CERN- KEK about LHC upgrades programs Lucio Rossi 14 December 2011.

Slides:



Advertisements
Similar presentations
1 Methods of Experimental Particle Physics Alexei Safonov Lecture #8.
Advertisements

The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
WLCG Collaboration Workshop, “Gotham City”, May 2012 Introduction WLCG Collaboration Workshop, “Gotham City”, May 2012 Introduction.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Future Accelerators at the High Energy Frontier
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
J-PARC Accelerators Masahito Tomizawa KEK Acc. Lab. Outline, Status, Schedule of J-PARC accelerator MR Beam Power Upgrade.
Cryogenics in SPS & LHC (2 K / 4.5 K) LHC-CC11, 14 November 2011 L. Tavian, CERN, TE-CRG With the contribution of N. Delruelle, G. Ferlin & B. Vullierme.
Eric Prebys, FNAL Snowmass 2013 Community Planning Meeting Fermilab, October 11-13, 2012 Minneapolis.
High Luminosity LHC (HL-LHC) and Crab Cavities Lucio Rossi CERN LHC Crab Cavity Worshop 15 Dec 2010.
Accelerator Group for LHeC LHeC Meeting at CERN; October Questions raised by Max  does the e-ring fit into the tunnel?  can one bypass ATLAS and.
EPPOG - LHC Machine LHC machine (and some outreach) Mike Lamont.
HL-LHC: scope, structure and management HL-LHC internal kick-off day 15 April 2011.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
February 2010 ALBA Synchrotron Light Source Francis Perez.
The CERN Roadmap Frédérick Bordry
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
WP2 status Gijs de Rijk This project has received funding from the European Community's Seventh Framework Programme (FP7/ )
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
JRA on Development of High Temperature SC Link Motivation Work Packages Partners & resources Amalia Ballarino Esgard open meeting CERN,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
LINAC4 and the Upgrade of the LHC Injector Complex R. Garoby 26 February, 2013.
FP7 HiLumi LHC Design Study Lucio Rossi CERN. Structure of the project HL-LHC and the FP7 HiLumi FP7 Design Study
HL-LHC Organization: Now and post HiLumi
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Cryogenics for crab cavities – SPS/LHC 2 nd HiLumi LHC meeting – Frascati (Italy) 15 November 2012 K. Brodzinski and L. Tavian on behalf of cryogenic team.
Superconducting Technologies for the Next Generation of Accelerators CERN, Globe of Science and Innovation 4-5 December Superconducting Links for the Hi-Lumi.
Already time to think of upgrading the machine Two options presently discussed/studied Higher luminosity ~10 35 cm -2 s -1 (SLHC) –Needs changes in.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
WP2: Beam dynamics and optics Workflow between Work Packages 1 O. Brüning – BE-ABP WP2 HL-LHC meeting 17. November 2011.
TE-CRG Activities D. Delikaris, TE-CRG.
Updates on Tevatron and LARP Vladimir Shiltsev FNAL/Accelerator Physics LARP/Accelerator Systems.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Eric Prebys, Fermilab Director, US LHC Accelerator Research Program (LARP) May 16, 2011.
Eric Prebys, Fermilab Program Director, LARP July 10, 2012.
New Magnet Technology (for high field) Lucio Rossi CERN INFN - CNS1 future strategy Elba 22 May 2014.
Crab Cavities for the HL-LHC Project Definition and Design Study E. Ciapala, E. Jensen, J. Tuckmantel (CERN) R. Calaga (BNL) US-LARP CM15, November 2010,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The High Luminosity LHC Project
EuCARD WP 7 – High Field Magnets EuCARD WP 7 – High Field Magnets Aim and goals Mini Workshop of Accelerators Radiation Mini Workshop of Accelerators Radiation.
Lucio Rossi The High Luminosity LHC Project Distinguished Lecturer 2013.
Lucio Rossi for the LARP Internal Project Review Via videlink, June 10, 2013.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The FCC Magnet Program seen from CERN Meeting at ASC-2014, Charlotte, August 13t, 2014.
CERN, 11th November 2011 Hi-lumi meeting
The CERN Linac4 history, performance, perspectives
Cryogenics storage and distribution
High Luminosity LHC (HL-LHC) and Magnet progress
contribution to the round table discussion
FP7-HiLumi LHC Design Study Summary and Feedback
Overview Summer student lectures 2016
LHC upgrade: High Luminosity
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
e-lens Readiness Review Introduction
Hollow e- lens, Cryogenic aspects
Accelerator and Experiment Interface Session: LS2, LS3
The HL-LHC project, and associated Cryogenics
The HL-LHC project: info day for industry
Acknowledgments: LIU-PT members and deputies, H. Bartosik
CSP Meeting CERN CERN Accelerators in th November 2010
SLHC-PP kick-off meeting, CERN 9 April 2008
Review of Quench Limits
Presentation transcript:

CERN- KEK about LHC upgrades programs Lucio Rossi 14 December 2011

The path and goals: 3000 fb -1 – L peak < Dec20112 Rad. damage

Tuning of the goal after summer Efficiency is defined as the ratio between the annual luminosity target of 250 fb -1 over the potential luminosity that can be reached with an ideal cycle run time with no stop for 150 days: t run = t lev +t dec +t turn. The turnaround time after a beam dump is taken as 5 hours, t decay is 3 h while t lev depends on the total beam current Dec20113

Cycle in the HL-LHC run 20E+34 pile up heat deposition in IR and DS other? pile up heat deposition in IR and DS other? Dec20114

Possible evolution toward 3000 fb -1 Dec20115

IR Magnets (triplet, D1, D2, MQ4, …) SC Crab Cavities, IR Collimation Dec20116

7 Other changes Cryogenics Cryogenics During LS2, a new refrigerator will be installed at P4, to feed RF cavities and restore IR 5L During LS2, a new refrigerator will be installed at P4, to feed RF cavities and restore IR 5L Refrigerator K: Refrigerator K: 4.5 kW kW (flash) kW (thermal losses line & valve box) kW (contingency 33%) 4.5 kW kW (flash) kW (thermal losses line & valve box) kW (contingency 33%) During LS3 new refrigerators for P1-P5 During LS3 new refrigerators for P1-P5 Warm compressor installed in surface. Warm gas lines in Pit Warm compressor installed in surface. Warm gas lines in Pit Cold boxes installed in underground and surface (if 2 K or 1.8 K options) Cold boxes installed in underground and surface (if 2 K or 1.8 K options) Distribution and transfer lines to equipments (magnets, DFBs, crab-cavities ?, SCL ?, sector powering ?...) Distribution and transfer lines to equipments (magnets, DFBs, crab-cavities ?, SCL ?, sector powering ?...)

Dec20118 Other changes (list not exhaustive…) R2E: whatever needed, see from experience frome next years R2E: whatever needed, see from experience frome next years P8 P8 Removal of EPC and DFBX from tunnel to surface via long SC links rated of GW d.c. Removal of EPC and DFBX from tunnel to surface via long SC links rated of GW d.c.

Dec20119 LIU – LHC Inj Upgrade (R. Garoby) LS2 (2018) and LS3 ( ) Linac4 (160 Mev H- vs. 50 MeV H of Linac2) Ready by mid 2014 Connected 2015? Reliability, brilliance… Linac4 (160 Mev H- vs. 50 MeV H of Linac2) Ready by mid 2014 Connected 2015? Reliability, brilliance… PS Booster upgrade: from 1.4 GeV (800 Gev) to 2 GeV to reduce space ahrge at PS injection Intensity gain : +65% Project launched; PS Booster upgrade: from 1.4 GeV (800 Gev) to 2 GeV to reduce space ahrge at PS injection Intensity gain : +65% Project launched; SPS reduction of impedence new optics with low  t (26  15 GeV) new 200 MHz cavities reduction e-clouds by vaccum chamber coating (or scrubbing?) SPS reduction of impedence new optics with low  t (26  15 GeV) new 200 MHz cavities reduction e-clouds by vaccum chamber coating (or scrubbing?)

The HL composition, larger than FP7 HiLumi Collimation Project Matching section and correctors Beam Diagnostics High Field Magnets R&D HE-LHC Studies Hardware Commissioning EuCARD2 WP10 on HTS dipoles Dec201110

Dec Budget FP7 HiLumi and HL-LHC Perfect score 15/15, ALL request to EU granted Estimated cost for the the whole HL-LHC over 10 years in M€ (October 2010)

Dec days Collaboration Meeting at CERN Nov (160 people) Collaboration Board members/invited

Dec201113

Staff HiLumi Design Study, with 377 p-m by US Labs and 159 by KEK (Magnets, CC, AP) 163 FTE-y Dec201114

Dec New baseline to follow the new EU strategy for HEP! Goal: HL-LHC approved by 2013 CB of 17 Nov 2011, message from President of Council, Prof. Spiro: PDR needed in preliminary form by Oct 2012, endorsed by SAC and MAC, approved by CERN Mngt for Council and HEP strategy Group (final step : Council Bruxelles June 2013) CB of 17 Nov 2011, message from President of Council, Prof. Spiro: PDR needed in preliminary form by Oct 2012, endorsed by SAC and MAC, approved by CERN Mngt for Council and HEP strategy Group (final step : Council Bruxelles June 2013) Need to fix choice earlier

Malta Workshop14-16 October TeV c.o.m Dec Magnet design: very challanging but not impossible. 300 mm inter-beam Multiple powering in the same magnet (and more sectioning for energy) Work for 4 years to assess HTS for 2X20T to open the way to 16.5 T/beam. Otherwise limit field to 15.5 T for 2x13 TeV Higher INJ energy is desirable (2xSPS) The synchrotron light is not a stopper by operating the beam screen at 60 K. The beam stability looks « easier » than LHC thanks to dumping time. Collimation is possibly not more difficult than HL-LHC. Reaching 2x10 34 appears reasonable. The big challenge, after main magnet technology, is beam handling for INJ & beam dump: new kicker technology is needed since we cannot make twice more room for LHC kickers.

Dec EC - FP7 EuCARD2 joint research activity WP10 : Future Magnets : WP10 : Future Magnets : T HTS Dipole Magnets 40 mm bore Accelerator Quality 5 T HTS Dipole Magnets 40 mm bore Accelerator Quality To be tested as insert in existing 13 T magnet To be tested as insert in existing 13 T magnet KEK and Univ. of Kyoto (and 5 US labs & Univ) declared associate collaborators. Interest in YBCO technology. KEK and Univ. of Kyoto (and 5 US labs & Univ) declared associate collaborators. Interest in YBCO technology. BeneficiaryTotal Person- Months Total Personnel direct costs Total Personnel indirect costs Total Sub- contracting cost Total Consumable and prototype direct costs Total Travel direct costs Total Material and travel indirect costs Total direct costs Toal indirect costs Total costs (direct +indirect) Total EC requested funding CERN120 1,129, , ,000 71, ,600 2,000,740 1,200,444 3,201, ,385 CEA54 321, , ,000 20, , , , ,805 INPG43 141,384 84, ,000 8,000 12, ,384 96, , ,672 INFN39 144,495 86, ,000 14,000 86, , , , ,752 KIT16 94, , ,000 10, , , , ,061 SOTON 16 89,680 79, ,000 10, ,680 79, ,495 87,998 UNIGE ,872 65, ,000 4,000 32, ,872 98, , ,239 UT ,580 78, ,000 8,000 34, , , , ,435 BHTS , , ,000 4, , , , ,003 TUT 8 37,757 22, ,000 7,200 49,757 29,854 79,612 31,347 DTI 10 66,687 46, ,000 6, ,687 46, ,368 58,393 TOTAL: 376 2,490,479 1,750, ,492, , ,400 4,149,479 2,446,342 6,595,820 1,700,091

What is the possibile for HE-LHC? Dec US 16 T small dipole EuCARD 13 T large dipole+ 18 T small insert US 13 T Quads FP7-HiLumi US NbSn-HTS development T dip final proto & Industrialization Final delivery Magnets HE-LHC HE-LHC start-up HE-LHC preliminary study HTS for HE-LHC: yes.or.no LARP 11 T long quad EuCARD R&D Industry contracts, start constrution US basic programs and LARP R&D EU FP6-CARE-NED EuCARD2 full bore dipole HTS T R&D dipole models and prototypes

Dec HiLumi (and HE) LHC : the best use of the (renovated) existing infrastructure LHeC ?