Impact of Increasing Meter Errors on the SEM Modifications Committee Meeting 65 3 rd December 2015.

Slides:



Advertisements
Similar presentations
INTRA-DAY TRADING: Conference Call COD for Interconnector Units in WD1 Ending Overlap Optimisation Period (EOOP) 29 November 2011.
Advertisements

Background T&SC V9.0: The Market Operator shall not grant the status of Under Test for the purposes of this Code to Autonomous Generator Units, Pumped.
1 Loss Adjustment When Exporting Mod 24_11 Reflection of Physical Fixity of Interconnector Flows in Operational Data Transactions hen Exporting Modifications.
Overview of Make Whole Payments Modifications Committee Meeting February 2015.
1 Mod_24_10 Introducing Loss of Profits as a Relevant Damage within the Limitation of Liability Provisions.
Mod_03_12 Alignment of TSC with Revised VAT Arrangements 29 th May 2012.
Global Aggregation Working Group 15 th September 2010.
Global Aggregation Working Group 15 th September 2010.
MPID 223 (Failure to Follow Synchronising Instruction) JGCRP 12 th November 2014 (Anne Trotter)
Wind Power in Ireland: Treatment of wind in the Single Electricity Market APEx Conference, Paris 16 th October 2007.
INTRA-DAY TRADING DESIGN Future Options for Limited Communication Failure (LCF) 27 September 2011.
Short Term Testing Mod 65_08 Modification Committee 25 th November 2010.
MARKET SYSTEM RELEASE UPDATE Modifications Committee Meeting 31 January 2012.
INTRA-DAY TRADING Development of Modification(s) 1st February 2011.
Challenges for the SEM.  Day-ahead price coupling is a key feature of the final draft Framework Guidelines on congestion management issued by ERGEG in.
PRR 568 – Settlement Timeline PRR 638 – Invoice Timeline PRR 599 – Mismatch Notification COPS January 2006 Updates.
Unit Registration Process Improvement SEMO 05/12/2012.
Metering Modification to T&S code Cathal Kearney Protection & Metering 15/04/2015.
Single Electricity Market Update Liam Ryan SEMO. Background 2 years in operation Gross Mandatory Pool All Suppliers All Generations units over 10 MW Trading.
SEM – One Year On Liam Ryan, Market Operations Manager.
Delivering Connections and Capacity RIIO-T1 and associated commercial changes - Summary June 7th 2012.
Nodal Program Update and SEWG Update COPS 1/11/2011 Jim Galvin.
1 Market Operations Presentation Board of Director’s Meeting January 22, 2003.
Configuration Management and Change Control Change is inevitable! So it has to be planned for and managed.
1 UNC Modification 429 Customer Settlement Error Claims Process – Guidance Document.
Training Session Managing Formal Queries by Katia Compagnoni.
Exit Capacity Substitution and Revision Transmission Workstream meeting, 3 rd December 2009.
Interconnector Under Test Update to TSC Modifications Committee 5 th December 2012.
Mod_02_13 Registration of Charges Legal Spending Update.
Market Systems Release Update Modifications Committee Meeting 65 December 3rd
Metering Modification to T&S code Cathal Kearney Protection & Metering 03/12/2015.
MARKET SYSTEM RELEASE UPDATE Modifications Committee Meeting 27 March 2012.
T&SC Modification Proposal: Clarification of Outturn Availability
SEM Regional Integration Decision Paper FUI Stakeholder Group Meeting 16 June 2010.
Intraday Trading March RAs raised a Modification (18_10) in March 2010, proposing the implementation of “intra-day trading” in the SEM. The Modifications.
Entry Capacity Substitution Workshop 4 9 th July 2008 Entry Capacity Substitution Methodology Statement: Discussion Paper.
1 Nodal Day Ahead Invoice Taskforce Update COPS, May 8, 2007.
IMM Report on MISO South Integration Presented by: David B. Patton, Ph.D. Independent Market Monitor Presented to: Entergy Regional State Committee April.
UNC Modification Proposal 0202 National Grid Distribution
* MARKET SYSTEM RELEASE UPDATE Modifications Committee Meeting 9 August 2011 * 1##
Capacity Conversion – 616s
ESB Networks AIP Programme
Global Aggregation Mod raised by ESB CS at Mods Meeting 24 ( )
Amendment Invoice Task Force Progress Report
Recovery of Costs due to Invalid Ex-Ante Contracted Quantities in Imbalance Settlement 12th December 2017.
TSC Modifications Panel Meeting
Unsecured Bad Energy Debt and Unsecured Bad Capacity Debt Version 2
Agreed Procedure Updates
Correction of Minor Material Drafting Errors
Part B Unsecured Bad Energy Debt and Unsecured Bad Capacity Debt
Review of the requirements regarding Unsecured Bad Debt within I-SEM
Update to Unit Under Test Process
MOD_21_18 Application of Settlement Reallocation Agreements to Market Operator Charges and Settlement Document Definition and Usage 21st June 2018.
Exit Capacity Substitution and Revision
MOD_10_18 Amendment to Capacity Settlement Statement Publication from Monthly to Daily 13th March 2018.
Mod_25_18 Unsecured Bad Energy Debt and Unsecured Bad Capacity Debt
Interim Suspension Delay Periods
Mod_34_18 Removal of Make-Whole Payments for biased quantities and negative imbalance revenue, and small clarifications to determination of Start Up Costs.
MOD_13_17 V2 Deferral of SEM NEMO Credit Reports and Non-acceptance of Contracted Quantities 13th March 2018.
Credit Cover Signage and Subscript Correction
Determining Marginal Energy Action Prices Modification Proposal
Amendment Invoice Task Force Progress Report
Use of Technical Offer Data in Instruction Profiling / QBOA Version 2
Determining Marginal Energy Action Prices Modification Proposal
Modification Proposal 136
Correction to No Load Cost - “and” vs “or”
Mod 09_19 - Removal of locational constraints from Imbalance Pricing
Long Term Consumption Adjustments
Interconnector trading in SEM 7th June 2007
Correction to COP and clarification to CNLR
Presentation transcript:

Impact of Increasing Meter Errors on the SEM Modifications Committee Meeting 65 3 rd December 2015

Background; Size of issues; Impact on the SEM; Conclusions; Considerations for I-SEM. Content

MOD_04_15 first raised at Modification Committee Meeting 61 on 15 th April 2015; TSO analysis highlighted the causes of incorrect Metering data submitted to SEMO and how these could be prevented; These affect ROI DSO connected Generators for which the TSO is Meter Data Provider (MDP) in the SEM; Committee asked ROI TSO and DSO for a cost/benefit analysis of upgrading the Meters and how such errors have impacted the SEM; Background

23 DSO connected Generators, with TSO as MDP, were in the SEM in Jan 2013; these became 29 by Jan 2014 and 32 by Jan 2015*. The TSO, as MDP, have identified the following Metering errors: The identified Metering errors up to Nov 2015, are currently 55. *By Dec 2015, four additional units have joined the SEM, bringing the total up to 36. Size of Issue

The majority of these errors were identified and resolved before D+3 and therefore had no impact on the Market; Those not identified in time resulted in Formal Queries: These represented 8%, 11% and 13% of all Settlement Queries raised for each calendar year (2015 only up to Nov.). Size of Issue cont.

In 2015, the MDP has observed a decrease in the number of metering issues; however, Formal Queries to the SEM have remained stable; All units are VPTGs except 7* currently completing Grid Code testing; Further 82* units above 5MW are in the planning for Gate 3; The number of DSO connected Price Effecting Units in the SEM could rise to 114*; It is expected that, as the number of units increases, so will the number of errors and relative Formal Queries; This has the potential of becoming highly disruptive and impact the efficient running of the market. *Numbers subject to review as units opt to merge or split Impact on the SEM

The Settlement Queries affected VPTG Generators (Price Effecting in the SEM) in all but three cases; None of these errors were identified within the timelines for Data Queries; Errors were mostly resolved in M+4, because of small monetary impact, but some occurred for prolonged periods; Nine queries affected two or more days; one of these affected 31 days; It is likely that in those cases a Re-price would have occurred should the error be identified in time; Following MOD_01_15, six queries were not raised: errors within +/- 1MW increasing average monetary error from approx €150 to €748. Impact on the SEM cont.

Pricing signals might not work correctly, over-estimating or under- estimating the SMP; Prolonged errors could impact Constraints and Participants revenues; Amounts resettled for such issues to date, vary from less than €1 to about €138,500 and could be either positive or negative; Resettlements result in new versions of Statements for the whole billing period for all Units in the Market; All Units are therefore affected even in cases of minor adjustments; Trend in 2015 of higher number of sizeable issues. Impact on the SEM cont.

SEMO welcomes any improvement in the quality of Meter Data received to prevent and reduce instances of Resettlement or Re-price; This will avoid additional administrative burden to Participants, MDP and MO and will ensure the SMP is based on correct pricing signals; An increase in the number of queries will affect all areas in SEMO: Customer service: management of increased number of Formal Queries; Market Analysis: increase in the number and sizes of manual assessments; Pricing: increase in Re-prices and relative ad-hoc Resettlement; Settlement: increase in Resettlement for both Energy and Capacity; Credit and Funds Transfer: increase in the number of Invoice runs. SEMO has been able to absorb these additional workload to date; Additional resources will be needed should query numbers increase substantially in line with the increase in Units joining the Market. Conclusions

SEMC view to date is: ‘overall Metering framework will endure for I- SEM…including ‘as much as possible of the timings and processes’; ‘work will be under the governance of the RAs’ *. Removed current Price Effecting/Non Price Effecting units distinction; As any unit could be Price Maker, should this require harmonization of metering standards across all units? Will all MDPs have a 7 day operation? Timelines for submission of Metered data will affect trading ability; Could metering errors cause revenue uncertainty and affect the unit’s ability to respond to Imbalance pricing signals? Imbalance Settlement should be limited to the affected unit; Diminished impact to other Participants; will these errors be addressed at scheduled M+4 and M+13? * Extracts from I-SEM ETA Detailed Design Decision Paper SEM Considerations for I-SEM

Questions