(Project) RISK MANAGEMENT PROCESS SEPTEMBER 5, 2008.

Slides:



Advertisements
Similar presentations
Risk Management Module 3D Canada Bridges Project Management Tools Risk Management - Module 3D 1.
Advertisements

PROJECT RISK MANAGEMENT
COST CONTROLS OF CAPITAL COSTS THROUGHOUT THE DESIGN PHASE Presented by Planning & Management Services, Inc Federal Way, WA (near Seattle) Western Winter.
BSBPMG508A Manage Project Risk Manage Project Risk Introduction to Project Risk Diploma of Project Management Qualification Code BSB51507 Unit Code.
Sponsored by the U.S. Department of Defense © 2002 by Carnegie Mellon University July 2002 Pittsburgh, PA Lecture 6: Team Planning.
(Project) SIGN OFF PROCESS June 21, 2010
Chapter 7: Managing Risk
Project Cost Management Estimation Budget Cost Control
1 June 15 / Slide 1 / Title of Document Top 10 Things Your Project Manager Should Be Telling You A TUSC PMO Presentation.
Project Risk Management
Project Based Risk Management Defusing a potential ticking time bomb
By Saurabh Sardesai October 2014.
Author:Prof.Dr.Tomas Ganiron Jr1 CHAPTER 7 PROJECT EXECUTION, MONITOR & CONTROL PROCESS 7-1 Project Executing process 7-2What is Project monitor & control.
Managing Project Risk.
Section 4.0 Project Implementation. Factors that Ensure Success  Update the project plan  Stay within scope  Authorized change implementation  Providing.
Project Risk Management Risk Mitigation. Risk Management  The prime objective of risk management is to minimize the impact and probability of the occurrence.
Program Management Satisfy requirements of all individual projects with minimal resources Human resource is the most expensive Leadership Methods of documenting.
Project Risk Management Presenter: Phil Harman, PMP Executive Director for ZCS Internal PMO and Enterprise Project Management (EPM) Practice Manager September.
Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team Identification Measures of Success Roles & Responsibilities.
Problem Management SDG teamIT Problem Management Process 2009 Client Services Authors: M. Begley & R. Crompton, Client Services.
ITPD PRODUCTION SUPPORT PROCESS OCTOBER 8, /15/2015 Guiding Principles 1.Support the business area’s needs to execute transactions and expand.
Change Advisory Board COIN v1.ppt Change Advisory Board ITIL COIN June 20, 2007.
Office of Project Management Metrics Report Presentation
What is Business Analysis Planning & Monitoring?
Challenges Faced in Developing Audit Plans and Programs 21 st March, 2013.
McGraw-Hill/Irwin © 2008 The McGraw-Hill Companies, All Rights Reserved Business Plug-In B15 Project Management.
McGraw-Hill/Irwin © 2006 The McGraw-Hill Companies, Inc. All rights reserved. BUSINESS DRIVEN TECHNOLOGY Business Plug-In B10 Project Management.
Chapter 10 Contemporary Project Management Kloppenborg
Risk Management - the process of identifying and controlling hazards to protect the force.  It’s five steps represent a logical thought process from.
© Mahindra Satyam 2009 Defect Management and Prevention QMS Training.
Risk Management Project Management Digital Media Department Unit Credit Value : 4 Essential Learning time : 120 hours.
Chapter 7 Managing risk and quality. Learning objectives discuss the importance of risk in a project and how it can be managed explain the processes of.
Software Project Management
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
BSBPMG505A Manage Project Quality Manage Project Quality Project Quality Processes Diploma of Project Management Qualification Code BSB51507 Unit.
Monitor & Control Risks 1 MEC-4. What is Monitoring & Controlling Risks? 2 » Monitoring & Controlling Risks is the process of: implementing Risk Response.
1 Advanced Project Management Project Plan Templates Ghazala Amin.
Lecture # 17 PRM 702 Project Risk Management Ghazala Amin
© Mahindra Satyam 2009 Risk Management QMS Training.
STEP 4 Manage Delivery. Role of Project Manager At this stage, you as a project manager should clearly understand why you are doing this project. Also.
Apply Quality Management Techniques Project Quality Processes Certificate IV in Project Management Qualification Code BSB41507 Unit Code BSBPMG404A.
Managing Risk CHAPTER SEVEN Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Risk Management How To Develop a Risk Response Plan alphaPM Inc.
Project Management Methodology
CHANGE CONTROL PROCESS SEPTEMBER 22, /16/2015 Purpose  a methodical approach for capturing, managing and implementing IT changes  ongoing management.
Team Assignment 10 K15T02-Team Scope 2.Risk Management Process 3.How to determine the impart of risk 4.Top 10 risk of Viking.
ITPD ISSUE MANAGEMENT PROCESS SEPTEMBER 5, 2008
Information Technology Project Management Managing IT Project Risk.
Introduction to Project Management Chapter 9 Managing Project Risk
Project Organization Chart Roles & Responsibilities Matrix Add Project Name.
Monitor & Control Risks 1 MEC-4. What is Monitoring & Controlling Risks? 2 » Monitoring & Controlling Risks is the process of: implementing Risk Response.
Change Request TUNE IT! Hi! My name is Ed Dubrawski, PMP and a member of the Program Management Center of Excellence Advisory Council. The purpose of.
1 City of Shelby Wastewater Treatment Division Becomes State’s Second Public Agency to Implement a Certified Environmental Management System CERTIFICATION.
Overview PRINCE Hogeschool Rotterdam. 2 Project definition  A project is a temporary organization that is created for the purpose of delivering.
BSBPMG508A Manage Project Risk Manage Project Risk Unit Guide Diploma of Project Management Qualification Code BSB51507 Unit Code BSBPMG508A.
Training on Safe Hospitals in Disasters Module 3: Action Planning for “Safe Hospitals”
Company LOGO. Company LOGO PE, PMP, PgMP, PME, MCT, PRINCE2 Practitioner.
TMP3413 Software Engineering Lab Lab 01: TSPi Tool Support.
A process is "a series of actions bringing about a result.“ Project processes typically consist of project management processes and product-oriented processes.
Project management. Software project management ■It is the discipline of planning, organizing and managing resources to bring about the successful completion.
IS&T Project Reviews September 9, Project Review Overview Facilitative approach that actively engages a number of key project staff and senior IS&T.
Managing Project Risk – A simplified approach Presented by : Damian Leonard.
ITPD ISSUE MANAGEMENT PROCESS SEPTEMBER 5, 2008
[Project Name] STEERING COMMITTEE UPDATE [Date]
Change Control Process
Risk Management Process (Revised)
Project Management Group
ISSUE MANAGEMENT PROCESS MONTH DAY, YEAR
(Project) SIGN OFF PROCESS MONTH DAY, YEAR
Cost Management Process MONTH DAY, YEAR
Presentation transcript:

(Project) RISK MANAGEMENT PROCESS SEPTEMBER 5, 2008

212/24/2015 Purpose and Definition  a structured approach for the documentation and review and risks throughout the project  an approach for identification and management of mitigation strategies that can be put in place to reduce the probability of occurrence  identification of those risks with the highest probability of occurrence and impact to the project for communication to and involvement of the Steering Committee for action The Risk Management Process ensures:

312/24/2015 Definitions Risks are also categorized into the following project impact categories: UnlikelyModerateLikely % chance of occurrence The risk is unlikely to occur even if no steps are taken to manage this risk. 25% - 75% chance of occurrence The potential impacts are moderately likely to occur if no steps are taken to manage this risk. > 75% chance of occurrence The potential impacts are likely to occur if no steps are taken to manage this risk. A risk is a possible future event which, if it occurs, is expected to have an undesirable impact on the project. Risks will be categorized into these probabilities of occurrence: Low Impact on schedule for a limited number of tasks, but no delay to key dates. Minor increase to project expenditures, but no noticeable degradation in quality Medium Impact on schedule for many tasks and minor delays on key dates. Major increase in project expenditures, Noticeable, but acceptable, degradation in quality, additional but acceptable risk exposure High Major impact on key dates requiring a new overall schedule. Unacceptable increase in project expenditures, Unacceptable degradation in quality and risk exposure Critical Complete project failure

412/24/2015 Guiding Principles 1)Risks should be proactively reviewed and managed by the Project Manager at lease once per month 2)The Risk Owners will be responsible for management and update of their risk mitigation plans 3)Risks should not be closed. They should live throughout the project with ongoing update to their mitigation plans and status To ensure efficiency in the process, the following will serve as guiding principles:

512/24/2015 Risk Resolution Process

612/24/2015 Process Steps Ref IDProcess StepDescriptionInput/OutputTime HorizonOwner 1Identify the RiskA risk is an element that may cause uncertain danger to the RP&A project. When a risk is discovered, a team member must contact his/her lead with all the pertinent information regarding the risk Input: Risk discovery Output: Detailed information about the Risk As necessaryProject Team 2Log the RiskThe lead must meet with the Project Manager to approve the risk and log it into the Risk log (Excel – short term or Document Repository Tool – long term). To minimize access to the log, only the Project Manager will have access to the log. Input: Detailed information about the Risk Output: Risk Management entry As necessaryProject Manager 3Communicate detail to Assignee with Risk Number If the Risk is to be assigned to a team other than the original team reporting the risk, Project Manager must communicate the Risk information to the Assigned Team Lead Input: Risk logged Output: Reassignment of Risk to different team As necessaryProject Manager 4Qualify the RiskThe Project Manager must review the Risk and detail all the relevant problems that can occur from the Risk. They must identify all the teams impacted if the Risk were to occur, and all potential loss Input: Risk logged Output: Updated Risk As necessaryProject Manager 5Track As Task, Action Item, or Issue and Update Risk Mitigation During Risk Qualification, the Project Manager may identify a Risk as being a Task, Action Item, and Issue in addition to being a Risk. If this occurs, a Task, Action Item, or Issue will be logged in Document Repository Tool, and the Risk Mitigation must contain the Task, Action Item, or Issue information. A Risk is NEVER closed Input: Updated Risk Output: Task, Action Item, and/or Issue resulting from Risk As necessaryProject Manager 6Manage the RiskThe “Assigned to Team” listed on the Risk will evaluate the Risk for a mitigation plan. This will involve proactively working with impacted teams and reporting out the mitigation plan tasks at least once per month. Risks will be reviewed within the Project Managers meeting at the first week of the month at a minimum but more frequently if warranted Input: Updated Risk Output: Possible escalation of Risk At least once/ month Project Team

712/24/2015 Process Steps Ref IDProcess StepDescriptionInput/OutputTime HorizonOwner 7Risk DispositionIf the Risk does not require any more escalation, the Project Manager will evaluate the continuing disposition of the Risk. If they feel it is still a Risk that requires a Mitigation Plan, they will choose to Mitigate the Risk. If the Risk Mitigation requires additional monies be spent, they will choose to Track the Risk as a Change Request. If the Risk should be tracked as an Issue, they will choose to Track the Risk as an Issue Input: Updated Risk Output: Decision on course of action (Create Mitigation Plan, Create Change Request, Create Issue) As necessaryProject Manager 8Propose Mitigation Plan The Project Team will update the Risk in Document Repository Tool with a detailed plan to mitigate the risk. If the Project Manager does not approve of the mitigation, the Project Team must work with the Project Manager to create an acceptable mitigation plan Input: Updated Risk Output: Detailed Mitigation Plan Immediately upon identification Project Team 9Update Risk and Log Issue If the Risk is actually an Issue, the Project Team must log an Issue in Document Repository Tool, update the Risk with the relevant information, and follow the Issue Management Process. The Risk should not be closed, but the Issue information listed as mitigation Input: Updated Risk Output: Logged Issue and Updated Risk As necessaryProject Team 10Execute Mitigation Action Items Once the Mitigation Plan is accepted, the Project Team must carry out the Action Items listed in their detailed Mitigation Plan. Input: Detailed Mitigation Plan Output: Action taken as directed by Mitigation Plan for Risk As necessaryProject Team

812/24/2015 Key Roles & Responsibilities RoleResponsibility Project Manager Communicate with Project Teams regarding current and future potential Risks Accurately track the Risk with the appropriate process (Issue, Action Item) Continuously review the Risk with the Project Team to ensure the Mitigation Plan Action Items are completed Project TeamCommunicate Risks to Project Manager in a timely manner Detail all possible problems that may result from this Risk Complete the Mitigation Plan Action Items in a timely manner to minimize the impact of the Risk on the RP&A Project There are several key roles and responsibilities necessary to ensure effectiveness of the Risk Resolution Process:

912/24/2015 Contact Information For additional information on this process, please contact… Contact Name Phone PrimarySteve SecondaryDeneeta