West Contra Costa Unified School District Facilities Subcommittee Meeting December 2, 2014 State School Facility Program Seismic Funding Update.

Slides:



Advertisements
Similar presentations
General Obligation Bond Presentation December 14, 2010.
Advertisements

Surveillance and Access Control The Process. Step 1: Create RFP for Head-End and FOC RFP Submitted – 4 vendors submitted proposals Must have Genetec and.
WCCUSD Bond Program Project Status Report
West Contra Costa Unified School District Facilities Subcommittee Meeting March 11, 2014 State School Facility Program Seismic Funding Update.
School Facility Program Update County School Facilities Consortium September 25, 2012 Presenters: Lisa Silverman, Executive Officer Rick Asbell, Chief.
FACILITIES SUBCOMMITTEE MEETING Emergency Repair Program June 12, 2012 Presented by: Jamie Iseman, Senior Associate Jack Schreder & Associates.
PINOLE VALLEY HIGH SCHOOL FACILITIES SUBCOMMITTEE MEETING December 13, 2011.
The E-rate Program Category 2 Budgets Fall 2014 Applicant Trainings Washington K-12 Statewide Training, November 10, 2014 Presentation posted at
FRED POWELL POWELL & PARTNERS, ARCHITECTS West Contra Costa Unified School District.
WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT HIBSER YAMAUCHI Architects DOVER ES PHASE II SITE IMPROVEMENTS FEBRUARY 27, 2014 DOVER ELEMENTARY.
LUCIA MAR UNIFIED SCHOOL DISTRICT Facilities Update Facilities Master Plan & Sustainability Projects Information.
West Contra Costa USD Presentation to the Facilities Subcommittee April 23, 2013.
California Department of Education Pre-State Allocation Board Meeting May 25, 2011 Presented By.
Riverside Overpass Master Planning Presenters: Sally Swanson & Magdy Abdalla June 11, SALLY SWANSON ARCHITECTS, INC. Riverside Elementary School.
Presented By: Lisa LeBlanc, Associate Superintendent Framing the Next Steps – Bond Program Facilities Subcommittee – 2/26/15 DRAFT.
Board of Trustees Meeting November 20,  On May 15, 2012 Board of Trustees authorized Administration to pursue a feasibility study and cost analysis.
Idaho Code Allocation for School Building Maintenance (HB 743) Schools must allocate at least 2% of the replacement value of school buildings.
West Contra Costa USD Facilities Sub Committee June 12, 2012 Peres Elementary School School Facility Program Funding Update.
West Contra Costa USD Tax Rate Resolution Presentation to the Board of Education August 13, 2014.
The Overcrowding Relief Grant (ORG) The State Allocation Board & The Office of Public School Construction Presented by Lina Lyda.
Calistoga Joint Unified School District Measure “A” Citizens’ Oversight Committee Meeting October 27, 2011.
WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT HIBSER YAMAUCHI Architects CALIFORNIA CHILDRENS SERVICES (CCS) OVERVIEW AND RELOCATION (3/13/12)
Bond Construction Update Citizens Oversight Committee Long Beach Community College District October 24, 2011 EDUCATE  ENGAGE  EMPOWER 1.
CAREER TECHNICAL EDUCATION FACILITIES PROGRAM Cycle 2 Conversions.
Texas Department of Public Safety Public Assistance Disaster Closeout.
Calistoga Joint Unified School District Measure “A” Citizens’ Oversight Committee Meeting December 19, 2012.
WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT HIBSER YAMAUCHI Architects DOVER ELEMENTARY Existing MPB (2/14/12)
WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT HIBSER YAMAUCHI Architects.
Portola Middle School and Gompers/Leadership Public Schools OPSC Funding Status Update.
Presented By: Lisa LeBlanc, Associate Superintendent Recommendation on Valley View ES Facilities Subcommittee – January 6, 2014.
1 West Contra Costa Unified School District December 7, First Interim Financial Report.
Page 0 The Role of the California School Finance Authority Katrina Johantgen July 13, 2009 Charter School Facilities Program 2009 Funding Round.
Facilities Interview Cindy McDaniel DSUSD Assistant Superintendent Business Services Maria E. Haigh Lupe Valdivia Marissa Fulache.
Request for Proposals: Energy Conservation Projects December 17, 2015.
S T A T E O F C A L I F O R N I A. Expediting the Application Review Process Building Schools — Putting Californians to Work.
West Contra Costa USD Presentation to the Facilities Subcommittee Bond Budget Update March 17, 2012.
STATE OF CALIFORNIA Green Schools in a Red Economy Pacific Energy Center September 21, 2010 Presented by the Office of Public School Construction (OPSC)
Pre-State Allocation Board Meeting October 26, 2011 Presented By California Department of Education.
State Allocation Board Meeting December 15, 2010 Presented By.
1 West Contra Costa Unified School District January 4, Budget Update.
West Contra Costa Unified School District Long-Range Facilities Master Plan West Contra Costa Unified School District Long-Range Facilities Master Plan.
West Contra Costa Unified School District Long-Range Facilities Master Plan West Contra Costa Unified School District Long-Range Facilities Master Plan.
Bond Package - $386 million $386 Million – No tax rate increase (25 year bond)  Funds all proposed unfunded maintenance, all high and medium high seismic.
West Contra Costa Unified School District Long-Range Facilities Master Plan WCCUSD.net/FMP Facilities Subcommittee Option Recommendation April 19, 2016.
Measure N Modernization IMPLEMENTATION PROCESS Planning, Bidding, Construction, and Occupancy.
Atkinson, Andelson, Loya, Ruud & Romo A Professional Law Corporation CERRITOS ● FRESNO ● PLEASANTON ● RIVERSIDE ● SACRAMENTO ● SAN DIEGO Board Member Liability.
1 Overview of the public school construction process: State agencies Construction Management Task Force December 2007.
Smart Schools Bond Act LAURENS CENTRAL SCHOOL. What is the Smart Schools Bond Act?  The Smart Schools Bond Act (SSBA) authorized the issuance of $2 billion.
SMITHVILLE R-II SCHOOL DISTRICT Tradition of Excellence The Power of One … One Community … One Future! November 4, 2014 SMITHVILLE R-II SCHOOL DISTRICT.
West Contra Costa Unified School District Facilities Subcommittee Meeting April 9, 2013 School Facility Program State Funding Update.
Presentation to Board of Education 1 August 2014 Facilities Capital Plan Board of Education Update August 18,
State Allocation Board Meeting November 3, 2010 Presented By.
West Contra Costa USD General Obligation Bond Program Status Presentation to the Facilities Subcommittee June 11, 2013.
Title Slide Los Banos Unified School District Presented by Lori Raineri February 24, 2005 Moving Forward with Funding Community Facilities District No.
“702 KAR 4:160, Capital construction process” 1.  To be developed as procedures document for K-12 school construction projects  Allows KDE to update.
West Contra Costa Unified School District Long-Range Facilities Master Plan WCCUSD.net/FMP Board of Education Workshop February 27,
Presentation to Board of Education 1 August 2014 Facilities Capital Plan Board of Education Update August 28,
Ken Casey, BEP, CSDP Manager, Business Development-California Lynwood Unified School District Presentation for Board of.
2017 Measure X First Quarterly Meeting
Plano ISD 2016 Bond Program.
Utah Water Conservation Forum – 5/12/2017
Pinole Valley High School (PVHS) Project Status
Humboldt energy project presentation
David Salazar, Chief Facilities Executive
REEF SUNSET UNIFIED SCHOOL DISTRICT
Lehighton Area School District
Pinole Middle School Soccer Field
DISTRICT vs. SITE ALLOCATION
Measure – V Facilities Update April 8th, 2019
SSUSD Richmond Elementary Status to Board of Education May 2, 2019
Presentation transcript:

West Contra Costa Unified School District Facilities Subcommittee Meeting December 2, 2014 State School Facility Program Seismic Funding Update

Agenda State Seismic Program Process – Division of the State Architect (DSA) Eligibility Process – Office of Public School Construction (OPSC) Funding Process Status of State Seismic Funds Status of Potential Funding for District Projects

Eligibility and Funding Process DSA Eligibility Process – Phase 1 – Program Eligibility Eligible Building Type DSA Concurrence with Structural Engineer Report that Determines Building Collapse Potential Due to Ground Shaking, Faulting, Liquefaction, Landslide – Phase 2/3 – Replacement/Rehabilitation Funding DSA Concurrence with Structural Engineer Report on Minimum Required Work to Mitigate Seismic Safety Issue Cost Benefit Analysis to Determine Replacement v. Rehabilitation Funding – Phase 4 – Final DSA Approval of Project Plans

Eligibility and Funding Process OPSC Funding Process – Request for Funding Funding Request Submitted to OPSC Once DSA Eligibility Process is Complete and Project Plans Receive California Department of Education Approval Secures Your Place in Line for Funding – Funding Determination Funding for Buildings that Qualify for Rehabilitation Equals 50% of OPSC Approved Rehabilitation Cost Funding for Buildings that Qualify for Replacement Equals $292 per Square Foot of Toilet Area and $162 per Square Foot of Non-Toilet Area of OPSC-Determined Eligible Replacement Square Footage

Status of State Seismic Funds $199.5 MillionTotal Set Aside from Proposition 1D $50.5 MillionAmount Apportioned $7.0 MillionAmount on Unfunded List $142.0 MillionAmount of Remaining Authority $6.6 MillionAmount on Workload List $138.3 MillionNet Available Funding as of November 25, 2014 (last State Allocation Board Meeting) Additionally, there have been six projects approved by SAB as Conceptual Approvals. If converted to Full Funding Requests, these projects could result in an additional $46.3 M drawdown from the available funding. Note: Of the $50.5M apportioned $13.9M was for Korematsu MS, which is more than any other district in the State has received for seismic funding.

Projects in Receipt of Seismic Funding: – Korematsu Middle School - $13.9M in State Funding Received Projects Submitted to OPSC for Seismic Funding: – Gompers Continuation High School Projects with Phase 2/3 Approval: – Juan Crespi Middle School – Pinole Valley High School Status of Potential Funding for District Projects

Projects with Phase 1 Approval: – Richmond High School – Helms Middle School – Valley View Elementary School – DeAnza High School Projects Submitted to DSA for Phase 1 Approval: – Kennedy High School Projects with Phase 1 Reports Complete: – El Cerrito High School – King Elementary School Status of Potential Funding for District Projects

Projects Deemed Ineligible: – Downer Elementary School – Lake Elementary School – Nystrom Elementary School – Ohlone Elementary School – Riverside Elementary School – Washington Elementary School Status of Potential Funding for District Projects

Evaluating Seismic Funding for Projects Including Upcoming Projects and Completed Projects Where the District Proactively Addressed Seismic Issues at School Sites Status Chart Attached that Indicates: – School Site – Buildings – Project Architect, Structural Engineer, Cost Estimator – Status of Project in DSA Eligibility and OPSC Funding Processes

Status of Seismic Projects

Questions