MICE Collaboration Meeting Frascati 26 – 29 June 2005 Work Group report On Design & Safety Review.

Slides:



Advertisements
Similar presentations
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Advertisements

MICE: Hall Infrastructure Chris Nelson CEng CM15 8 th June 2006.
G.Barber Tracker Planning & Mechanical Preparation June Tracker Planning & Mechanical Preparation An outline of (known) outstanding work to be carried.
MICE Collaboration Meeting at Frascati, Jun 26~29, 2005 Iron Shield Mounting Design Stephanie Yang.
CEA DSM Irfu - Bernard GASTINEAU - R3B Technical Board Meeting -April 4, Reactions with Relativistic Radioactive ions Beams GSI Large Acceptance.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
Action Who Progress made status Implement central repository for drawings -- need detector information to add to official drawing WL Progress on-going.
MICE RF and Coupling Coil Module Integration Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 27, 2004.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Video Conference 114 September 18, 2008.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
MICE Collaboration meeting at CERN March 28 – April 1, 2004 MICE Cooling Channel --- AFC Module work group report Wing Lau – Oxford.
23 October 2005MICE Meeting at RAL1 MICE Tracker Magnets, 4 K Coolers, and Magnet Coupling during a Quench Michael A. Green Lawrence Berkeley Laboratory.
MICE Safety Review Process and Schedule Elwyn Baynham Tom Bradshaw Iouri Ivaniouchenkov Columbia Meeting June 2003.
Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports.
Tracker Solenoid Module Design Update Steve VirostekStephanie Yang Mike GreenWing Lau Lawrence Berkeley National LabOxford Physics MICE Collaboration Meeting.
Project Report Paul Drumm CM15, FNAL June MICE Schedule Overview First beam September/October 2007 –Shutdown from January 2007 –Eight months for.
1 RAL Integration Issues MICE Collaboration Meeting, Osaka, August 1-3, 2004 Elwyn Baynham, Paul Drumm, Yury Ivanyushenkov, Tony Jones RAL.
9 June 2006MICE CM-15 Fermilab1 Progress on the MICE Cooling Channel and Tracker Magnets since CM-14 Michael A. Green Lawrence Berkeley Laboratory.
Background to the current problem 1. As a result of the high stresses in the bobbin due to the magnet load, the bobbin end plate needs to be increased.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
MICE Collaboration Meeting at Frascati, Jun 26~29, 2005 Diffuser Mounting Design Stephanie Yang.
Paul drumm; 3rd December 2004; AFC MM 1 Why? Goal: Ultimate (CCLRC defined) Safety & Design Review –How do we get there? We need a Process –What is needed?
MICE Collaboration Meeting March 29 - April 1, CERN MICE alignment, tolerances and supports Tuesday March 30 Room Edgar Black/IIT March17-
MICE Installation and Commissioning meeting RAL, 12 June 2007 Diffuser Oxford University.
1 Status of infrastructure MICE Video Conference, August 17, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department.
Phone meeting on PID Detectors 25 Jan 2006 Implementation of PID detectors in the general MICE layout By Wing Lau, Oxford.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
MICE Collaboration Meeting at Frascati, Jun 26~29, 2005 PID Support Design Stephanie Yang.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
MICE Collaboration Meeting Harbin, China 13 – 17 January 2009 Integration Issues By Wing Lau, Oxford University.
G.Barber Mice Tracker Mechanical Progress Imperial Tracker Update Contents:- Components Station Layout Light Guide Map QA Patch Panel Alignment.
Main progress on Design & Safety Review: EmCAL -- Received the revised TRD write up from Ludovico Design & Safety Audit sheets need to be revised to correspond.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
Project manager report paul drumm CM16 October 2006.
Update on alignment kit and stave 250 frame M.Gibson (RAL) 1.
MICE Collaboration Meeting Frascati 26 – 29 June 2005 Work Group report On Design & Safety Review.
J A Hill – EID RAL 1-2 September EE End Cap Mechanical Design ECAL EE End Cap Engineering CMS-UK Collaboration Meeting Brunel University September.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
1 Layout and Installation MICE Collaboration Meeting, RAL, October 27-29, 2004 Elwyn Baynham, Tom Bradshaw, Paul Drumm, Matthew Hills, Yury Ivanyushenkov,
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l History l Requirements l Environment l Design l Structural Integrity l Preparation l.
1 MICE Collaboration meeting at Berkeley 9 – 12 February 2005 Integrated Design & Safety Review Presented by Wing Lau & Paul Drumm.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM29 at RAL, UK February 17, 2011.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
Design & Safety Review Work Group meeting 10 March 2005 Progress update Wing Lau, Oxford.
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
1 MICE PID Group Meeting 11 May 2005 Update on Design & Safety Review Presented by Wing Lau.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab NFMCC at LBNL January 25, 2009.
G.Barber Mice Tracker Mechanical Progress Tracker Mechanical Progress Contents:- Station Space Frame Station Layout Light Guide Map Connectors Patch.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
22 October 2005MICE Meeting at RAL1 Tracker Solenoid Overview Michael A. Green Lawrence Berkeley Laboratory MICE Collaboration Meeting 22 October 2005.
G.Barber Mice Tracker Integration Harbin Jan Mice Tracker Integration Installation requirements & Procedure.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
Tracker 1. Status 2. Expected delivery date of system to RAL 3. Required support infrastructure needed for setup and initial debug. Things like vacuum,
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
1 Status of infrastructure MICE Collaboration Meeting, Frascati, June 26-29, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
1 MICE UK meeting at RAL 05 May 2005 Integrated Design & Safety Review Presented by.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
1 paul drumm; Date; Title …project report …more comments paul drumm february 2005.
K.Long/G.Barber Mice Tracker Mechanical Status CM20 Feb 08 1 Mice Tracker Mechanical Status Contents:- Tracker 1 Status Tracker 2 Status Further Hardware.
MICE Partial Return Yoke Mechanical Design
MICE CM31 Schedule summary
Cryomodule Assembly Plan
Presentation transcript:

MICE Collaboration Meeting Frascati 26 – 29 June 2005 Work Group report On Design & Safety Review

Progress summary on some PID related components and Infrastructures

1046 mm mm z= mm End Coil 120 mm mm mm 7.6 mm mm Diffuser position (relative to the centre of MICE in stage VI). Q9 Diffuser 17-Jan mm 250mm Iron Shield Patch panel 163mm -6173mm Courtesy of Paul Drumm

Clearance envelop for the diffuser assembly approx. 150 mm 95 mm Tracker solenoid The space constraint & positioning requirement for the diffuser Patch panel Iron shield Clearance gap = 250mm Diffuser envelop when fully withdrawn 163 mm from flange face

Insertion of diffuser assembly caused the main arm to be rotated, thereby extending the arm mechanism See animation in the next 9 pages on how this works

Knife-edge flange fixed to the Tracker Solenoid cover flange

The Knife edge flange mounted on the top of the patch panel cover plate The original arrangement

3D exploded view

Questions raised during the parallel session were:- Should the top hat for the patch panel require a window?

Questions raised during the parallel session were:- Should the top hat for the patch panel require a window? The changing operation of the Lead diffuser needs to be completed in the shortest possible time – within 15 to 20 minutes

Well if they can change 4 wheels in 8 seconds, I don’t see why we can not change 1 diffuser in 8 MINUTES! We will employ quick release clamping mechanism if its needs be!

Questions raised during the parallel session were:- Should the top hat for the patch panel require a window? The changing operation of the Lead diffuser needs to be completed in the shortest possible time – within 15 to 20 minutes Should the lead plate be segmented?

The Iron Shield support system

The existing design has the iron shield sitting on a frame structure before it is bolted to the Tracker solenoid cover plate via a set of spacers

The revised design allows the shield to be suspended to the cryostat vessel via a set of “links and brackets”

A support lug is welded onto the flange cover plate for connection to the 2 nd link-bar Main hanging bracket is welded on a patch plate (saddle) of 15mm thick by 40 degree wide which is in turn welded on the top of the tracker solenoid vessel These 2 lugs are welded directly to the iron shield The 1 st and 2 nd link bars (red & blue in diagram) are the main supporting structure for the iron shield. The link bars are free to rotate at both ends. This allows finer adjustment to be made to achieve the positional tolerance needed.

Lifting of Iron Shield by mobile lifting unit Or Overhead Crane A fork lift truck, e.g.

Once suspended, a further set of link blocks will be machined insitu. The shield will be connected and dowelled into the required positional precision level. Link Blocks (3 off) for positional fixing & registration Link Bars (2-off)

The Iron Shield support is clear of the space envelop required by the Patch Panel

An exploded view

Vessel support position on both sides FEA calculation carried out to ensure integrity of tracker vessel not affected

Maximum deflection at the support bracket is 0.43mm in Z direction

Max. realistic stress on vessel is about 160 MPa at the junction of the bracket and the vessel

Issues raised in the parallel session: Proposed Iron Shield attachment system were generally acceptable; Needs to see if the link blocks could be aligned with the Cold Mass support positions of the Tracker magnets We need to check with IC to make sure that this does not clash with the Patch Panel space envelop

The PID support re-design

Iron Shield suspended off the tracker solenoid cryostat The revised PID support structure TOF 2 Cherenkov 2 EMCalorimeter PID support can slide in and out of normal anchor position in both X & Z directions X Y Z

Elevation view of the support structure End view of the support structure The PID support Structure

Support details at the Cherenkov 2 Support is via two 125 x 125 x 10 C-Channels bolted on existing Cherenkov outer frame Shim pack to adjust the final height

Support arrangement for the TOF2 Seating plate is via a 10mm thick plate welded to the end of the C-channel TOF support legs: 50 x 50 x 4mm thick C- channel

CKOV2 drawing received from Ghislain in Feb,2005 TOF2 drawing received from Maurizio in Feb, 2005

Issues raised during the parallel session One member pair of the support need repositioning to allow clear access for the removal of the Cherenkov tubes, otherwise the proposed design was generally accepted;

Iron Shield suspended off the tracker solenoid cryostat The revised PID support structure TOF 2 Cherenkov 2 EMCalorimeter PID support can slide in and out of normal anchor position in both X & Z directions X Y Z

Issues raised during the parallel session One member pair of the support need repositioning to allow clear access for the removal of the Cherenkov tubes, otherwise the proposed design was generally accepted; Needs to add ancillary support structures, such as cable support etc This will be incorporated into the design as soon as we have received the change requests from the PID project leaders The support will be modified to incorporate the rail system that is being looked at by RAL engineers

Infrastructures

Support structure – Rail-mounting concept

Requirements/specification: - to move (all) MICE modules out the beam (to the side direction) for various MICE stages Accuracy/tolerances: - along the beam +/- 1 mm - across the beam +/- 1 mm Adjustment: - adjustment possibility is required. Locking mechanism: - required. Loads: - max load is 6.65 tonnes. Force transfer function: - gravity force to the floor; - module-to-module axial force to the floor ? MICE support structure - Specification

MICE support structure – Next steps Revise support structure requirements/specs for full MICE - include and analyze requirements of access to every module ( collect information from all technical supervisors) Suggest support structure for Stage 2 (is it different from the one for complete MICE ?) Discuss revised version of support structure at RAL meeting

Issues raised at the Parallel session Do we need a second Iron Shield during the Stage II testing?

Support structure – Layout and sequences Add spacer

The Design & Safety Review

The task We have agreed a working method at the Berkeley meeting in February. This was endorsed both by the Wok group and the Collaboration Board; In Phase 1 we have a total of 16 items that require such reviews….. Progress to date: Well….slow….could have done better So far we have 5 Design Audits collected, two of which may require substantial re-work to bring it inline with the rest We have also received 3 Safety audit returns and there are not much in them. Most boxes are filled with a “to be carried out later” message

Beamline & Targets; Fibre Tracker; Tracker solenoid; Magnetic Shield; Cherenkov 1; Cherenkov 2; TOF 1 & 2; EMCalorimeter; Diffuser; 4 groups of Infrastructure items, one of which is the Hydrogen system; Hydrogen system R&D; Absorber R&D RF R&D This could be accessed from the MICE web page via the “Speakers Bureau”

The audit sheets that have been returned to me so far

…but it makes no reference to the Target … This needs to be modified when the design is completed.

Some minor details are still being worked on. References to the MICE Technical Notes will be moved to the TRD for consistency reason

Depending on whether we adopt a one piece solid sheet, or a 3-piece sheeting arrangement for the shield, it may need revising. In any case the support design has all changed since. It will require a fair amount of revising

So how does the scheme work?

The audit format is not without its drawbacks 1.It forces people to re-format their write-up in line with the format set out in the TRD document – this takes longer time to do compared with writing up a short note adequate for a design justification; The existing format is the best way to ensure consistency and quality control. The alternative would create paperwork that is difficult to manage and almost impossible to assemble

The audit format is not without its drawbacks 1.It forces people to re-format their write-up in line with the format set out in the TRD document – this takes longer time to do compared with writing up a short note adequate for a design justification; 2.It requires constant update of the TRD section(s) to reflect any modification or additions made subsequently; This requires a lot of Paul Drumm’s time. However this is now largely done. It makes the job of any future changes a lot easier to handle

The audit format is not without its drawbacks 1.It forces people to re-format their write-up in line with the format set out in the TRD document – this takes longer time to do compared with writing up a short note adequate for a design justification; 2.It requires constant update of the TRD section(s) to reflect any modification or additions made subsequently; 3.It requires book marking the TRD section and hyperlinking the reference marks to locate the right section; Hopefully the majority of this is a one-off event. We are getting better, and quicker, in doing this. However we would be happy to receive suggestion / advice on how to improve this.

The audit format is not without its drawbacks 1.It forces people to re-format their write-up in line with the format set out in the TRD document – this takes longer time to do compared with writing up a short note adequate for a design justification; 2.It requires constant update of the TRD section(s) to reflect any modification or additions made subsequently; 3.It requires book marking the TRD section and hyperlinking the reference marks to locate the right section; 4.Because the hyperlinks refer to only one section at a time, it doesn’t provide a full view of the complete write-up and therefore makes the review somewhat difficult and clumsy. We acknowledge this drawback and would advice that a hard copy of the TRD document be used during the review.

Where do we go from here? Phase 1 delivery is due at the beginning of April 2007 – some 20 months away I am concerned that we have not done as much as we would have liked I blame this on the following: The approach is somewhat new and needs time to get used to; Lack of enthusiasm from our component group leaders who, including myself, have the habit of leaving the design write up to the end. 20 months seem a long time to go and this may give people the impression that this is not a priority item;

Where do we go from here? Phase 1 delivery is due at the beginning of April 2007 – some 20 months away I am concerned that we have not done as much as we would have liked I blame this on the following: The approach is somewhat new and needs time to get used to; Lack of enthusiasm from our component group leaders who, including myself, have the habit of leaving the design write up to the end. 20 months seem a long time to go and this may give people the impression that this is not a priority item; For this reason, we must: Work out a realistic schedule with milestone dates that meets MICE delivery requirement

* Outline designs Preliminary Assessments Proposal for final choice Detailed design Manufacture and installation Permission to operate RAL Review Failure Modes Stress Calculations Interlocks & Operational Procedures Contingency Plans Pressure Vessel & ATEX regulations…. Hazard and Operability Assessment Working Group SequenceDocuments Required MICE Hydrogen Safety Review Procedure OK for detailed design OK to Manufacture Preliminary Hazard and Operability Assessments Reviews MICE Review + + Operation Readiness Review -- ISIS Safety Officer MICE is somewhere here! Task List Target Beamline ToF Stations Cherenkov Stations Calorimeters Spectrometers  Solenoid + Trackers Hall Layout R&D: Hydrogen & Absorber DL

Task time-line: 2005: Introduce decay solenoid in hall - testing Modifications to solenoid stand Installation of a hydrogen test area in hall 5.2 & tests Late 2005: S7 swap test target – few pulses at start-up : Installation of cryo-system for decay solenoid Shutdown 2006 install shielding install stands etc in synchrotron Late 2006: Rail system, beam line stands, b-l elements 2007: Spring 2007: install detectors first beam Late 2007: install spectrometer Prior design hazard & safety review Operational readiness review Full layout & infrastructure incl. PID

Time scales Permissible to submit prior reviews at any time -Better to coordinate (groups of related things) - Depending on scale of risk -- review can be internal - ISIS engineer / safety group / RPA -- e.g. Synchrotron target -- MICE should review fit for purpose -- ISIS will review acceptability -- or review will be external - Hydrogen system – ISIS external – industrial – SNS…. - Three months notice - Bookmark October 05 for Hydrogen system

● Prior review – Either before commencing build or – During/after build with increased risk ! ● Judgement call ● Readiness review – Will permit operation

Where do we go from here? Phase 1 delivery is due at the beginning of April 2007 – some 20 months away I am concerned that we have not done as much as we would have liked I blame this on the following: The approach is somewhat new and needs time to get used to; Lack of enthusiasm from our component group leaders who, including myself, have the habit of leaving the design write up to the end. 20 months seem a long time to go and this may give people the impression that this is not a priority item; For this reason, we must: Work out a realistic schedule with milestone dates that meets MICE delivery requirement To have closer contact (face to face) with the component group leaders and lead them through the mechanics of doing the audit If that fails…..Scream – use the whip, if it needs to!

That is not what I meant by WHIPPING!