P. Shanahan May 29, 2003 Page 1 MINOS WBS 2.3: Electronics, DAQ and Database Status Accomplishments since Dec. 2002 review Near Detector Electronics production.

Slides:



Advertisements
Similar presentations
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
Advertisements

CMS Week March presented by John Coughlan RAL FED Hardware Status Pre-Series Manufacture Final Production Plans.
US CMS DOE/NSF Review: May 8-10, US CMS Cost & Schedule Mark Reichanadter US CMS Project Engineer DOE/NSF Review 8 May 2001.
L. Greiner 1HFT PXL LBNL F2F – March 14, 2012 STAR HFT The STAR-PXL sensor and electronics Progress report for F2F.
The LAr ROD Project and Online Activities Arno Straessner and Alain, Daniel, Annie, Manuel, Imma, Eric, Jean-Pierre,... Journée de réflexion du DPNC Centre.
MINER A NuMI MINER A DAQ Review 12 September 2005 D. Casper UC Irvine WBS7: Electronics and Data Acquisition  Overview (this talk): D. Casper  Front-end.
MINER A NuMI MINER A DAQ Review 12 September 2005 D. Casper UC Irvine WBS 7.2 & 7.3: Data Acquisition D. Casper (UC Irvine)
Detector Systems Update MICO March 3, MICE Detector Systems  CKOV u CKOV humidity (HIH4000) and temperature (LM35) sensors in hand for installation.
Geoff Pile LCLS Und. System Fabrication FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Fabrication Schedule FAC.
WBS 1.7: AFE II Project Cost and Schedule Alan Bross DZero Run IIb AFE II Director’s Review April 13, 2005.
July 19, 2003 HEP03, Aachen P. Shanahan MINOS Collaboration 1 STATUS of the MINOS Experiment Argonne Athens Brookhaven Caltech Cambridge Campinas Dubna.
Project Management Methodology Project monitoring and control.
W. Freeman, D0 PMG 25-Feb-03 1 Run IIb Schedule Status u Schedule Status u Update on near-term equipment expenditures u Budgeting Update u Summary.
March 20, 2001M. Garcia-Sciveres - US ATLAS DOE/NSF Review1 M. Garcia-Sciveres LBNL & Module Assembly & Module Assembly WBS Hybrids Hybrids WBS.
Common PDR Problems ACES Presentation T. Gregory Guzik March 6, 2003.
August 2 and 3, 2010 Project Cost, Schedule, Risk and Contingency Jay Elias.
NuMI NuMI Overview NBI 2002 S. Childress (FNAL) 14 March ‘02 NuMI / MINOS Overview.
Saverio Minutoli INFN Genova 1 1 T1 Electronic status Electronics Cards involved: Anode Front End Card Cathode Front End Card Read-Out Control card VFAT.
Status of NA62 straw electronics and services Peter LICHARD, Johan Morant, Vito PALLADINO.
ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused.
Slide 1 6-Nov-98PHOBOS Review: Cost & Schedule Cost & Schedule S. Steadman, MIT PHOBOS Cost & Schedule Review Technical Advisory Committee BNL November.
October 4-5, Status of ARRA funded AIPs Electron Lens Scope, Cost, and Schedule Wolfram Fischer October 4, 2010 Electron Lens.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
P. Shanahan June 13, Near Detector Electronics Status Status Production Issues Peter Shanahan FNAL MINOS Collaboration Meeting June 13, 2003.
Hall D Online Meeting 28 March 2008 Fast Electronics R. Chris Cuevas Group Leader Jefferson Lab Experimental Nuclear Physics Division System Engineering.
1/24/01TDC Review1 Report to the TDC Review Committee Presented by Myron Campbell.
M&O status and program for ATLAS LAr calorimeter R Stroynowski (on vacations)
GLAST LAT Project – Cost and Schedule ReviewJanuary 27, 2004 AntiCoincidence Detector 1 GLAST Large Area Telescope: Cost/Schedule Review January 27, 2005.
Project Management Methodology
NUMI Off Axis NUMI Off Axis Workshop Workshop Argonne Meeting Electronics for RPCs Gary Drake, Charlie Nelson Apr. 25, 2003 p. 1.
CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)
John Coughlan Tracker Week October FED Status Production Status Acceptance Testing.
HBD electronics status All the ADC and XMIT boards are installed. –Top 3 crates are for the ADC, XMIT boards –Bottom crate is for test pulse boards/future.
1 US Cost & Schedule Summary W. R. Edwards US Project Manager CD-2/3a Review January 8, 2008 BNL.
1 ME1/1 ODMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project.
P. Shanahan Nov 15, 2003 Page 1 MINOS WBS 2.3: Electronics, DAQ and Database Status Accomplishments since May review Near Detector Electronics production.
18 March 2002 All Experimenters’ Meeting Alan L. Stone Louisiana Tech University 1 DØ Status: 03/11 – 03/18 Week integrated luminosity –1.1 pb -1 delivered.
D0 PMG 6/15/00 PMG Agenda June 15, 2000  Overview (Tuts) u Detector status u Reportable milestones u Financial status u Summary  Response to DOE review.
Peter Shanahan – Fermilab - Near Detector Electronics Status MINOS Collaboration Meeting University of Sussex Sep Near Detector Electronics.
Tevatron BPM Upgrade Stephen Wolbers CD Accelerator Coordination Meeting August 3, 2004.
MICE CMPB Alain Blondel 1 Highlights on MICE.
Tevatron BPM Upgrade Stephen Wolbers CD Accelerator Coordination Meeting September 21, 2004.
Trigger Commissioning Workshop, Fermilab Monica Tecchio Aug. 17, 2000 Level 2 Calorimeter and Level 2 Isolation Trigger Status Report Monica Tecchio University.
Brenna Flaugher Sept. 24 th Lehman Review1 Run IIB Silicon Upgrade: Cost and Schedule Lehman Review Sept. 24, 2002 Brenna Flaugher Run IIB Silicon Project.
DOE/NSF Review of U.S. ATLAS May 21-23, 2003 CSC Mechanics and Electronics Paul O’Connor Tom Muller BNL May 22, 2003.
1 draft NO A WBS J. Cooper NO A Working Group Meeting June 29,2005 Work is the effort of Ron, Dave, Bill, Suzanne, Harry, not just me.
US CMS DOE/NSF Review: April 11-13, Trig. - Estimate to Complete.
24/03/2010ALICE TOF General Meeting March TOF hardware and data taking 2010 Andrea Alici Museo Storico della Fisica e Centro Studi e Ricerche “Enrico.
DAQ Status & Plans GlueX Collaboration Meeting – Feb 21-23, 2013 Jefferson Lab Bryan Moffit/David Abbott.
Plans to Test HBD Prototype in Run 6 Craig Woody BNL DC Meeting March 8, 2006.
D0 PMG February 15, 2001 PMG Agenda February 15, 2001  Overview (Weerts) u Detector status u Reportable milestones u Summary  Operations Organization.
March 25, FVTX Monthly/Quarterly Report June, 2009 Technical Status, Cost & Schedule Melynda Brooks, LANL.
9/12/2003Ivan Hruska1 First box prototype –Box design in July ‘03 –Box produced during August ’03 Tested last week in few fingers Small changes necessary.
Executive Committee, Toronto August 3, 2005 TRT Barrel WBS 1.2/3.2 Harold Ogren Indiana University.
News and Misc Didier Contardo, Jeff Spalding UPO 3/2/12 1 UPO 2/2/12 o The MM, cost estimates and reporting o Milestones and scheduling o Chamonix Meeting.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
NUMI NUMI/MINOS Status J. Musser for the MINOS Collatoration 2002 FNAL Users Meeting.
NUMI MINOS MINOS Far Detector Installation & Commissioning Jeff Nelson MNHEP DoE Visit September, 2002.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
MINER A at the Triple Point: Three Phases at once Deborah Harris AEM August 31, 2009.
Evelyn Thomson Ohio State University Page 1 XFT Status CDF Trigger Workshop, 17 August 2000 l XFT Hardware status l XFT Integration tests at B0, including:
Sumary of the LKr WG R. Fantechi 31/8/2012. SLM readout restart First goal – Test the same configuration as in 2010 (rack TS) – All old power supplies.
CMS ROC Report Patricia McBride May 26, 2005.
Page Headline Project Management Cost & Schedule Review Rob Michnoff.
CLAS12 Forward Tracking: Status and Challenges
J. Musser for the MINOS Collatoration 2002 FNAL Users Meeting
T1 Electronic status Conclusions Electronics Cards:
Mini-drawers, FE-ASIC , Integrator
Hardware needs (ARCS) Current ARCS capabilities at both sites should be able to keep up with production assuming software changes Automatic I-V curves,
Presentation transcript:

P. Shanahan May 29, 2003 Page 1 MINOS WBS 2.3: Electronics, DAQ and Database Status Accomplishments since Dec review Near Detector Electronics production False positive cost variance MENU production Schedule Possible contingency usage Peter Shanahan Department of Energy Review of the NuMI Project MINOS Parallel Session May 28-30, 2003

P. Shanahan May 29, 2003 Page 2 Overview of 2.3 Status Schedule Status (BCWP/Total Budget): 89% complete Near Electronics: WBS (Argonne, Fermilab) In production – focus of this talk The rest of WBS is summarized below

P. Shanahan May 29, 2003 Page 3 WBS 2.3 Accomplishments Since December, 2002 Review L3 Milestones: WBS MS.6 Begin Menu Card Checkout *completed on time, 4/15/03 WBS MS.5 ND Order Production Boards *completed on time, 4/18/03 Production Started on All Near Detector Electronics Components Fabrication and Assembly for all Printed Circuit Boards Orders issued for All Crates, Power Supplies Schedule Logic Improvements (Mostly 2.3.1) More natural logic flow  more realistic progress tracking (Except 2.3.6: VME Timing Module Redesign – 15 units) …cont…

P. Shanahan May 29, 2003 Page 4 WBS 2.3 FD FEE, DAQ, DATABASE WBS Far Detector Front End Electronics (Harvard, Oxford, FNAL) Complete WBS DAQ & Triggering (RAL, Argonne) Far Detector: *Final readout crate commissioned in February 2003 Near Detector *Planning with WBS 2.5 Installation group for ND installation *DAQ Code: used at CALDET, daily use at ANL test stand WBS Database (UMinn, Oxford, Fermilab) Gathering module construction data Testing data distribution system Work on implementing Oracle database

P. Shanahan May 29, 2003 Page 5 WBS 2.3 Aux Systems, DCS, HV WBS Auxiliary Systems (Oxford, FNAL, IIT) Far clock system installation will be completed next month Near clock modules: see below WBS Slow Control & Monitoring (UMD, UWisc, FNAL) Detector Control System: Automatic HV control Rack Protection (RPS) *Near: equipment being staged at FNAL, procurement will finish this summer, with assembly to follow Software: HV, Environmental, Magnet, and RPS data now logged to database WBS High Voltage (Texas A&M) Far: HV dropouts traced to bad power conditioner – fixed Near: Power conditioner purchased

P. Shanahan May 29, 2003 Page 6 Change Requests in WBS 2.3 CR $580K overrun (burdened) on electronics Near Detector EDIA : $194K Near Detector Parts Order & Assembly: $129K *Fixed Errors in early CR Far Detector EDIA: $82K Far Detector Parts Order & Assembly: $146K Far Detector Production Checkout: $26K CR 223 – Schedule Logic Change Gave every task predecessor and successor tasks Thinned out unnecessary predecessor/successor relationships Results: more ‘natural’ production schedule, more meaningful floats $25K increase from escalation

P. Shanahan May 29, 2003 Page 7 New Milestones Level 2: WBS MS.2 *Change “Electronics ready for installation – Near” to “Electronics ready to begin installation – Near” *Emphasizes pipeline of production and installation WBS MS.4 *New: “Electronics production complete – Near” *Emphasized completion of all electronics Level 3: MS.6 Begin MENU Card Checkout MS.7 Complete Shipping for CalDet MS.8 Begin Near FE Electronics Installation

P. Shanahan May 29, 2003 Page 8 Upcoming Schedule Milestones WBS TaskScheduleFloat MS.2Electronics Ready to Begin Installation - Near10/15/ d MS.4Electronics Production Complete - Near03/01/ d MS.5ND Order Production Boards04/18/ d MS.6Begin MENU Card Checkout04/15/ d MS.7Complete Shipping for CalDet07/10/200329d MS.8Begin Near FE Electronics Installation04/05/ d Total WBS 2.3 Float is 54 days – partially over-constrained by constant scheduled effort in aiding with electronics installation

P. Shanahan May 29, 2003 Page 9 Near Detector Electronics MASTER Module MINDER Crate Trigger/Keeper MINDER modules MASTER Crate Component Count (not counting ~10% spares): 9328 MENUS 583 MINDERS 81 MASTERS

P. Shanahan May 29, 2003 Page 10 Near Detector Electronics Status Schedule Status (BCWP/Total Budget): 85% March 03 (88% April 03) All system components are in production Problems with MENU startup Minder schedule is tight for CALDET run at CERN Artificial Large Favorable Cost Variances: +$1M in March mostly due to “statusing” order tasks Some production orders are under budget Some overruns on labor

P. Shanahan May 29, 2003 Page 11 Near Detector Electronics Status ItemNumber for Detector Operation Number for CALDET Operation Assembled Number in Hand Comments MENUs % passing checkout MINDERs KEEPERs4585Balance expected week 5/27 MASTERs more due 5/21 MINDER CRATEs45810 MINDER PS45810 MASTER CRATEs9211 MASTER PS9211 VME Timing Module1024Caldet won’t use prod. version Minder Timing Module458 ~few need repair post-checkout Master Clock Controler113 Clock Fanout617 Spares (~10%) not included in this table. Various Auxillary cards not included (which have CALDET quantities met).

P. Shanahan May 29, 2003 Page 12 MENU Front-end daughter card Supports and reads out QIE Stores digital data in pipeline 9328 in system 1440 plus spares required for CALDET

P. Shanahan May 29, 2003 Page 13 MENU Production Problems Sporadic production startup: Fabrication Solder on gold contacts – not noticed until fabrication began. Vendor has accepted responsibility: inspection+new boards Vendor inspection insufficient (no microscope on QC line!) *Additional Fermilab technician time Assembly Incorrect 1 st articles Overheated “burn-in” by vendor on 200 boards Poorly tuned initial automated optical inspection by vendor Wrong solder flux on several hundred boards All problems addressed by vendor *but with substantial FNAL tech time

P. Shanahan May 29, 2003 Page 14 MENU Good News 1600 boards in hand Checkout rate of boards with no acute problems is >90% Assumed 67% in checkout schedule CALDET schedule virtually assured IIT Undergrads for Checkout Resident at FNAL for 5 weeks Will later take test-stand to IIT Long-term production Rate of 330/wk will complete production by 12/31/03

P. Shanahan May 29, 2003 Page 15 MINDER STATUS MENU Mother Board 16 MENUs/MINDER 583 MINDERS in the system 100 needed for CALDET Assembly began in early May Testing for CALDET >5 modules/day required Run 2 teststand shifts at Argonne Collaborator help for simpler checkout tasks may be used

P. Shanahan May 29, 2003 Page 16 Near Detector Electronics Schedule (from Dec. ‘02 Review) Beneficial Occupancy of Near Detector hall – Dec. 22, 2003 Near Detector CALDET Run – 1500 Channels needed starting June, 2003 Actual assembly start (fabrication for power supplies) Actual CALDET Run: Sept. 4 – Oct. 4 Ship in late June Shifting complete dates by these amounts will not affect ND schedule

P. Shanahan May 29, 2003 Page 17 CALDET Last year’s run 150 channels on 1 side had Near Electronics Generally useful system test PID issues and high rate (for Far Detector Electronics) limited ability to compare ND/FD Time of Flight Cerenkov ,e,p Steel/Scintillator

P. Shanahan May 29, 2003 Page CALDET Run Sept. 4 – Oct. 4, channels on Near Detector Electronics Full instrumentation of 1 side (actual ND is one sided) Near only, and Near/Far running Production calibration of Near response ND Electronics is principle focus of run Ship electronics in late June L3 milestone 7/7/03 Move to beam enclosure 8/26/03

P. Shanahan May 29, 2003 Page 19 Large Artificial Cost Variance in WBS $994 K favorable cost variance Two main artificial components: “Order” tasks BCWP based on technical progress, although ACWP doesn’t accrue until item is received – temporary effect *March 03 total encumbrances=$900k Delays between Argonne activity and Fermilab accounting BCWP ACWP CV k$ Production turn-on here E.g.: “order” task including specification, bid solicitation, and purchase time BCWS Favorable Cost Variance if BWCP tracks technical progress Unfavorable Schedule Variance if BWCP track receipts M&S start to be received

P. Shanahan May 29, 2003 Page 20 Possible Real Favorable Cost Variances Sampling of recent M&S purchase orders: Power supplies, crates, printed circuit boards Possible $100K+ favorable variance *Based on Purchase Order records (excludes PMT cable overrun of ~$20K) Preliminary, unofficial accounting k$

P. Shanahan May 29, 2003 Page 21 Possible Contingency Use (ignoring possible favorable variances) Travel for FNAL engineers: ~$20k Tech and Engineer Labor Clock system – possible c. $50k overrun MENU Production *Initial fabrication and assembly quality problems being addressed by high- level FNAL techs – possible c. $50k overrun. *Will be partially mitigated by general MENU checkout by off-project student labor PMT – MINDER cables Issue discovered just before last review: complicated patterns of 64 in to 64 out Fabrication: will be farmed out for $35k, about $20k over budget Total currently foreseen overruns for 2.3: $140K

P. Shanahan May 29, 2003 Page 22 Summary WBS 2.3 has had much progress since Dec. 02 WBS finished Steady progress towards completion on DAQ, Database, DCS, HV Near Detector electronics in production Artificial large favorable cost variance in Estimates of real negative and positive variances by sub-tasks in 2.3.1/2.3.6 are approximately both $100-$200k scale Actual production appears in line with CALDET run and Near Detector installation CALDET schedule is tight – may require physicist shifts on checkout WBS 2.3 is 89% complete