R2E relocation & shielding activities Anne Laure Perrot EN/MEF- LE R2E project meeting, 23 rd October 2012
Outline 1.R2E mitigation activities - status 2.R2E LS1 planning 3.Documentation 4.Organisational aspects R2E project meeting, 23rd October 2012A. L. Perrot, EN-MEF/LE2
Areas of the R2E mitigation activities Main critical areas today considered UJ76 UJ14/16 RR13/17 UJ56 RR53/57 US85 R2E project meeting, 23rd October 2012A. L. Perrot, EN-MEF/LE3
Status of the mitigation activities Actions already performed – shielding ( ) Point 1: RBs/UJs Points 2 & 8: UJ22/23/88/87 Point 7: UJ76 wall Point 6: ducts between RAs/UAs 63/67 Xmas break 2011 RBs and UJs in LSS1, Xmas break 2011 R2E project meeting, 23rd October 2012A. L. Perrot, EN-MEF/LE4
Shielding activities Christmas break Point 1: RBs/UJs 5
Shielding activities Christmas break R2E project meeting, 23rd October 2012A. L. Perrot, EN-MEF/LE6
2008: UX85 cryogenics cold compressor system, PLCs QURCA & QUICC : UPS removed from UJ : UX85 cryogenics valves positionners (QURCA, QUICC) 2009: US85 fire & ODH detector control racks and associated detectors units Christmas break: UJ56/76 EN/EL RTUs UJ56/76 fire & ODH detection control racks TS4: UJ14/16 PIC TS5: cryogenics US85 CPU (QURCb) Actions already performed – relocation ( ) Status of the mitigation activities R2E project meeting, 23rd October 2012A. L. Perrot, EN-MEF/LE7
Actions already performed – relocation ( ) 2011 Xmas break Point 1: Fire detectors (from RR13/17 to US15) Points 4/6: cryogenics CPUs (from UX to UL) Point 5:UPS (from UJ56 to UL557) UL557: Civil engineering activities (ducts, vault along 20 m) Point 8: Ethernet racks (startpoint) (from US85 to UL86) WIC & timing racks (from US85 to UA83) QURCb & rack EYQ (from US85 level 2 to lUS85 level 0) 2012 Technical Stops (TS1-3) Point 1: cable trays, survey references, empty racks installed in ULs Point 5: cable trays, GGPSO preparatory work for installation, UL557 new lightning, pipes survey of the UL557 by CE Point 7: cables trays, survey references, empty racks moved to nominal location EL preparatory work before wall dismantling Point 8: cable trays Status of the mitigation activities R2E project meeting, 23rd October 2012A. L. Perrot, EN-MEF/LE8
Actions to be performed during Xmas break 2012 Relocation Point 1: cable trays, if time start cables installation, Point 5: UL557: GGPSO installation, cable trays modification, new lightning UJ56: survey activity to link UJ56 to LHC tunnel framework Point 7: power sockets replacement Point 8: start installing the UPS cables between US85 and UA83, Shielding Point 8: CE activities (rail installation) for US85 mobile shielding Status of the mitigation activities R2E project meeting, 23rd October 2012A. L. Perrot, EN-MEF/LE9
Relocation Point 8 Point 5 Point 1 Point 7 Shielding Points 1, 5, 7 & 8 Integration studies R2E activities in Point 8 Point 5 Point 1 Point 7 Planning – LS1 Finished and approved Sequences finished Merged into LHC LS1 planning Status of the mitigation activities R2E project meeting, 23rd October 2012A. L. Perrot, EN-MEF/LE10
R2E LS1 planning work by M. Barberan R2E project meeting, 23rd October 2012A. L. Perrot, EN-MEF/LE11
Point weeks Start = End of April 2013 End = mid July 2014 Point 5 – 68,5 weeks Start = mid April 2013 End = Aug Point 7 – 54 weeks Start = May 2013 End = June 2014 Point weeks Start = mid May 2013 End = mid Dec R2E LS1 planning work by M. Barberan & K. Foraz R2E project meeting, 23rd October 2012A. L. Perrot, EN-MEF/LE12
13 Criticality Point 1: EL 45 weeks, CV 33 weeks Point 5 : EL 59 weeks (2 shifts), CV 32 weeks (2 teams), CE 9 weeks No margin! Anticipation in implementation (2012 Technical stops) 20 days in total Profit of each day & each available ressource Minimise the criticality level Point 7 : EL 58 # weeks, CV 16 weeks, CE 9 weeks & Very close supervision of work in-situ Material procurement Installation procedures Key points to avoid delays Storage areas management R2E LS1 planning
Constraints by LHC activities Exception: Point 1- preparatory work start during ELQA sectors 12 &81; but equipment unplug only after ELQA R2E after ELQA tests in adjacent sectors Constraints on LHC activities Point 1: Cool down starts when R2E commissioning activities are finished Point 7: Cryo and 3 VAC control racks (insulation vacuum control for QRL and cold magnets) relocated and commisionned before the cool down can start in adjacent sectors. Point 5: - Cool down depends of the R2E cryo activities - Shielding transport via Pt4/6 and/or via PM54 => co-activities with LHC and/or CMS to be optimised Pt5 planning may slightly change R2E LS1 planning R2E project meeting, 23rd October 2012A. L. Perrot, EN-MEF/LE14
Integration studies Documentation (1/2) Title= %integration R2E% (exact) in EDMS: 32 documents R2E project meeting, 23rd October 2012A. L. Perrot, EN-MEF/LE15
- ‘Protection of equipment located in UJ76 ‘ (Phase I, edms: ) - ‘Mobile shielding for RR73/77’ (edms: ) - ‘Protection of equipment located in US85’: Phase I (edms: ) & Phase II (edms ) - ‘Strategy against SEE for Fire and Oxygen deficiency detection systems’ (edms: ) - ‘Protection of equipment located in UJ56’ ( edms: ) - ‘R2E shielding for LHC Points 1, 5, and 8’ (edms: ) - ‘Protection of equipment located in UJ14 and UJ16’ (edms: ) - ‘Protection of equipment located in UJ76 (phase II)’ : under preparation Documentation (2/2) ECRs All in EDMS :/projects/LHC machine/LHC R2E Project/related documents/Integration and Installation :/projects/LHC machine/LHC R2E Project/related documents/Integration and Installation R2E project meeting, 23rd October 2012A. L. Perrot, EN-MEF/LE16
Organisation towards LS1 - R2E relocation & shielding meetings are now weekly from mid November focus on installation & material issues - Work-package analysis Point 1 : 28/09/2012 Point 5: 19 & 26/10/2012 Point 7: 9 & 16/11/2012 Point 8: 10/09/2012 Documents by Maria (soon in edms for approval) - Installation drawings checks Start in December by EN/MEF-int if drawings available Drawings provided by EN/EL and EN/CV (firm) - Installation procedures Request by EN/MEF-OSS at the end of the WPA Follow-up in R2E meetings (start mid-November) ICL LS1 & R2E meetings R2E project meeting, 23rd October 2012A. L. Perrot, EN-MEF/LE17
Critical points during LS1 implementation Integration Material Intermediate survey scansBE/ABPFollow-upEqpt owners & services - procurement - storage before installation - Installation non conformities Cross-checks with modelsEN/MEF Delays vs planning Installation Follow–up & adaptationEN/MEF Required actionTeam Critical points Day-to-day in-situ supervision EN/MEF, BE/OP Management of storage areasEN/MEF R2E project meeting, 23rd October 2012A. L. Perrot, EN-MEF/LE18
19 1. Day-to-day in-situ management & supervision (rapidly react/solve problems of all nature as they occurred, direct contact with the groups supervisors, cleaning/ waste management) 5. Planning: follow – up and adaptation (detailed installation planning & critical path weekly updated, impact on/of the non R2E works) 3. Material delivery & contracts: weekly follow – up 6. Communicating (periodical reviews of the activities, non conformities & planning) 2. Safety supervision (sites managers to enforce safety and environment protection rules, ‘VIC’, follow the implementation of safety measures/procedures) 4. Integration: non conformities follow-up (weekly reports, intermediate survey scans ) Organisation during the LS1 installation R2E implementation & worksite organisation R2E Point coordinator in charge R2E point coordinator involved
Main concerns – Review 2011 Integration Technical solution proposed by EN DSO and M. Brugger to DGS/SEE: Fire proof racks in TZ76 (see Markus presentation) - Relocation of EN/EL equipment located in the UJ56 safe room - TZ76 separating wall dismantling Worksite supervision – R2E point coordinators Point 1: M. Jeckel Point 5: B. Lefort Point 7: O. Andujar Point 8: B. Mikulec Storage requests (surface- tunnel) - Space already reserved in surface for shielding blocks - Material storage under the equipment owners responsibility (discussed during work-package analysis) R2E project meeting, 23rd October 2012A. L. Perrot, EN-MEF/LE20
Main concerns towards LS1 Integration - Installation drawings Checks by LHC integration team (ICL) Should start in Dec with EN/EL – EN/CV - Cables trays in USC55 Discussion with CMS and EN/EL Material procurement Manpower Regular follow-up by R2E will start mid November Equipment owners should finalise their requests R2E project meeting, 23rd October 2012A. L. Perrot, EN-MEF/LE21
Summary Integration & planning studies = finished R2E activities will start Mid April 2013 ECR documentation almost finished (Pt7 ECR missing) WPA : in progress Main concerns raised during R2E 2011 review= solved Main concerns towards LS1: Installation drawings & procedures, material requirement, storage areas, manpower Follow-up start Mid November in the R2E relocation & shielding meetings R2E project meeting, 23rd October 2012A. L. Perrot, EN-MEF/LE22
Addendum
R2E LS1 planning Evolution Point 5 7/06/2012 54 weeks 12/06/2012 64,5 weeks (10 weeks ) CV No work in // with EL CV 2 Teams EL 2 Shifts 13/07/2012 66,5 weeks No works during Christmas (2 Weeks) 10/08/2012 67, 5 weeks Transport UTAs (1 Week) 23/10/2012 68,5 Weeks ERD & Power Converters Board (1 Week)
LS1 R2E civil engineering activities Point 5: UL557-UL558: 2 ducts Ø350mm R2E work package analysis, 10 th September 2012A. L. Perrot, EN-MEF/LE25 UL557: mini ‘safe room’ implementation UL557-UJ56: 4 ducts 16 m long Ø400mm UJ56 – LHC tunnel: 5 ducts Ø350mm Point 7 TZ76 wall dismantling
access EL UPS: already relocated in TZ76 Point 7 – Relocation Equipment to be relocated outside UJ76- level 0 inside blue thick borders equipment to be relocated. 48 V dc system CO AUG CO Anti-panic ligthning R2E work package analysis, 10 th September 2012A. L. Perrot, EN-MEF/LE26
Point 7 – Relocation TZ76 equipment layout after relocation Today: extremity of the separating wall R2E work package analysis, 10 th September 2012A. L. Perrot, EN-MEF/LE27