1 INTRA – STATE AVAILABILITY BASED TARIFF (ABT) A Presentation on INTRA – STATE AVAILABILITY BASED TARIFF (ABT)

Slides:



Advertisements
Similar presentations
1 FREQUENCY LINKED DISPATCH AND ELECTRICITY PRICING (An unconventional approach for tackling the peculiar problems existing in India) - Bhanu Bhushan -
Advertisements

1 PRESENTATION ON INTRA – STATE ABT BY GENERAL MANAGER (SLDC) DELHI.
Sharing of ISTS Charges & Losses Regulation
1 FREQUENCY CONTROL -- Bhanu Bhushan -- (April, 2011)
OPEN ACCESS IN INTER-STATE TRANSMISSION. DEFINITION OF “ OPEN ACCESS ” IN THE ELECTRICITY ACT, 2003 “The non-discriminatory provision for the use of transmission.
Duke Energy Ohio Standby Rates Jim Ziolkowski, P.E., Rates Manager September 13,
Ramping and CMSC (Congestion Management Settlement Credit) payments.
Energy Storage Definitions/Definitions ETWG 18 Feb 2013.
Maharashtra State Load Despatch Centre Role of SLDC in RRF Implementation & Issues By MSLDC.
1 Framing Regulatory and Government Policy India Energy Mart 2004 New Delhi S L Rao.
1 ABT Based Boundary Metering. 2 ABTBoundary Metering+
Congestion When transmission demand >capability When Voltage levels in a corridor beyond operable limits When Real time line flow exceeds the TTC Most.
Development Of A Common Platform For Electricity Trading CERC Public Hearing Presentation By POWERGRID 19-December-2006.
RRF Mechanism ENERGY ACCOUNTING Western Regional Power Committee
INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.
1 Least Cost System Operation: Economic Dispatch 2 Smith College, EGR 325 March 10, 2006.
Costs of Ancillary Services & Congestion Management Fedor Opadchiy Deputy Chairman of the Board.
1 THE INDIA ELECTRICITY MARKET TIME LINE REAL TIME 15 MT BLOCKS LONG TERM LOAD FORECAST FUND MOBILISATION 10-5 YEARS POWER PURCHASE AGREEMENTS CAPACITY.
Module on Computation of PoC Transmission Charges
IEGC PROVOSIONS FOR RENEWABLE GENERATION SCHEDULING & UI SETTLEMENT 1.
1. 2 ENERGY MANAGEMENT SYSTEM AN OVERVIEW AN OVERVIEW.
Welcome New York Independent System Operator. (Pre-NYISO) Regulated Market Physical contracts Regulated industry Cost Based System Two Party Deals Bundled.
Options for Renewable/ Captive/ IPPs etc. EXTRACTS FROM ELECTRICITY ACT 2003 Para 3(1) NATIONAL ELECTRICITY POLICY AND PLAN: The Central Government shall,
‘S ORDER ON AVAILABILITY BASED TARIFF PRESENTATION BY C.V.ANAND Sr.Supdt (Comml)
With amendments w.e.f  (1) In these regulations, unless the context otherwise requires,-  (a) ‘Act’ means the Electricity Act, 2003 (36.
Section 7.5 –4 – ii of Indian Electricity Grid code (IEGC): “The summation of station-wise ex-power plant drawal schedules for all ISGS after deducting.
Ontario Electricity Supply Forum PEO Mississauga Chapter - September 6, 2007 Rhonda Wright-Hilbig, P.Eng Market Analysis - IESO.
CERC Paper on Open Access Presentation by the MPERC Bhopal At New Delhi 25 September 2003.
CAPTIVE POWER POLICY. Section 44 of the Electricity(Supply) Act, 1948 gave birth to Captive Generation.  Any other person to establish or to acquire.
PJM©2013www.pjm.com Economic DR participation in energy market ERCOT April 14, 2014 Pete Langbein.
PETITION BY TNEB TO INVESTIGATE ANY GAMING BY THE GENERATORS PETITION NO:- 90/2005 CERC HEARING ON 06-OCT-05.
Power Trading By P.S.Bami President – India Energy Forum & Former Chairman & Managing Director, NTPC 1.
Open Access for Renewables New initiatives. Scheduling and OA of RE Open Access through LTA/ MTOA/ STOA route envisaged Applicable to Wind and Solar without.
Sharing of Inter-State Transmission Losses 11/29/
Queries raised by Director (Tariff) on ARR and Tariff Application of OPTCL for FY on
Low Peak Frequency High Off-Peak Frequency Wide Frequency Fluctuation Damage to Generating Plants and Consumers’ Equipment Merit Order not followed - Optimizat.
SRLDC 1 POWER SYSTEM OPERATION A FRESH PERSPECTIVE Power Grid Corporation of India Limited New Delhi, India.
ABT / IEGC CLAUSES While making or revising their declaration of capability, the generator shall ensure that their declared capability during peak hours.
MERIT ORDER OPERATION AND GRID DISCIPLINE S.P.KUMAR MANAGER(IT), SRLDC,BANGALORE.
HYDRO TARIFF Commission Tariff Notification 26/03/01 Commission Tariff Notification 26/03/01 Applicable Period 01/04/01 to 31/03/04 Applicable Period 01/04/01.
NLDC 1 Ancillary Services in Indian Context. NLDC 2 Outline Definition Drivers for Ancillary Services Ancillary Services in Indian Context.
IMPACT OF ABT, NETWORK STRENGTHENING ON GRID OPERATION IN KARNATAKA SOUTHERN REGIONAL LOAD DESPATCH CENTRE POWER GRID CORPORATION OF INDIA LIMITED ADVANTAGE.
Workshop on State-Level Electricity Reforms: Firm Choices, Emerging Generation Markets and Externalities “Open Access: Experiences” ALOK ROY General Manager,
Congestion regulations. Definitions and Interpretation “Available Transfer Capability (ATC)” means the transfer capability of the inter- control area.
OPEN ACCESS IN INTER STATE TRANSMISSION. Gazette Notification of Open Access in inter state transmission systemGazette Notification of Open Access in.
Talha Mehmood Chapter # 5 TARIFF. Introduction The electrical energy produced by a power station is delivered to a large number of consumers. The supply.
G1 G2 SERC SLDC SEB/STU State Govt. RLDC REB CTU CERC Central Govt. CEA ISTS ISGS Load L1L2 Intra State System IEGC to Operate on the periphery X=- GLG.
Illinois Wholesale Market Update December 10, 2003.
POWER SECTOR REFORMS Grid Operation and Control in the changed Scenerio.
Availability Based Tariff (ABT) in Northern Region.
AVAILABILITY BASED TARIFF AND SCHEDULING MECHANISM.
Transmission Tariff V.Balaji Chief Manager SRLDC.
Extract from Annexure-1 on ‘Complementary Commercial Mechanisms of Indian Electricity Grid Code ’12(a) Weekly bills shall be issued to the constituents.
NORTHERN REGIONAL LOAD DISPATCH CENTER 1.Revision Of Ceiling Of UI Rates and slope. 2.Revision Of Schedule after a Transmission Constraint is over. 4.RLDC’s.
SOUTHERN REGIONAL GRID ▀ Centre Generating Stations in the Region are Ramagundam Super Thermal Power Stn. : 2,600 MW (200x x4) Neyveli Lignite Corporation.
OPEN ACCESS EXPERIANCES AND WAY-AHEAD V K Agrawal, General Manager, SRLDC WORKSHOP ON GRID SECURITY AND MANAGEMENT 28 th and 29 th April, 2008.
Issue of Declared Capacity (DC), and Actual Generation (AG) by Generating Stations Hon’ble Commission has issued Interim order dated 19/ directing.
Demarcation of responsibilities (as per IEGC) 1. REGIONAL GRID SHALL BE OPERATED AS LOOSE POWER POOLS WITH STATES HAVING FULL OPERATIONAL AUTONOMY. 2.SYSTEM.
Southern Regional Power Committee Central Electricity Authority.
AVAILABILITY BASED TARIFF. - Tariff structures - Two part tariff - Concept of ABT - ABT structure - Expectations from OEMs/Utilities Session outline.
MERIT ORDER SCHEDULING AND DESPATCH V. K. AGRAWAL NRLDC.
Point of connection Mechanism
OPEN ACCESS IN INTER STATE TRANSMISSION 29 TH MARCH TH MARCH 2004.
Grid Operation --- Role of RLDC. Contents Load Generation Balance Electricity Accounting Real Time Trends ABT Feedback Inter Regional Exchanges Loading.
Transmission Tariff Regulations. 1. ‘Applicant’ means a generating company or transmission licensee who has made an application for determination of tariff.
Open Access.
IN ADDITION OF UI RATE CORROSPONDING TO FREQUENCY OF 49
Sharing of Inter-State Transmission Losses
Congestion regulations
GRID STATUS – PRE - ABT Very wide Frequency fluctuations
Presentation transcript:

1 INTRA – STATE AVAILABILITY BASED TARIFF (ABT) A Presentation on INTRA – STATE AVAILABILITY BASED TARIFF (ABT)

2 Intra-state ABT is a techno-economic tool for bringing rational tariff structure for supply of electricity from State generators to the distribution Licensees. It is a mechanism for enforcing discipline in the Grid. Why Intra – State ABT

3 a)Benefits to the Power System Brings about grid discipline by maintaining frequency in prescribed band (49.5 to 50.5 Hz). Ensures optimum utilization of available generation capacities. Enhances opportunities for Open access, and Trading of electricity. Scope for encouraging competition among generators. Benefits of Intra – State ABT

4 b)Benefits to the Generator Encourages maximization of Generation during peak hours with incentives and discourages the same during off-peak hours with penalties linked with frequency. Enables systematic scheduling in terms of long term, short term as well as day ahead, duly considering plant availability and maintenance. Ensures better life of equipments due to efficient management of Demand Vs Supply. Thereby the ‘Hidden Costs’ due to damage is avoided. The three-part Tariff under ABT provides for proper recovery of fixed and variable costs of Generator.

5 c)Benefits to the Distribution Licensees Economic efficiency dictates that the least cost power should be dispatched in preference to costly power (Merit Order Dispatch). ABT provides for the same. Licensees can plan their requirement, both for peak and off peak demands. Enables efficient Load Management through their own Area Load Dispatch Centers.

6 d)Benefits to the End Users Enables open access, captive generation and trading of electricity. Ensures quality and reliable power supply. Scope for reduction in cost of power due to licensees opting for merit order dispatch in their scheduling.

7 CONSTITUENTS OF INTRA-STATE ABT in RAJASTHAN 1.JVVNL 2.AVVNL 3.JdVVNL 4.RVUN

8 ABT BILLING METHODOLOGY ABT is, basically, a three part tariff system consisting of the following components :- Fixed charges – on monthly basis subject to adjustment on yearly basis. Variable charges - on monthly basis. Unscheduled inter-change (UI) charges. – on weekly basis.

9 The UI for a Generating Station shall be equal to its actual generation minus its scheduled generation. UI for States shall be equal to its total actual drawal minus its total scheduled drawal. UI shall be worked out for each 15 minutes time block. Charges for all UI transactions are based on average frequency of the time block. The UI Tariff structure w.e.f., 07/01/2008 is as under. UNSCHEDULED INTER-CHANGE (UI) CHARGES Average Frequency of time-block UI Rate (P/kWh) Hz and above 0.00 Below Hz and upto Hz 8.00 Below Hz and upto Hz Below Hz and upto Hz Below Hz Between Hz and Hz Linear in 0.02 Hz 8 P/kWh for each step Below Hz Linear in 0.02 Hz 18P/kWh for each step

10 INTRA-STATE UI RATE UI S = UI R / (1-L) Where, UI S is Intra State ABT rate for a frequency step UI R is UI rate applicable for Northern Region for that frequency step L is the Inter-State transmission losses of NR in per unit

11 UI SETTLEMENT MECHANISM IN INTRA-STATE ABT At Inter – state level the Unscheduled interchanges of Inter regional sources are determined with reference to their schedule at the point of injection but those of SEBs with reference to their ex-periphery schedule. Datum for working out UI not being same for all entities, this results in UI MISMATCH which is equalised by averaging the two ON DAILY BASIS. The above adjustment is required to equalize payable UI amount to receivable UI amount so that UI pool account is maintained as a Zero balance account.

12 METHODOLOGY FOR ZERO BALANCING THE UI POOL ACCOUNT AT INTER-STATE LEVEL 1.UI AMOUNT IS DRAWN FOR ALL THE UI POOL MEMBERS ON ACTUAL BASIS. 2.FROM THE UI ACCOUNT AMOUNT RECEIVABLE MEMBERS AND AMOUNT PAYABLE MEMBERS TO THE POOL IS SEPERATELY DRAWN OUT. 3.AMOUNT PAYABLE AND RECEIVABLE WILL NOT MATCH BECAUSE FOR GENERATORS THE UI IS DRAWN OUT BASED ON INJECTION & SCHEDULE AT GENERATOR PERIPHERY WHEREAS FOR STATES THE SAME IS BASED ON DRAWAL & SCHEDULE AT STATE PERIPHERY. 4.AS PER THE CERC STIPULATION THE UI POOL ACCOUNT SHOULD BE A ZERO BALANCE ACCOUNT. 5.THE UI MIS-MATCH IS CALCULATED ON DAILY BASIS AND APPORTIONED TO ALL UI POOL MEMBERS IN THE RATIO 50:50 TO THE PAYING AND RECEIVING MEMBERS IN THE RATIO OF THE ORIGINAL UI AMOUNT DRAWN OUT. 6.A CASE STUDY BASED ON THE ABOVE METHODOLOGY FOR UI ACCOUNT ISSUED BY NRPC IS SHOWN IN THE NEXT SLIDE.

13 SAMPLE CASE FOR 19 TH MARCH 2007 ACTUAL UI AMOUNT FOR PAYEE AND RECEIVING CONSTITUENTS

14 METHODOLOGY FOR ZERO BALANCING THE UI POOL ACCOUNT AT INTER-STATE LEVEL MIS-MATCH BETWEEN THE PAYABLE AND RECEIVABLE AMOUNT FROM THE UI ACCOUNT IS ( )= LACS RUPEES. THIS DIFFERENCE IS DIVIDED EQUALLY BETWEEN THE TWO i.e.PAYING & RECEIVING ENTITIES IN THE RATIO 50:50 AMOUNTING TO LACS RUPEES EACH. SINCE NO INTER-REGIONAL LINK IS AMONGST THE RECEIVING UTILITES LACS IS DIVIDED AMONGST ALL THE RECEIVING UTILITIES IN PROPORTION TO THEIR UNADJUSTED UI AMOUNT. AMONGST THE PAYING UTLITIES EXCLUDING THE INTER- REGIONAL LINKS THE AMOUNT OF LACS IS CREDITED TO ALL IN PROPORTION TO THEIR UNADJUSTED UI AMOUNT. THE ADJUSTED ACCOUNTS ARE DISPLAYED IN THE NEXT SLIDE.

15 ADJUSTED UI ACCOUNT FOR PAYEE AND RECEIVING CONSTITUENTS

16 In Intra – State ABT also the UI account should be a Zero Balance Account which indicates UI payable/receivable to/from the Regional UI pool account should be equal to the UI receivable/payable in the Intra-State UI pool Account. The following mechanism is proposed : 1. SLDC shall draw-out the Intra-state UI account in same principle as that of Inter-state UI account. 2. The amount payable / receivable to the Regional pool account would then be equated on the basis of Intra-state ABT amount. METHODOLOGY FOR ZERO BALANCING THE UI POOL ACCOUNT AT INTRA-STATE LEVEL

17 SAMPLE CASE FOR INTRA-STATE ABT SETTLEMENT ACTUAL UI AMOUNT FOR PAYEE AND RECEIVING CONSTITUENTS calculated for dated 18/02/2008

18 METHODOLOGY FOR ZERO BALANCING THE UI POOL ACCOUNT AT INTER-STATE LEVEL MIS-MATCH BETWEEN THE PAYABLE AND RECEIVABLE AMOUNT FROM THE UI ACCOUNT IS ( )= LAC RUPEES. THIS DIFFERENCE IS DIVIDED EQUALLY BETWEEN THE TWO i.e.PAYING & RECEIVING ENTITIES IN THE RATIO 50:50 AMOUNTING TO LACS RUPEES EACH. AMONGST THE RECEIVING UTILITES LACS IS DIVIDED AMONGST ALL THE RECEIVING UTILITIES IN PROPORTION TO THEIR UNADJUSTED UI AMOUNT. AMONGST THE PAYING UTLITIES EXCLUDING THE INTER- STATE ACCOUNT THE AMOUNT OF LACS IS CREDITED TO ALL IN PROPORTION TO THEIR UNADJUSTED UI AMOUNT. THE ADJUSTED ACCOUNTS ARE DISPLAYED IN THE PREVIOUS SLIDE.