BI.DIS10: Magnets & generators R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November 20152.

Slides:



Advertisements
Similar presentations
Proton Driver Magnet Power Supply System Cezary Jach BD/EE Support April 19, 2000.
Advertisements

Multi-Turn Extraction / L.Ducimetière / Kicker options for MTE Prepared by L.Ducimetière, L.Sermeus Outline: Reminder : Present MTE dedicated.
Andrew Moss Daresbury Laboratory August 2013 Latest results of MICE amplifier testing.
PSB extraction and transfer kickers 01/10/2014 LIU-PS ABT review1 L. Ducimetière, L. Sermeus.
1/10/2014 LIU-PS ABT review1 T. Kramer, L. Ducimetiere, L. Sermeus.
CEA DSM Irfu - Bernard GASTINEAU - R3B Technical Board Meeting -April 4, Reactions with Relativistic Radioactive ions Beams GSI Large Acceptance.
Alternating Current Circuits
Development of Solid State Long Pulse Klystron Modulators
Experience of High Voltage Conditioning of Kicker Magnets M.J. Barnes Acknowledgements: G. Bellotto, P. Burkel, H. Day, L. Ducimetière, T. Kramer, V. Gomes.
LHC 30 th and 31 st July :10 Finish scrubbing fill 25 ns trains by operator dump. –No XPOC data … 08:40 Inject for another scrubbing fill 09:09.
STRIPLINE KICKER STATUS. PRESENTATION OUTLINE 1.Design of a stripline kicker for beam injection in DAFNE storage rings. 2.HV tests and RF measurements.
Linac Marx Modulator Update Trevor Butler 10/29/2014.
The CNGS Horns Electrical Systems The CNGS Horns Electrical Systems 4th workshop on Neutrino Beams and Instrumentation 7 – 11 November 2003 at KEK Gilles.Maire.
Linac Marx Modulator Update Trevor Butler 5/20/2015.
MKI Erratics: Hardware and Electronics Related Aspects M.J. Barnes Acknowledgements: A.Antoine, R.A. Barlow, P. Burkel, E. Carlier, N. Magnin, V. Mertens.
Modulator and overmoded RF components status for the 12GHz Test Stand at CERN - RF meeting – 17/03/2010.
The Stripping Foil Test Stand in the Linac4 Transfer Line
2 Davide Aguglia TE-EPC-FPC Sept. 23 rd rd PSB injection EPC powering rack space coordination meeting Stripping foil chicane BSW magnets powering.
Jean-Paul BURNET, AB/PO ATC-ABOC days, 22 January 2007 PS Main Power System: What has been done from June 2006? What will be the situation in 2007? PS.
1 Thermal tests planning for mock-up TM0 Thermal tests planning for CLIC prototype module type 0 May 30th,
14 th ESLS RF Meeting – Trieste, September 2010 ALBA RF Status 1/28 ALBA RF Status Francis Perez.
7 November 2003 Status of CNGS NBI presented by K. Elsener 1 Status of CNGS Konrad Elsener CERN – Accelerators+Beams Division.
R. Rosol, LIU-PSB review, 10 September BI.DIS Pulse generators R. Rosol, LIU-PSB review, 10 September Luc SERMEUS, Rodolphe ROSOL Laurent.
ABT LIU Project Review 2015 BI.KSW: Magnet November 20 th 2015 L. Feliciano TE/ABT.
22 Set 2009 EPPC 09 CERN September /14 Solid-State MARX Type Circuit for the ISOLDE Target Voltage Modulator L.M. Redondo*, J. Fernando Silva.
Status of ATF Fast Kicker Experiment
IBL CO 2 cooling planning 03 July 2013 Jan Godlewski, Bart Verlaat, Lukasz Zwalinski 1
SBDS – MKDV/H: The new MKDV Generator and additional Magnet for BA5 installation V. Senaj, L. Ducimetière November 20 th 2015.
Outline Injection septum SMH42 Injection bumper Resources Conclusion LIU-ABT review 20/11/2015 Status PS injection septa2.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
Technology Department 1 ELENA Fast Deflectors status Nicolas Voumard, Jan Schipper TE/ABT/EC TCM 17/11/2015 1/11.
LIU-ABT systems: SPS T. Kramer, E. Carlier, L. Ducimetiere, L. Sermeus, J. Uythoven LIU-IONS 4 th November /11/2014 SPS LIU-ABT Systems Review2.
R. A. Barlow, LIU-PSB review, 20 Nov BI.DIS Pulse generators controls R.A.Barlow, LIU-PSB review, 20 Nov
MERIT review, Dec. 2005CERN AB-ATB1 CERN installation I. Efthymiopoulos, A. Fabich, J. Lettry CERN AB-ATB MERIT review, Dec.
POTENTIAL EN-MME DESIGN JOBS IDENTIFIED BUT CURRENTLY NO REQUEST FROM EQUIPMENT OWNERS TO EN-MME EDMS B.RIFFAUD On behalf of EN-MME design team.
LIU-ABT systems: PSB BI.DIS controls prepared by R.A.Barlow (September 2014) 1 CERN TE-ABT-EC.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
Serge Pittet (Work-Package holder) Konstantinos Papastergiou (Work-unit: Sirius converters) CERN Technology Department | Electrical Power Converters 12.
ABT review on the LIU-PSB Systems PSB KSW Magnets September 10 th 2014 L. Feliciano TE/ABT.
The way to fast and "loss-free" SPS kickers E. Gaxiola With contributions from AB-BT-KSL section and F. Caspers, T. Kroyer, M. Timmins, J. Uythoven.
Technology Department BI.DIS general controls status R.A.Barlow EC section
ELENA KICKERS AND SEPTA ELENA Meeting, Prepared by J. Borburgh, E. Carlier, A. Fowler, L. Sermeus TE/ABT.
Status of the Spanish contribution to CTF3 L. García-Tabarés, F. ToralCERN, 17/9/2006.
L. Sermeus TE-ABT-FPSELENA IIC meeting 3 th April Review of ELENA Injection kicker Luc Sermeus on behalf of WP 2.8 (with informations from EN-MME)
Udo Blell - Synchrotrons 1 Udo Blell GSI, Darmstadt MAC – 7 April 2 th - 3 th, 2012 FZ - Jülich SIS 100 Injection / Extraction systems.
LIU-SPS T. Kramer, L. Ducimetiere, L. Sermeus, J. Uythoven LIU-IONS 20 th November /11/2015 LIU-ABT Review - SPS2.
High Voltage modulators ESS developments Carlos A. Martins ESS Accelerator Division, RF electrical power systems.
POPS: Power for PS A novel 60 MW Pulsed Power System based on Capacitive Energy Storage Jean-Paul Burnet June 2010.
Two half-day seminars on the remaining work packages to complete the MEDICIS Facility POWER CONVERTERS FOR MEDICIS Davide Aguglia & Julien Parra-Lopez.
Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus.
PSB extraction and transfer kickers LIU TE-ABT review, 20 November L. Sermeus.
MKDV upgrade LIU-SPS ABT meeting V. Senaj, L. Ducimetiere, P. Faure November 4 th 2014.
26/11/2015 LIU-PSB meeting, Status of BE and BT kickers and septa 2 Extraction and Recombination Septa and Kickers status Jan Borburgh, M. Atanasov, W.
Status of HESR 18th March Gießen Dieter Prasuhn.
LINAC4 ADVISORY COMMITTEE
Brief Status SPS Prototype PSB Prototype Installed in LS1
CSP 25th November 2010 Technical agreement number 3: overview
Teleconference ACS – FREIA 17th October 2017
Power converters for 2GeV injection
LV Safe Powering from UPS to Clients
prepared by R.A.Barlow 30/056/2016
Target and Horn status report
352MHz Klystron Control for the 3MeV Linac test stand
Junji Urakawa (KEK) for ATF International Collaboration
Klystron Power Supplies for ILC
Teleconference ACS – FREIA 20th February 2018
III. Correction Dipoles MDG Accessories for all Magnets V. Summary
Teleconference ACS – FREIA 19th June 2017
Status of the BI Work Package in the LIU-PSB frame
KFA10 status 03/06/2019 Currently:
Presentation transcript:

BI.DIS10: Magnets & generators R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November 20152

Contents -BI.DIS system parameters -System and pulse generator description -Test results -Final design -Planning, Resources, EVM -Conclusions R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November

BI.DIS system parameters R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November 2015 ParameterUnitValue Deflection angle at 160 MeV (vertical) mradDIS0: 3.77 DIS1: 4.23 DIS2: 3.84 DIS3: 3.4 DIS4: 3.97 Kick flat-top durationµsDIS0: 20 DIS1: 170 DIS2: 320 DIS3: 470 DIS4: 620 Kick rise time (1-99)%µs≤ 2 Kick flat-top ripple (p-p)%≤ ±1 Magnet currentA~ 1000 A PFN impedanceΩ6.25 PFN voltagekV6.25 Repetition rateHz1.1 ~ 150µs 4

System and pulse generator description R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November magnets in one vacuum tank 5 Pulse Forming Networks 6.25 Ω (one per magnet) + 1 spare PFN voltage up to 10 kV ( ~ 7 kV nominal with H - operation) IGBT switch (2 × 6.5 kV device in series) fixed duration (different for each PFN, max 620 µs) short-circuited magnet recuperation of a large fraction ( > 50 %) of the PFN stored energy (1270 J) 5

BI.DIS10 vacuum tank R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November 2015 Tank (with 5 magnets) under vacuum in SAL6 test cage ready for connection to pulse generator. Pressure ok: 2e-9 mbar. TE-VSC will re-test the water circuit before their final acceptance. Spare tank to be tested later. ENG. Spec: EDMS

Prototype pulse generator tests results R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November 2015 Impedance ~6.25 Ω chosen for 2 µs rise time. 2×6.5 kV IGBTs in series for operation at ~7 kV/1000 A. Switches: ABB or Hitachi are suitable. 60 cells for 620 µs pulse (60 capacitors of 1 µF) to fill the available space and have a minimum flat-top ripple. 7

Prototype pulse generator tests results R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November 2015 Magnet current (= Kick) Voltage to reach 1000 A is 7 kV due to resistive losses and rising edge shape adjustment (and optimisation) leading to a PFN impedance near 7 Ω. Rise-time ≤ 2 µs achieved with more than 500 ns margin. 8

Prototype pulse generator tests results R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November 2015 Ripple ≤ ±1 % achieved with foreseen improvement to ≤ ± 0.5 % in final installation. Magnet current (= Kick) Pulse lengths from 170 to 620 µs achieved with 1, 2, 3 and 4 capacitor rows. 20 µs still to be done. 9

Pulse generators final design R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November 2015 Each cabinet rack contains two separate PFNs of 60 L-C cells maximum L-C cell PFN Rack Switch rack 10

Pulse generators final design R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November 2015 Each PFN cabinet half is “hermetic” and has an integrated automatic fire detection and CO2 injection system. Pressure relief valves have to be installed to limit the CO2 pressure in the rack. Pressure relief valveFront cell IGBT Switch Earthing device 11

Pre-series pulse generator R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November 2015 Pre-series status 17 November

BI.DIS Prototype Definitive Design Type Test  Performance  Reliability  Operational conditions  Safety  Preliminary Controls Functional Spec. First Prototype Design Update Test Improved Design Review  12/2014  07/2015 Realisation and Development Proof of Concept  03/2016 Engineering Spec. Start of Series Production Definitive Design R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November

Present Status and tests still to be performed STATUS PFN mechanical design complete at 95 % (CATIA 3D models and 2D fabrication drawings). In stand-by due to the illness of P. Faure. One full pre-series almost ready for test. Two IGBT types selected among four manufacturers to meet the pulse required rise time Tests with full pulse length (620 ms) and nominal required current (1000 A) performed. Fire extinguisher test performed. Final three cabinets ready for delivery by the manufacturer. More than 60 coils ready for the series. NEXT TEST Full operational conditions with closed cabinet to see if we have thermal issues. The departure of Rodolphe will slow down the restart. R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November

BI.DIS Generator Assembly Schedule MarJunJulAugSepOctNovDec2017 Start Series Production 1 st Rack Ready End April Ready to install End December 2 weeks (FSU!) Cabling 1 week Cell Tuning 2 weeks Verification Test Feb 1 st Definitive Generator 2 weeks (2 x FSU!) Rack Assembly May Apr 9 weeks March Start 2 nd Rack June 1 week Disassembly Start 3 rd Rack September 2 nd Rack Ready End July 3 rd Rack Ready November Fast Interlock Trigger System 2 nd Rack Fast Interlock and Timing Controls Test 3 weeks 3 rd Rack Validation 2 weeks 9 weeks 1 week R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November

Resources for 2016 (FPS only) 1.Material to be ordered and delivered in 2016 (6 PFNs) Mechanical components: 100 kCHF Electrical components: 80 kCHF Miscellaneous: 20 kCHF Total: 200 kCHF 2.FSU Coil manufacture : 35 man.week PFN cabinet assembly: 18 man.week Total: 53 man.week 3.CERN FTE Drawings update and orders: 0.3 Assembly: 0.4 Supervision and tests: 1.3 Total: 2 FTE R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November

EVM: Provide BI.DIS magnets Year PV EV AC Metrics per year in kCHF Cumulative metrics per year in kCHF Year PV EV AC R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November

EVM: Provide BI.DIS pulse generator Year PV EV AC Metrics per year in kCHF Cumulative metrics per year in kCHF Year PV EV AC R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November

Conclusion The new BI.DIS generators are entering their production phase but the full pre-series version still has to be validated. Test of the full pre-series one will start hopefully this year for completion early next year. The goal of having the full system ready for installation end of 2016 should be met assuming that the necessary resources will be available at the right moment. The management has to set priorities accordingly. R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November

THANK YOU FOR YOUR ATTENTION! R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November