AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009.

Slides:



Advertisements
Similar presentations
HCAL Front End Boards HCAL – Technical Meeting Status of the FE Boards Parameter Shift Register Time Schedule Test Setup Mathias Reinecke.
Advertisements

AHCAL Mechanics and test beam setups status report Karsten Gadow AHCAL Main Meeting DESY,
LCWS2010, Beijing, 2010 MAR29 Ivo Polák, FZU, Prague1 LED notched fibre system at AHCAL Calibration system for SiPM Ivo Polák 1.Notched fibre.
Calice, UT ArlingtonJiri Kvasnicka, FZU, Prague1 LED notched fiber system Jiri Kvasnicka 1.Introduction 2.Test setup and fiber layout on HBU0.
ECAL electronics Guido Haefeli, Lausanne PEBS meeting 10.Jan
Mathias Reinecke CALICE meeting Argonne EUDET module – Electronics Integration Contents -Next prototype : architecture -HCAL Base Unit (HBU)
Feb 20, 2009 CALICE meeting, Daegu, Korea QRL in Magnetic Field 1 QRLed Driver in Magnetic Field Jaroslav Zalesak Institute of Physics of the ASCR, Prague.
AHCAL – Electromechanical Integration EUDET annual meeting – Paris Oct M. Reinecke.
AHCAL Electronics. Status EUDET Prototype Mathias Reinecke for the DESY AHCAL developers EUDET Electronics/DAQ meeting London, June 9th, 2009.
Reports from DESY Satoru Uozumi (Staying at DESY during Nov 11 – 25) Nov-21 GLDCAL Japan-Korea meeting.
AHCAL Electronics. Front-end electronics and DAQ Mathias Reinecke CALICE meeting Hamburg March 21st, 2013.
06/03/06Calice TB preparation1 HCAL test beam monitoring - online plots & fast analysis - - what do we want to monitor - how do we want to store & communicate.
AHCAL Electronics. Status and Outlook Mathias Reinecke AHCAL main Meeting D ESY Hamburg, Dec. 16th, 2014.
Saturation in V-calib LED scans CALICE AHCAL – Main Meeting 2010/07/05 Jaroslav Zalesak analysis still in progress but gives global results FNAL & CERN.
AHCAL Electronics. Status Commissioning and Integration Peter Göttlicher for the AHCAL developers CALICE meeting UT Arlington, March 12th, 2010.
Calibration UV LED system for CALICE scintillator based Tile Hadron Calorimeter Ivo Polák on behalf of the CALICE Collaboration Institute of Physics of.
AHCAL – DIF Interface EUDET annual meeting – Paris Oct M. Reinecke.
AHCAL electronics. Status and Outlook Peter Göttlicher for the AHCAL developers CALICE meeting UT Arlington, March 11th, 2010.
LCWA, ALCPG 2009 Albuquerque, NM Ivo Polák, FZU, Prague1 Calibration system of CALICE AHCAL detector Ivo Polák 1.Two calibration light distribution.
AHCAL updates: SPIROC and DIF Mathias Reinecke, Felix Sefkow CALICE/EUDET electronics meeting London, January 10, 2008.
AHCAL Electronics. Status and Outlook Mathias Reinecke CALICE collaboration meeting Cambridge, UK March 16th-19th, 2012.
Light Calibration System (LCS) Temperature & Voltage Dependence Option 2: Optical system Option 2: LED driver Calibration of the Hadronic Calorimeter Prototype.
1. DESY tests 2. Electronics developments 3. Optical developments 4. Outlook Casablanca J. Cvach, CALICE Coll. meeting.
AHCAL Status. Electronics and DAQ Mathias Reinecke CALICE meeting Argonne ANL, Mar. 19th, 2014.
HCAL – Integration Plans Mathias ReineckeHCAL – Main meeting Introduction 2.HCAL Base Unit (HBU) - Update 3.Testboards 4.Light Calibration System.
Detector Interface (DIF) Status CALICE meeting – DESYDec Mathias Reinecke.
R&D for a 2nd generation AHCAL prototype LCWS 2007 – DESY Hamburg Mathias Reinecke on behalf of the AHCAL partners.
5 July 2010Ivo Polák, FZU, Prague LED notched fibre distributing system Calibration system for SiPM Ivo Polák, Ji ř í Kvasni č ka
CALICE / Silicon PM activities Detector and readout electronics development Development of a system for mass production of AHCAL “HBU” scintillator/PCB.
AHCAL Physics Prototype. The Electronics Part Mathias Reinecke for the AHCAL developers DESY, March 2nd, 2010.
AHCAL electronics. Status Module Production an Power Pulsing Mathias Reinecke AHCAL main meeting DESY, Dec. 10th, 2013.
AHCAL Electronics. SPIROC2 and HBU measurement results Mathias Reinecke CALICE main meeting Univ. HASSAN II, Casablanca, Morocco Sept. 23rd, 2010.
Mathias Reinecke CALICE week Manchester DIF development – Status and Common Approach Mathias Reinecke for the CALICE DAQ and Front-End developers.
SPIROC update Felix Sefkow Most slides from Ludovic Raux HCAL main meeting April 18, 2007.
Visit to CALICE ECAL testbeam (by Shinshu) at DESY, 16 th – 19 th October 2012 Samir Arfaoui & Erik van der Kraaij 30 th October 2012.
CALICE Tungsten HCAL Prototype status Erika Garutti Wolfgang Klempt Erik van der Kraaij CERN LCD International Workshop on Linear Colliders 2010, October.
Scintillator tile – SiPM development at ITEP Michael Danilov, ITEP CALICE Meeting, Casablanca, 23 Sep 2010.
1 Calorimeters LED control LHCb CALO meeting Anatoli Konoplyannikov /ITEP/ Status of the calorimeters LV power supply and ECS control Status of.
Main HCAL, JUL1,2008Ivo Polak, IP_ASCR, Prague1 Calibration system with optical fibers HCAL main meeting, DESY.
5-9 June 2006Erika Garutti - CALOR CALICE scintillator HCAL commissioning experience and test beam program Erika Garutti On behalf of the CALICE.
(s)T3B Update – Calibration and Temperature Corrections AHCAL meeting– December 13 th 2011 – Hamburg Christian Soldner Max-Planck-Institute for Physics.
Mathias Reinecke AHCAL Main Meeting Electronics Integration - Status Mathias Reinecke for the AHCAL developers.
Status of the PSD upgrade - Status of the PSD cooling and temperature stabilization system - MAPD gain monitoring system - PSD readout upgrade F.Guber,
Tile HCAL status Felix Sefkow CALICE Technical Board Review April 19, 2007.
AHCAL Electronics. integration status and open issues Mathias Reinecke CALICE main meeting Univ. HASSAN II, Casablanca, Morocco Sept. 23rd, 2010.
AHCAL Electronics. Status and Outlook Mathias Reinecke for the AHCAL developers CALICE Days DESY Hamburg, March 31st, 2009.
Mathias Reinecke EUDET Annual Meeting 2008 – NIKHEF AHCAL Power Aspects P. Göttlicher, M. Reinecke, H.-J. Wentzlaff for the AHCAL developers.
14 jan 2010 CALICE/EUDET FEE status C. de LA TAILLE.
AHCAL Integration. Status and Outlook Mathias Reinecke for the AHCAL developers CALICE week Lyon IPNL, Sept. 16th – 18th, 2009.
Mathias Reinecke CALICE week - Manchester Electronics Integration - Status Mathias Reinecke for the AHCAL developers.
AHCAL Electronics. Status of Integration Mathias Reinecke for the DESY AHCAL developers AHCAL main and analysis meeting Hamburg, July 16th and 17th, 2009.
CALICE/EUDET FEE status C. de LA TAILLE. 31 aug 2009 EUDET SC meeting Status of JRA3 Front End Electronics 2 ILC front-end ASICs : the ROC chips SPIROC.
HCAL Modules -First Ideas Mathias ReineckeHCAL – MPI meetingJan Motivation 2.Mechanical Constraints 3.HCAL Base Unit (HBU) 4.Light Calibration.
11 may 2010 Performance of 2 nd generation ASICs for CALICE/EUDET C. de LA TAILLE OMEGA-LAL Orsay.
AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers EUDET electronics and DAQ meeting Paris Palaiseau, Jan. 14th, 2010.
AHCAL Electronics. status and open issues Mathias Reinecke CALICE ECAL/AHCAL - EUDET electronics and DAQ - AIDA DESY, July 5th to 6th, 2010.
LED notched fibre distributing system Calibration system for SiPM
LED notched fibre system short HBU0 party with QMB6
Online Monitoring : Detector and Performance check
AHCAL Beam Interface (BIF)
Status of HBU, EBU and SM_HBU
CALICE meeting 2007 – Prague
HCAL task status report
Testbeam Timing Issues.
LED notched fibre system at AHCAL Calibration system for SiPM
HCAL Modules -First Ideas
Felix Sefkow CALICE/EUDET electronics meeting CERN, July 12, 2007
CALICE meeting 2007 – Prague
Status of the EUDET Prototype
Scintillator HCal Prototype
Presentation transcript:

AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 2 Outline > System Commissioning  Labview DAQ operation  First Results > Testbeam Preparation > The Next Generation > Conclusions and Outlook

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 3 HCAL Base Unit (HBU) and system setup 2 setups in operation

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 4 Tile Assembly – HBUII SPIROC2 area Alignment ‘Reflector Foil – HBU’ Some positions cannot be assembled (tiles do not fit in) “mechanics tiles” (cassette construction) Reflector foil: without cover (blank) still with cover

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 5 Single-Photon Peaks I 100fF PA feedback, 50ns shaping, no ‘hold’ sent, ext. trig., SiPM at nom. bias, ~9000 entries per curve, one SPIROC2 memory cell used. VCALIB ~ LED light ampl. Preliminary

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 6 Single-Photon Peaks II (reduced SiPM bias) Gain blue curve: ~70% 100fF PA feedback, 50ns shaping, ext. trig., no ‘hold’, ~9000 entries per curve one mem-cell used Preliminary

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 7 Single-Photon Peaks III (SPIROC2 SCA test) Preliminary time between LED triggers: ~40µs

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 8 Single-Photon Peaks III (SPIROC2 SCA test) Preliminary > Different light amplitudes due to integrated LED system, but reason unknown (no level shifts of GND or VCALIB observed). > Offset may be due to SCA cells, or due to GND level shifts. > Without correction, sum of SCA cell results (black curve) should not be used.

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 9 integrated LED system – dynamic range SPIROC2: 400fF PA feedback, 50ns shaping, results for 18 assembled channels shown Zoom of Fig. on the left > LED comp-to-comp spread is large => preselection necessary. > Dynamic range: Change LED capacitor? VCALIB max = 10V.

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 10 Testbench Labviews – Histogram Building Choose: Channel or all Memory cell or all SPIROC2_2 SPIROC2_1 Result file

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 11 Testbench Labviews – Coherent Noise Analysis mean values (white points) now: rip off block capacit. no coh. noise: circular shape

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 12 Testbeam Synchronization (CALICE DAQ setup) Concept: M. Wing et al., hopefully extended correctly > All timing critical signals are distributed from central DAQ (via CCC). > All detector units (+DIFs) run synchronously.

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 13 Testbeam Data Taking: Internal Trigger AHCAL timing scheme for common CALICE testbeam > Internal Trigger with “Validate_Event”. Pink boxes: deadtime! > Do we need “Internal trigger mode” without Val_Evt in TB (full clock rate)? > CALICE DAQ: Synchronize Val_Evt on global clock (multi-DIF synchron.).

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 14 DESY Testbeam Synchronization (Labview setup) > Synchronization done by temporary hardware signals to/from DIF. > First: Only one DIF/HBU used. With two HBUs the CCC is needed. > Readout Speed limited due to USB/Serial Interface.

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 15 DESY Testbeam Synchronization (Labview setup) LV: Labview TB: Testbeam Electronics HW: Hardware > Due to shutdown of DESYII: HBU testbeam tests end of Feb > External and Internal trigger will be tested.

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 16 The Next Generation (‘final’ ILC setup concept) Mechanical concept: K. Gadow Not in scale!

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 17 The Next Generation Sector Connecting Plate Cassette (=slab) HBU SPIROC Central Interface Board with DIF, CALIB and POWER Not in scale!!

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 18 The Next Generation SPIROC LED Flexlead + tiny connector Central Interface Board with DIF, CALIB and POWER Cooling Pipe Tile with SiPM Reflector Foil Cassette Bottom Plate Not in scale!! HBU Height pitch of 20mm possible: HCAL-W, under invest.

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 19 Conclusions and Outlook > AHCAL prototype in full operation! 2 setups realized! > CALICE DAQ (hardware, DIF firmware) still has to be implemented.  we expect a first system Feb/March Till then: Labview operation. > SPIROC2a submission Jan2010. Changes under discussion. > DESY electron-testbeam preparation ongoing. > Redesigns of AHCAL modules are prepared now. > Fibre based calibration system in operation as well! (see Ivo’s talk) > A lot of system’s and SPIROC analogue and digital tests ahead.  all shown analysis have not been completed.  status only demonstrates readiness of the system and system’s tools.