Optimisation of Entry Capacity Strawman Transmission Workstream 4 th May 2006.

Slides:



Advertisements
Similar presentations
UK Gas Entry Regime – Review of existing Interruptible Arrangements & Potential Reforms for this Winter.
Advertisements

Commercial Arrangements For Gas Quality Service – Process UNC Transmission Workstream 23 rd April 2007.
UNC Mod 485: CMP-LTUIOLI Progress Update 3 April 2014.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
The Treatment of “Spare / Sterilised” Capacity – follow up Draft for discussion purposes only.
Entry Capacity Release Methodology Statement Transmission Workstream, 4 th May 2006.
Capacity trade and transfer mechanism and the next AMSEC auction Nienke Hendriks Head of Gas Transmission Policy, Enforcement and Compliance 9 May 2007.
1 CODE MODIFICATION PROPOSAL No 0243 Amendments to the process for initialisation of Enduring NTS Exit (Flat) Capacity at the Moffat NTS Exit Point Presentation.
GRI NW Investment Workshop Chris Logue, European Policy Manager, 4 th June 2010 The Hague.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Transfer & Trades Special Transmission Workstream
The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream
Capacity Release Processes and Investment Planning Transmission Planning Code Workshop 2 1 st May 2008.
Transfer & Trades Special Transmission Workstream
Entry Capacity Substitution Workshop 7 – 10 th February 2009.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Entry Capacity Substitution Workshop 9 – 7 th July 2009 DRAFT PRESENTATION.
Transfers and Trades Transmission Workstream
Discretionary Release of Non Obligated NTS System Entry Capacity Transmission Workstream 1st May 2008.
Modification Proposal 0246: Quarterly NTS Entry Capacity User Commitment Chris Shanley.
Assignment of NTS Entry Capacity Transmission Workstream 06 November 2008.
Classification: Statoil Internal Status: Draft Mod 156/156a Questions regarding the proposals…
Update on Entry Capacity Substitution Transmission Workstream 6 th March 2008 Summary of consultation responses.
Entry Capacity Substitution Workshop 2 7 th May 2008 Substitution Example.
Review Group 221: Option 3 – security provided after allocation.
Exit Capacity Substitution and Revision Transmission Workstream meeting, 3 rd December 2009.
Mod Clarifications Transmission Workstream 6 August 2009.
Review of Entry Capacity and the Appropriate Allocation of Financial Risk Review Group th Sept 2008.
Initial Thoughts on the Release of Non Obligated NTS System Entry Capacity Transmission Workstream 3 rd April 2008.
Capacity Methodology Statements Transmission Workstream 5 th July 2007.
Entry Capacity Substitution Workshop 3 11 th June 2008 Substitution Example.
Implementation of Trades and Transfers National Grid NTS 5 th June 2008.
Entry Capacity Trading Transmission Work Stream, 5 April 2007.
September 2008 QSEC auction - Allocations Transmission Workstream
Fundamental review of entry charging principles UNC Transmission Workstream - 6 th August 2009.
Transmission workstream 6 April Overview of TPCR Third Consultation UNC transmission workstream – 6 April Mark Feather.
Entry Capacity Substitution Workshop 4 9 th July 2008 Entry Capacity Substitution Methodology Statement: Discussion Paper.
Facilitating Release of Non-obligated Entry Capacity Draft – for discussion purposes only 22 November 2007.
Entry Capacity Substitution: Discussion Document Transmission Workstream 7 th August 2008 Initial Analysis of Responses.
DRSEC Update Transmission Workstream 06 November 2008.
Entry Capacity transfers in the constrained period Transmission Workstream 5 th October 2006.
Trades and Transfers Workshop, 6 th November 2007.
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.
Mod Entry Capacity Transfers Transmission Work Stream, 5 April 2007.
Transfers and Trades Special Transmission Workstream
Force Majeure Existing FM situation: Up to 200GWh/d capacity shortfall due to the rejection of NG’s planning application for a PRI in Corse / Tirley area.
Development Modification Proposal: Introduction of an Inter-day Linepack Product Review Group August 2010 Transmission Workstream 07/10/2010.
NTS Exit Regime Transmission Workstream – 6 th July 2005.
The Entry Capacity Substitution Regime Transmission Workstream 7 th February 2008 Thoughts for discussion.
DN Interruption Reform Transmission Workstream Mark Freeman 5 th April 2007.
Entry Capacity Overrun price calculation
Transmission Workstream, 01 October 2009
Non-approved draft Transmission Workstream, 6th December 2007
Transmission Workstream, 2nd March 06
Entry Capacity - update
Capacity Methodology Statements: Impact of Mod 452
Exit Overruns in the Enduring Regime - draft MOD principles
NTS Entry Charging Review Update
Capacity Methodology Statements
Exit Capacity Substitution and Revision
Modification 501 slides for Workgroup
Long Term Non Firm Capacity Update
Review of Trade and Transfer Winter 09/10
Transmission Workstream – 6th July 2005
Richard Fairholme E.ON UK
Modification Proposal 0133 – “Introduction of AMTSEC auction”
Optimisation of Entry Capacity Modification Proposal
Modification 0043 – Limitation on offering for sale unsold capacity
Entry Capacity Transfers - Constrained Period
Revised Tender Timescale for DN Interruption Arrangements
Presentation transcript:

Optimisation of Entry Capacity Strawman Transmission Workstream 4 th May 2006

Current Arrangements  Under the current regime we are obliged to release up to baseline levels at all ASEPs until a clearing allocation has been held.  In the last AMSEC auction we had some ASEPs that had sold out and were oversubscribed whilst others had unsold capacity.  We can release non-obligated capacity  If the revenue generated from releasing this capacity is not exceeded by the forecast costs associated with the release i.e. entry constraints and buy backs.  Historically we have only released non-obligated capacity in the constrained period close to the gas day.

Issues  This can create a scenario where capacity is effectively sterilised  In the event that we did look to release non- obligated capacity at more than one ASEP we do not have a non discriminatory process by which it could be achieved  These proposals look to address these issues

Optimisation of Entry capacity – Key Features The process for optimisation of entry capacity can be broken down into 5 key areas;-  Identification of recipient ASEPs  This establishes which ASEPs require additional capacity  Identification of donor ASEPs  This establishes which ASEPs have capacity available for transfer  Identify demand for transferable capacity  This identifies the amount of capacity required at the recipient ASEP  Exchange Rate  This establishes the cost of transferring capacity between from the donor ASEP(s) to the recipient ASEP(s) and therefore indicates the value required to successfully bid for capacity.  Allocation methodology  This establishes how the capacity is allocated between competing recipient ASEPs and competing Users.

Identification of recipient ASEPs  Identification of recipient ASEPs  It is proposed that ASEPs which have demand for capacity in excess of baseline levels would become the ‘recipient ASEPs’  This would take place after the AMSEC auction and would look at the period April to March

Identification of Donor ASEPs - Options  All ASEPs  This would make every ASEP with unsold capacity or with capacity being offered back to National Grid a donor ASEP.  ASEPs within local vicinity  This would identify only ASEPs in the same geographical area as the donor ASEP(s)  Donor ASEPs will have a physical interaction with recipient ASEP.  Lowest cost ASEP  This would identify only one ASEP as the donor and would be based on the cheapest capacity available to transfer to the recipient ASEP  In the event that this donor ASEP didn’t have enough capacity to meet demand then the next lowest cost ASEP would then be selected.

Transferable Capacity The proposals for identifying capacity available for transfer are as follows:-  Unsold Capacity  After completion of the AMSEC auction any unsold capacity at the donor ASEP(s) would be available for transfer.  Sold Capacity  After completion of the AMSEC auction we could hold a tender at the donor ASEP to buy back firm capacity and if a User wished to sell then this capacity would become available for transfer

Identify demand for transferable capacity  This would be done by holding an AMTSEC auction for the identified recipient ASEPs.  Auction rules would be similar to existing AMSEC  Pay as bid  Applications could be for [April] to [March]  The invitation could include:-  The [1] date on which the auction would be held  The reserve price for the recipient ASEP(s)  The recipient ASEP(s)  Indicative exchange rate  Valid bids would identify level of demand for transferable capacity at the recipient ASEPs.

Exchange Rates  There is a requirement to establish the value of the transferable capacity, this accounts for;  the expected change in supply profile  the buy back risk of transferring the capacity between ASEPs.  The exchange rate sets the value of transferring the capacity between the donor ASEP and the recipient ASEP.

Allocation methodology  The basis of the allocation process is to maximise the release of the transferable capacity. This is achieved by;  Assessing the cost of transferring the capacity from the donor ASEP (through the exchange rate)  Assessing the value of the bids for the transferable capacity at the recipient ASEP (through the AMTSEC auction)  Allocate capacity until the cost of transferring the capacity exceeds the value of the bids for the capacity  This is relatively straight forward if there is one donor ASEP and one recipient ASEP.  High degree of complexity when there are multiple donor and recipient ASEPs

Treatment of costs and revenues It is proposed that the costs and revenues would be managed through the existing incentive mechanism  The revenues generated by the sale of the capacity are based on the forecast cost of transferring capacity  Impact on Users through neutrality and impact on incentive should be minimal

Commercial Framework  The following amendments have been identified as being required to facilitate the process  UNC  Amendments to facilitate ‘new’ AMTSEC auction and allocation process  Amendment to move current AMSEC auction  Licence  Amendment to change the obligation to release baselines and/or clearing allocation

Timetable (option 1- post AMSEC) NovLTSEC Allocation confirmed Issue Invitation letter for AMSEC DecHold AMSEC auction Identify recipient ASEP(s) Identify donor ASEP(s) Issue invitation letter for AMTSEC Issue buy back tender for donor ASEP(s) JanHold AMTSEC auction Feb – MarComplete allocation process MarConfirm allocations (including successful buy back tender) Apr – Mar Capacity transfer effective

Timetable (option 2 – pre AMSEC) AMSEC auction completed Identify recipient ASEP(s) Identify donor ASEP(s) NovIssue invitation letter for AMTSEC Issue buy back tender for donor ASEP(s) DecHold AMTSEC auction Dec – FebComplete allocation process FebConfirm allocations (including successful buy back tender) Apr – Mar Capacity transfer effective

Timetable  NG to consider bringing forward a draft UNC proposal to June Workstream  Submit Mod Proposal to July Mod Panel