5/1/2014 1 PHENIX WEEKLY PLANNING May 1, 2014 Don Lynch.

Slides:



Advertisements
Similar presentations
4/11/20131 PHENIX WEEKLY PLANNING 4/11/2013 Don Lynch.
Advertisements

2/6/ PHENIX WEEKLY PLANNING Feb. 6, 2014 Don Lynch.
12/12/ PHENIX WEEKLY PLANNING Dec. 12, 2013 Don Lynch.
6/19/2014 PHENIX WEEKLY PLANNING June 19, 2014 Don Lynch 1.
8/7/2014 PHENIX WEEKLY PLANNING August 7, 2014 Don Lynch 1.
PHENIX WEEKLY PLANNING 6/7/2007 Don Lynch. 6/7/2007 Weekly Planning Meeting 2 Schedule End of Run Party 6/29/07 Next Maintenance Day No More Planned Remove.
7/3/2014 PHENIX WEEKLY PLANNING July 3, 2014 Don Lynch 1.
9/26/ PHENIX WEEKLY PLANNING Sep. 26, 2013 Don Lynch.
5/15/ PHENIX WEEKLY PLANNING May 15, 2014 Don Lynch.
1/30/ PHENIX WEEKLY PLANNING Jan. 30, 2014 Don Lynch.
3/6/ PHENIX WEEKLY PLANNING March 13, 2014 Don Lynch.
2/9/20121 PHENIX WEEKLY PLANNING 2/9/2012 Don Lynch.
PHENIX WEEKLY PLANNING 5/17/2007 Don Lynch. 5/17/2007 Weekly Planning Meeting 2.
10/10/ PHENIX WEEKLY PLANNING Oct. 10, 2013 Don Lynch.
6/6/ PHENIX WEEKLY PLANNING 6/6/2013 Don Lynch Note: No PHENIX planning meeting this week due to end of run party. Feel free to discuss safety and.
5/9/ PHENIX WEEKLY PLANNING 5/9/2013 Don Lynch.
11/7/ PHENIX WEEKLY PLANNING Nov. 7, 2013 Don Lynch.
8/9/20121 PHENIX WEEKLY PLANNING 8/9/2012 Don Lynch.
12/26/2013-1/2/ PHENIX WEEKLY PLANNING Dec. 26, Jan. 2, 2014 Don Lynch.
7/17/2014 PHENIX WEEKLY PLANNING July 17, 2014 Don Lynch 1.
12/5/ PHENIX WEEKLY PLANNING Dec. 5, 2013 Don Lynch.
PHENIX WEEKLY PLANNING 5/24/2007 Don Lynch. 5/24/2007 Weekly Planning Meeting 2 Schedule End of Run Party 6/29/07 Next Maintenance Day 6/6/07 Remove HBD.
12/29/20121 PHENIX WEEKLY PLANNING 12/29/2011 Don Lynch.
5/29/ PHENIX WEEKLY PLANNING May 29, 2014 Don Lynch.
6/26/2014 PHENIX WEEKLY PLANNING June 26, 2014 Don Lynch 1.
6/12/2014 PHENIX WEEKLY PLANNING June 12, 2014 Don Lynch 1.
7/3/2014 PHENIX WEEKLY PLANNING July 10, 2014 Don Lynch 1.
1/9/ PHENIX WEEKLY PLANNING Jan. 9, 2014 Don Lynch.
4/10/ PHENIX WEEKLY PLANNING April 10, 2014 Don Lynch.
1 PHENIX WEEKLY PLANNING December 3, 2015 Carter Biggs.
7/31/2014 PHENIX WEEKLY PLANNING July 31, 2014 Don Lynch 1.
PHENIX WEEKLY PLANNING 6/29/06 Don Lynch. 6/29/2006 Weekly Planning Meeting 2 This Week TOF W tests continue, modification decisions made? New HV connector.
3/6/ PHENIX WEEKLY PLANNING March 6, 2014 Don Lynch.
8/21/2014 PHENIX WEEKLY PLANNING August 21, 2014 Don Lynch 1.
PHENIX WEEKLY PLANNING 1/10/2008 Don Lynch. 1/10/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
PHENIX WEEKLY PLANNING 2/9/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
5/22/ PHENIX WEEKLY PLANNING May 22, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 9/14/06 Don Lynch. 9/14/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown '065/1/200612/8/2006.
1 3/10/2011 PHENIX WEEKLY PLANNING 3/10/2011 Don Lynch.
1 PHENIX WEEKLY PLANNING January 21, 2016 Carter Biggs.
PHENIX WEEKLY PLANNING 10/4/2007 Don Lynch. 10/4/2007 Weekly Planning Meeting 2007 PHENIX Shutdown October 2007: Finish MPC South Installation, replace.
3/22/20121 PHENIX WEEKLY PLANNING 3/22/2012 Don Lynch.
2/14/20131 PHENIX WEEKLY PLANNING 2/14/2013 Don Lynch.
4/24/ PHENIX WEEKLY PLANNING April 24, 2014 Don Lynch.
5/16/ PHENIX WEEKLY PLANNING 5/16/2013 Don Lynch.
6/5/ PHENIX WEEKLY PLANNING June 5, 2014 Don Lynch.
3/20/ PHENIX WEEKLY PLANNING March 20, 2014 Don Lynch.
4/17/ PHENIX WEEKLY PLANNING April 17, 2014 Don Lynch.
12/6/20121 PHENIX WEEKLY PLANNING 12/6/12 Don Lynch.
6/28/20121 PHENIX WEEKLY PLANNING 6/28/2012 Don Lynch.
5/8/ PHENIX WEEKLY PLANNING May 8, 2014 Don Lynch.
8/7/2014 PHENIX WEEKLY PLANNING August 14, 2014 Don Lynch 1.
5/24/20121 PHENIX WEEKLY PLANNING 5/24/2012 Don Lynch.
12/19/ PHENIX WEEKLY PLANNING Dec. 19, 2013 Don Lynch.
PHENIX WEEKLY PLANNING 5/7/2007 Don Lynch (Thursday is Monday this week)
12/20/20121 PHENIX WEEKLY PLANNING 12/20/12 Don Lynch.
SPHENIX MECHANICAL D. Lynch September 11, AGENDA Global Design Concept – Updated Global Assembly Concept – Updated Inner HCal Installation concept.
DON LYNCH OCTOBER 28, October 28, 2014 sPHENIX Detector Integration & Assembly Concept.
SPHENIX MECHANICAL D. Lynch, R. Ruggiero June 12, /12/2014sPHENIX Mechanical Design.
5/30/20131 PHENIX WEEKLY PLANNING 5/30/2013 Don Lynch.
3/7/20131 PHENIX WEEKLY PLANNING 3/7/2013 Don Lynch.
12/08/20111 PHENIX WEEKLY PLANNING 12/08/2011 Don Lynch.
2/27/ PHENIX WEEKLY PLANNING Feb. 27, 2014 Don Lynch.
SPHENIX Mechanical Don Lynch & Rich Ruggiero April 10, 2014.
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
1 7/9/2009 PHENIX WEEKLY PLANNING 7/9/2009 Don Lynch.
12/6/20121 PHENIX WEEKLY PLANNING 12/13/12 Don Lynch.
PHENIX WEEKLY PLANNING 6/8/06 Don Lynch. 6/8/2006 Weekly Planning Meeting 2 This Week Rec’d TOF West Access: move HBD to Dead Turtle Position Sec’y of.
2/20/ PHENIX WEEKLY PLANNING Feb. 20, 2014 Don Lynch.
SPHENIX Mechanical Don Lynch & Rich Ruggiero April 10, 2014.
Presentation transcript:

5/1/ PHENIX WEEKLY PLANNING May 1, 2014 Don Lynch

5/1/ This Week Run 14 Continues Controlled access last Friday – replaced DC.W FEM, PbGl power supply Yesterday’s scheduled access DC West wire 4(?) wires removed MPC-Ex FEM replacement not needed fixed problems from rack VTX small external leak repaired. Plan for 2014 Shutdown Tech Support for Run 14 as required Support for sPHENIX efforts as required

5/1/ Next Week Run 14 Continues No access next week, next access 5/14 Plan for 2014 Shutdown Tech Support for Run 14 as required Support for sPHENIX efforts as required

5/1/ MPC-Ex N & S Final Installations This summer

5/1/ planned Technical Support & 2014 Shutdown Support for run 142/3-6/30/2014 Procure & Fabricate parts for MPC-Ex North and South1/1/2014-6/30/2014 Assemble & test MPC-Ex South, ready for installation3/1-7/1/2014 End of Run Party (Move to 7/7 or 7/8?) 7/11/14? MuID Efficiency Measurement (Itaru, requires cooling water & isobutane)7/7/14 Assemble & test MPC-Ex North, ready for installation7/1-9/25/2014 Start of Shutdown Tasks (purge flammable gas, disassemble and stow shield wall, remove collars, move EC to AH, Move MMS south, etc.)7/14 – 7/25/2014 Remove FVTX/VTX East to PHYSICS?, repair and reinstall7/14 – 9/15/2014 Remove MMS east vertical lampshade 7/28-7/30/2014 Troubleshoot intermittent water leak in MMS7/30- 8/8/2014 Other Maint. In MMS TBD Reinstall MMS east vertical lampshadeTBD Summer Sunday prep AH, tours and restore AH7/30-8/15/2014 Install scaffolding in Sta 1 South7/28/2014 Remove MPC-Ex prototype, Install new MPC-Ex South7/28-8/22/2014 Maint. & Repairs for MPC South, BBC South, RPC1 South, MuTr sta 1 South, as necessary7/28-8/22/2014 Remove scaffolding from sta 1 south, Move CM South8/25/2014 Install scaffolding in Sta 1 North8/26-8/29/2014 Prep MPC-Ex North installation area9/1-9/26/2014 Install new MPC-Ex North9/29-10/17/2014 Remove Sta 1 North scaffolds, Move CM North 10/20-10/24/2014 Other detector supportTBD Infrastructure Maintenance and ImprovementTBD Decommissioning of obsolete PHENIX detector equipmentTBD sPHENIX Supporton-going End of Shutdown Tasks (Move MS north, roll in EC, install collars, remove 10 ton cart, plates and manlifts, build shield wall, etc.)10/27-11/26/2014 Pink/White/Blue Sheets1/17/2014 End of Shutdown Party???? Start Flammable gas flow???? Close shield wall, install radiation interlocks and prepare for run 1412/31/2014 Start run 151/2/2015

5/1/2014 sPHENIX “Outie” Concept This is the design we will continue to pursue until if and when a final decision directs us to the “innie” option 6

5/1/2014 HCal Central Pedestal V1 7

sFHENIX HADRON CALORIMETER 90 degree Support Structure Analyses ANSYS MODULE. MESH sPHENIX Mechanical Design May 1, 2014

sFHENIX HADRON CALORIMETER 90 degree Support Structure Analyses ANSYS MODULE. DEFORMATION sPHENIX Mechanical Design DUE TO NOT SYMMETRICAL ABSORBER STRUCTURE MODULE INCLINED TO ONE SIDE 1 mm = ” May 1, 2014

sFHENIX HADRON CALORIMETER 90 degree Support Structure Analyses ANSYS MODULE. EQUIVALENT STRESS sPHENIX Mechanical Design 1 MPa = p.s.i. May 1, 2014

5/1/ Additional Support Concepts

5/1/2014 sPHENIX Engineering: Major Subsystems/Subtopics: Magnet (BABAR) (Magnet Div) start 2/1/ /31/2018 Hadronic Calorimeter (HCAL) (PHENIX) start 2/1/ /31/2020 EM Calorimeter EMCal (PHENIX) start 2/1/ /31/2020 VTX (RIKEN)start 2/1/ /31/2020 DIRC (?)start ? - 12/31/2020 VTX additional layers (RIKEN)start ? - 12/31/2020 Carriage Support structure (PHENIX)start 2/1/ /31/2020 Readout Electronics (PHENIX)start 2/1/ /31/2020 Infrastructure (PHENIX ++) Electrical Power Services (PHENIX)start ? - 12/31/17 Instrumentation Support start ? - 12/31/2020 (Signal trays & Racks) (PHENIX) Cryo Services (CAD)start 2/1/14 – 8/1/18 Cooling water (CAD)start ? - 12/31/2017 Safety Systems (PHENIX )start ? - 12/31/2020 Work Platforms and Access/Egress start ? - 12/31/2017 Structures (CAD) HVAC (CAD)start ? - 12/31/2017 PHENIX Decommissioning start ? - 6/30/2017 (CAD, PHENIX) System Integration (PHENIX)start 2/1/ /31/2020 Testing (PHENIX)start 2/1/ /31/2020 Installation (PHENIX, CAD)start 2/1/ /31/2020 Commissioning (PHENIX)start 2/1/ /31/

May 1, 2014 sPHENIX Mechanical Design Magnet (BABAR) (Magnet Div) Acquire rightsDone Evaluate Transport5/1/14 Design Transport fixtures 5/1/14 Fabricate Transport Fixtures 6/1/14 Evaluate BNL test facility requirements 6/1/14 Prepare test facility8/1/14 Install Transport fixtures8/1/14 Transport to BNL 9/1/14 Install in test facility10/1/14 Design tests/test equipment10/1/14 Fabricate/procure test equipment1/1/15 Run tests6/1/15 Design Magnet modifications12/1/14 Fabricate magnet modifications6/1/15 Install magnet modifications8/1/15 Evaluate final installation9/1/15 Design installation support equipment12/31/2016 Fabricate/procure support equipment7/1/2018 Transport to IR7/1/2018 Install10/31/2019 Test 11/31/2019 Commission12/31/2019

5/1/ ePHENIX 2ft high x 1 ft wide clearance needed for e-ring components

5/1/ Safety and Security From Ray Karol: Anyone need ladder training?

5/1/ PHENIX Safety and Security

5/1/

5/1/ Where To Find PHENIX Engineering Info Run 14 Continues! Kentucky Derby This Week! Have a mint Julep And Watch the horses run. Favorites: California Chrome (PP 5, 5-2) Hoppertunity (PP 11, 6-1) Wicked Strong (PP 20, 8-1) My long shot picks: We Miss Artie (PP 7, 50-1) and Wildcat Red (PP 10, 15-1)