First radiological estimates for the HIRADMAT project H. Vincke and N. Conan 1.

Slides:



Advertisements
Similar presentations
Simulations des niveaux de radiations en arrêt machine M. Brugger, D. Forkel-Wirth, S. Roesler (SC/RP)
Advertisements

Preliminary studies for T2 primary target for the NA61 fragmentation beam run 11 th October 2010 – NA61 Collaboration Meeting M. Calviani on behalf of.
1 Activation problems S.Agosteo (1), M.Magistris (1,2), Th.Otto (2), M.Silari (2) (1) Politecnico di Milano; (2) CERN.
Induced Activity Calculations in Support of D&D Activities at SLAC Joachim Vollaire, Radiation Protection Department.
HIRADMAT IN THE WANF TUNNEL I. E FTHYMIOPOULOS, EN/MEF  HIRADMAT-Exp.Area Working Group  EN/MEF : I. Efthymiopoulos, A. Pardons, M.Lazzaroni, N. Gilbert.
C. Theis, D. Forkel-Wirth, S. Roesler, H. Vincke.
Activation of equipment - overview Chris Theis, Helmut Vincke - DGS/RP.
Air activation inside and around the SPS beam dump M. Baudin H. Vincke DGS-RP-AS.
ATC/ABOC Days 21-23/1/2008 Heinz Vincke for SC-RP 1.
Studies of radiation hardness of ECAL modules 1Yu. Guz 2013/05/28.
H IGH L UMINOSITY LHC WP1 - CERN S AFETY R EQUIREMENTS Stefan Roesler - Phillip Santos Silva – Ralf Trant EDMS# HSE Unit April 2011.
HIGH RADIATION TO MATERIALS: EXPERIMENTAL AREA DESIGN Ans Pardons HiRadMat review, 26 th of May 2011 Outline  Location of experimental area & services.
STATUS REPORT ON HIRADMAT I. E FTHYMIOPOULOS, EN/MEF  Slides taken from HIRADMAT presentation to A&T management  R. Assmann, C. Hessler, I. Efthymiopoulos,
1 Induced radioactivity in the target station and in the decay tunnel from a 4 MW proton beam S.Agosteo (1), M.Magistris (1,2), Th.Otto (2), M.Silari (2)
Lessons learnt from WANF (*) dismantling Outline  Introduction  WANF/HiRadMat location  WANF operation  WANF dismantling  Preparation  Dismantling.
Neutronics & RP Issues Neutronics & RP Issues nToF Review 14 th February 2008 CERN AB/ATB/EET n_TOF Team.
Radiation Protection considerations concerning a future SPS dump design Helmut Vincke DGS-RP.
First AWAKE dump calculations Helmut Vincke. Beam on dump Muon axis inside and outside CERN Distances: Beam impact point to end of West hall: ~300 m Beam.
Estimation of temperature increase in the dump through Monte – Carlo simulations and rough calculations N. Charitonidis (EN/MEF)
MG - IEFC meeting 22/01/20101 Linac 3 shielding S. Gilardoni, M. Giovannozzi, S. Baird, R. Brown, S. Damjanovic, T. Otto, M. Widorski, Acknowledgements:
Additional Lift to Access ECA5 Etienne Carlier, Jean-Louis Grenard, Damien Lafarge SPS Dump Upgrade Meeting 09/07/2015.
Loss in TED Loss in magnet Loss in iron rod Assessment of the production of airborne radioactivity caused by various beam loss scenarios in the SPS.
Highlights of RP activities in support of ISOLDE operation and projects Joachim Vollaire, Alexandre Dorsival and Christelle Saury with material from others.
The Status of ESS Accelerator Shielding and Accident Scenarios Lali Tchelidze May 26, 2014.
JAERI nuclear analyses for IFMIF T. Umetsu, M. Yamauchi and M. Sugimoto Presented by Takeo NISHITANI Japan Atomic Energy Agency (JAEA) IAEA Technical Meeting.
Update for muon studies Helmut Vincke. Additional dump calculations Two options were studied: Option 1: beam is bend by 2 degree towards soil and beam.
Authorization and Inspection of Cyclotron Facilities Design, Layout and Shielding.
Beam loads & dump concepts T. Kramer, B. Goddard, M. Benedikt, Hel. Vincke.
Radiation Protection aspects for SHIP Doris Forkel-Wirth, Stefan Roesler, Helmut Vincke, Heinz Vincke CERN Radiation Protection Group 1 st SHIP workshop,
Activation around dump shielding, and design of beam line mask Mathieu Baudin, RP Genevieve Steele, EN-STI Helmut Vincke, RP.
Considerations for an SPL-Beamdump Thomas Otto CERN in collaboration with Elias Lebbos, Vasilis Vlachoudis (CERN) and Ekaterina Kozlova (GSI) Partly supported.
1 Sector Test – Preparation Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
Radiation Protection in J-PARC neutrino beam line Sep Yuichi Oyama (KEK) for T2K neutrino beam line construction group Happy birthday.
HL-LHC Standards and Best Practices Workshop CERN, June 13, 2014 Best Practices for ALARA C. Adorisio and S. Roesler on behalf of DGS-RP.
New SPS scraping system: preliminary RP remarks Helmut Vincke DGS-RP.
NToF - Radiation Protection M. Brugger, P. Cennini, A. Ferrari, E. Lebbos, V. Vlachoudis CERN AB/ATB/EET.
WP2 progress on safety E. Baussan EUROnu CB Meeting Monday 10th & Tuesday 11th June 2011 CERN, Geneva, Switzerland.
Radiation protection and radiation safety issues for HIE-ISOLDE. FLUKA calculations Y. Romanets ISOLDE Workshop and Users meeting 2010 CERN, 8 December.
Radiation Protection studies for the Linac4 / Linac2 interface Joachim Vollaire, DGS-RP 28/09/2015 Linac4 Coordination Meeting.
1 Radiation Monitoring at CTF3 CTF3 Buildings – weak spots Radiation Monitoring system Monitoring results – First Lessons Idelette Floret, Thomas Otto,
Radiation Protection Considerations for the CDR Helmut Vincke DGS-RP.
Mixed field irradiation -- Who answered ?  In total 36 forms filled / 34 persons answered: 38% 62% CERN: mainly LHC related topics CERF: beside LHC topics.
Characterization of the nTOF Radioactive Waste M. Brugger, P. Cennini, A. Ferrari, V. Vlachoudis CERN AB/ATB/EET.
HIGH RADIATION TO MATERIALS Ans Pardons for the HiRadMat project team IEFC Workshop, March 22, 2011 Outline  The HiRadMat facility – Why, What, When,
R ADIATION P ROTECTION ASPECTS LSS1 LHC f RE - INSTALLATION Cristina Adorisio (CERN - DGS/RP) LTEX Meeting – May 10 th, 2012.
1 July 2004 Radiation Protection Issues 1 M.Brugger, D.Forkel-Wirth, S.Roesler, H.Vincke SC/RP Review of the LHC Collimation Project 30 June – 2 July 2004.
PRESENT AND FUTURE TEST FACILITIES FOR HIGH- INTENSITY TARGETRY CERN I.Efthymiopoulos, CERN with input from Jacques Lettry & Rende Steerenberg.
The Panorama of the Future Radioactive Areas from now to 2020 S. Roesler on behalf of DGS-RP Workshop on remote manipulations and diagnostics in radioactive.
EURISOL DS Task meeting Orsay, 07 Janvier Preliminary shielding assessment of EURISOL Post Accelerator D. Ene, D. Ridikas. B. Rapp.
HIRADMAT/ IRRADITION facilities Overall view with the biggest object to irradiat, T9 shielding with TED inside and the beam dump with 12 meters of cast.
The target handling concept of the pbar- separator at FAIR M. Helmecke, V. Gostishchev, R. Hettinger, K. Knie 6th High Power Targetry Workshop Oxford.
Neutron double differential distributions, dose rates and specific activities from accelerator components irradiated by 50 – 400 MeV protons F. Cerutti.
Radiological Safety for Experiment T-489 Irradiation Experiment in Endstation A Spring 2007 ITEMS: Experimental Setup Long-Term Radiation inside ESA Short-Term.
EURISOL, TASK#5, Bucuresti, November 1 Preliminary shielding assessment of EURISOL Post Accelerator D. Ene, D. Ridikas. B. Rapp.
J. Bauer, V. Bharadwaj, H. Brogonia, A. Fasso, M. Kerimbaev, J. Liu, S
Heating and radiological
Induced-activity experiment:
S. Roesler (on behalf of DGS-RP)
Radiation Protection Issues After 20 Years of LHC Operation
A.-L. Perrot, TS/LEA-int LEMIC A.L. Perrot – TS/LEA/int LEMIC
Evangelia Dimovasili TS/LEA
Studies on Energy Deposition and Radiation for the 4horn system
CATIA users meeting 07/06/2012 Material guidelines project – radiological hazard classification Helmut Vincke, Chris Theis on behalf of DGS/RP RSO committee.
Radiation protection of Linac4 M. Silari Radiation Protection Group
TI8/WIC Incident & UJ87/UA87 Radiation Levels & Analysis
Preliminary Study – Radiation induced activity in a SB Target
Fassò, N. Nakao, H. Vincke Aug. 2, 2005
Present and Future test facilities for High-intensity Targetry CERN
C. Adorisio Extracted from the presentation given at
T-489: Induced Activity and Residual Dose Rates
Presentation transcript:

First radiological estimates for the HIRADMAT project H. Vincke and N. Conan 1

Contents 1.Results of the radiation survey around the WANF target area (2008) 2.Collective dose to be expected for a WANF area dismantling 3.Residual dose rates to be expected in the empty WANF area 4.Residual dose rates to be expected from the HIRADMAT beam operation 2

Radiation survey (24/9/08) around the T9 Target – WANF area 6.5 Old TAX blocks storage at 40 cm Dose Rate in µSv/h to 10 Dose rate inside and downstream the target shielding will be significantly higher than 1 mSv/h Gamma spectroscopy of concrete samples taken in the area showed that the concrete tunnel structure is radioactive 3

Dismantling of the WANF AREA The WANF facility was already once fully dismantled in For the removal of the old WANF beam line a collective dose of 210 mSv was taken by the personnel. The full refurbishment of the area caused an additional collective dose of 170 mSv. According to reports from that time, the residual dose rate in the area of the target was at least 2 times higher than today. Hence, as a first order estimate we can expect a collective dose which is a factor of 2 lower than the one received in From the RP point of view it is recommended that the zone is dismantled. The dose rate will not drop substantially in the next 10 years. However, the area conditions (rust, dirty) worsen with time. Space for the radioactive WANF material still has to be found. Hence, a reuse of radioactive material (e.g.: WANF target station) in the beam dump is advisable. 4

First radiation studies concerning the radioactivity level of the empty WANF area (after removal of the WANF beam line equipment) 5

Procedure to obtain dose rate results considering the concrete only The dose rate of the concrete cannot be measured directly: The surrounding beam line elements are highly radioactive and overshadow the dose rate coming from the concrete The concrete with the highest radioactivity is inaccessible (blocked by beam line components) FLUKA simulations have to be conducted to obtain first ideas about the radioactivity level of the empty area. Drawbacks: the simulation results are only as good as the input parameters of the simulations: Details of geometry (target and shielding parameters) Concrete composition (real composition unknown, typical CERN concrete was used in the simulations)  Results should be seen as indication and not as accurate number 6

FLUKA simulation geometry used for the WANF simulations Tunnel Target station 110 m 7

Details of target station used in simulation (Information taken from ACAD file, received from M. Lazzaroni) Iron shielding Marble shielding Be-target Beam 8

Simulation procedure to obtain residual dose rate in the empty tunnel Two steps: 1.Simulation of the beam impact in the target producing a radionuclide “inventory” in the concrete tunnel. Beam parameters used : 10 years of operation (2E19 protons per year) + subsequent cool down of 10 years. 2.Simulation of the decay of radionuclides (beta or gamma emission) in the concrete considering only the empty beam tunnel (without beam line elements)  dose rate map 9

Dose rate profile in the empty WANF tunnel (after removal of beam line) Position of target station Radiation in this area might be considerably higher since beam line equipments in this area were not taken into account in this first estimate 10

Profile taken over  y = 60,  x = 180, along the beam line x y z Dose rate (uSv/h) seen by a person (1.8 m) walking through the empty tunnel Location of Target station Profile taken over  y = 60,  x = 180, beside target station Most preferable place for installation work can be found upstream the target station. 11

In case HIRADMAT cannot be installed upstream the WANF target station location  Bypass tunnel leading to low radiation location Tunnel made of 40 cm concrete walls + 20 cm concrete floor reduces dose rate from 200 uSv/h to 5 uSv/h Tunnel made of 40 cm concrete walls (no additional floor) reduces dose rate from 200 uSv/h to 60 uSv/h Effect of bypass tunnel 12

Generic studies concerning residual dose rate levels caused by the future HIRADMAT collimator irradiation Estimates are based on the report “CERN-SC RP-TN”: Remnant dose rates in the area of a TCDI collimator after 200 days of normal operation and after an accidental beam loss; Helmut Vincke 2 irradiation scenarios 1.Short term scenario: impact of 10 subsequent full SPS beam cycles (3.3E13 protons per cycle) 2.Long term scenario: 1E16 protons equally distributed over 200 days 5 cooling times 1.1 hour 2.12 hours 3.1 days 4.1 week 5.1 month Beam Concrete wall TCDI (carbon) collimator Beam line elements 13

10 full SPS beam cycles (3.3E13 protons per cycle) 1E16 protons equally distributed over 200 days Cooling time Dose rate between wall and beam line Dose rate maximum value Dose rate between wall and beam line Dose rate maximum value 1 hour26 mSv/h1.3 Sv/h 800  Sv/h 32 mSv/h 12 hours2 mSv/h66 mSv/h 600  Sv/h 24 mSv/h 1 day 660  Sv/h 15 mSv/h 480  Sv/h 20 mSv/h 1 week 66  Sv/h 3.3 mSv/h 280  Sv/h 12 mSv/h 1 month 26  Sv/h 0.7 mSv/h 200  Sv/h 6 mSv/h Summary for full loss and operational scenario The dose rate level in the tunnel after one year of operation is higher than the dose rate in the empty WANF tunnel. The long term irradiation levels are mainly caused by the two elements installed in the beam line and not by the concrete walls In case the carbon jaws are replaced by copper or tungsten jaws, the dose rate will increase significantly Dose rate after1E16 protons in 200 days + 1 month of cooling mSv/h 14

Summary WANF area is still radioactive From the RP point of view it is recommended to dismantle the WANF area. Storage space for radioactive waste has to be found. Radioactive material (e.g.: WANF target station) should be reused as beam dump. In terms of the radioactivity distribution in the WANF area it would be preferable to install HIRADMAT upstream the target location Residual dose rates caused by one year of HIRADMAT operation (generic model) was calculated to be higher than the current dose rate of the empty WANF tunnel 15

END 16

Arguments against installation in TI8 (TJ8) or TT40 area LHC and CNGS beam goes through the same area Due to the high dose rate around the equipment after the test, operation of LHC and CNGS will be jeopardized in case beam line equipment has to be repaired in the surroundings of the test area Significant waiting times before installation have to be expected Due to these reasons test areas should be installed in dedicated areas only The same argument can also be used for the installation close to the T1 target position in TT60/TI2 area (option B in Ilias’ presentation). 17

Residual dose rate comparison between tungsten and carbon jaws 18

1E13 protons Irradiation time: 2d, cooling time: 1d Hot spot: ~ uSv/h Tungsten collimator Carbon collimator Hot spot: ~ 460 uSv/h 19

1E13 protons Irradiation time: 2d, cooling time: 1w Hot spot: ~ 1500 uSv/h Tungsten collimator Carbon collimator Hot spot: ~ 150 uSv/h 20

1E13 protons Irradiation time: 2d, cooling time: 1m Hot spot: ~ 220 uSv/h Tungsten collimator Carbon collimator Hot spot: ~ 40 uSv/h 21