K.Gadow CALICE technical review 1 Move to FNL ECAL/HCAL-Movable Table Setup test beam integration to Fermilab MT6-B3/B4
K.Gadow CALICE technical review 2 ECAL/HCAL Movable Table Setup no change in basic dimension
K.Gadow CALICE technical review 3 Setup in test beam area update beam area ground dimension HCAL Movable Table placed in MTB6-B3 ? ECAL/HCAL Movable Table Control room ?
K.Gadow CALICE technical review 4 Setup in test beam area inner height ? other equipment ? shielding concrete roof support dump
K.Gadow CALICE technical review 5 Setup in test beam area one escape route is sufficient ? Escape rote from B4 blocked
K.Gadow CALICE technical review 6 Setup in test beam area crane height and crane load critical needed hook height over roof 4 m transport weight 15 tons
K.Gadow CALICE technical review 7 Setup in test beam area total height ~ 4 meter
K.Gadow CALICE technical review 8 Setup in test beam area permanent closed roof (except openings) installation of Movable Table HCAL and ECAL with “tricks” only installation of HCAL modules in position B3 critical crane needed !
K.Gadow CALICE technical review 9 Infrastructure at Fermilab (Joe Howell) Power Conversion –Experiment 2 x 50 Hz 400 VLL A –Standard Fermilab 60 HZ, 208v/120v or 480v –Initial checks indicate there is no existing on- site conversion equipment –Continue checking options Data Transfer –Desire at least 1 Gbit/s Eathernet Link –Erik Ramberg is checking current capacity
K.Gadow CALICE technical review 10 Operations Readiness Clearance (Joe Howell) Approval given by the Fermilab Partical Physics Division Head indicating that the experiment is safe to operate Safety Review Committees –Mechanical and Conventional Safety –Electrical –Fire (and flammable gas) Documentation Review and Equipment Inspection Help provided to guide through the process