shifts –And 200 shifts among Australia CERN Germany Switzerland After Mike’s call I had a positive response but need to discuss formula that works better for smaller participation and a more predictable presence when at regime

13 September 2005A.Ciocio - SCTSG13 Current Shift Counts per Institute Institute Total CompletedPending Prague19163 Bergen19190 Geneva18162 Valencia11110 CERN550 Okayama440 UC Santa Cruz330 LBL330 Kyoto330 UCL220 KEK220 Cracow220 Ioffe110

13 September 2005A.Ciocio - SCTSG14 Summary Delivery of Cables –Need to improve QA of components –Follow up with company Installation –Ramping up Connector work –New plan PP3 –Need units without delays and help with installation Testing –Will work if a more predictable presence when at regime