Process Water VE Updates (Main Linac Only) Emil Huedem FNAL ILC Meeting - CHICAGO Nov 17 2008 E. Huedem 2008.

Slides:



Advertisements
Similar presentations
Nov. 17, 2008 ILC08 Global Design Effort 1 Americas KlyCluster Cost Analysis Overview Tom Lackowski RF & Sum reported by Peter H. Garbincius.
Advertisements

11/27/2007ILC Power and Cooling VM Workshop Mike Neubauer 1 RF Power and Cooling Requirements Overview from “Main Linac Power and Cooling Information”
Nov. 07 DR-KOM-CFS 1 Damping Rings KOM Conventional Facility & Siting Overview Tom Lackowski Acknowledgment: Atsushi Enomoto, Jean-Luc Baldy, John Osborne,
Global Design Effort - CFS TILC09 and GDE AAP Review Meeting - Tsukuba, Japan 1 GDE ACCELERATOR ADVISORY PANEL REVIEW CONVENTIONAL FACILITIES.
Areal RF Station A. Vardanyan RF System The AREAL RF system will consist of 3 RF stations: Each RF station has a 1 klystron, and HV modulator,
KAGEYAMA, T. Open Meeting for Proto-Collaboration March 19, 2008.
November 17, 2008 ILC08 HVAC and VE Update November 17, 2008 ILC CFS Workshop 2008 Chicago Lee Hammond, Fermilab Global Design Effort.
CONVENTIONAL ELECTRICAL TDR DESIGN Randy Wielgos March 22, 2012 ILC CFS Baseline Technical Review.
1 ILC Mechanical & Electrical Review Conventional MECHANICAL System Design Summary Emil Huedem, FNAL Lee Hammond, FNAL Parsons Mechanical Team (Tim Sheehan,
Chilled Water Systems Total Cost of Ownership
Global Design Effort - CFS Baseline Assessment Workshop 2 - SLAC Reduced Bunch Number 1 BASELINE ASSESSMENT WORKSHOP 2 CONVENTIONAL FACILITIES.
1 HVAC OVERVIEW and VALUE ENGINEERING ITEMS August 13, 2008 CLIC Working Group CES Lee Hammond, Fermilab.
Value Engineering Session Air Treatment / HVAC November 27, 2007 Lee Hammond, FNAL CFS.
Central Region Discussion Power and Cooling GDE Beijing-CFS.
Powering the main linac implications Daniel Siemaszko, Serge Pittet OUTLINE : Cost impact of power converters, power consumption and powering.
Global Design Effort 1 Conventional Facilities and Siting Overview A. Enomoto, J-L. Baldy, V. Kuchler GDE.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Accelerator Laboratory 1 CFS Review of Asian Region (S. Fukuda) June 1/2010 DRFS HLRF System KEK S. Fukuda Introduction: Basic Concept of DRFS Progress.
E Huedem, Nov ILC VALUE ENGINEERING SESSION of POWER & COOLING (Focus on Main Shaft 7) November 27, 2007 INFORMATION PHASE Conventional.
1 Process Water and Air Treatment 01 June 2007 Emil Huedem, Maurice Ball, Lee Hammond Fermilab.
ILC Power and Cooling VM Workshop Mike Neubauer 1 Collector Cooling Design example Failures in the field Water quality.
ILC Energy Efficiency Marc Ross and Ewan Paterson, SLAC CFS-ADI Joint Meeting ICEPP University of Tokyo 9 April 2014 Three examples: 1) higher quality.
NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS Page 1 1 Infrastructure Review - W.B.S Water Systems Water Systems –Upstream.
LCC Linear Collider Collaboratio ILC - CFS 12 November 2013 LCWS13 Tokyo University 1 Site-specific CF design from TDR LCWS13, 12 November 2013 Atsushi.
ILC CFS AD&I Daresbury Lab Summary J.Osborne / V.Kuchler / A.Enomoto.
BDS Magnet-Power System-Facility Optimization1 ILC BDS Kickoff Meeting Basis for Magnet, Power System and Cooling Facility Optimization Discussion Paul.
Clustered Surface RF Production Scheme Chris Adolphsen Chris Nantista SLAC.
February 17-18, 2010 R&D ERL Alex Zaltsman R&D ERL High Power RF Systems Alex Zaltsman February 17-18, 2010 High Power RF Systems.
LCWS08 (Nov.18, 2008) 18/11/ Proposal of Distributed RF-source Scheme (DRFS) Shigeki Fukuda (KEK) Introduction Consideration of the cost Possible.
SLAC_OCT07 BDS-KOM-CFS 1 Beam Delivery System & Interaction Region KOM Conventional Facility & Siting Overview Fred Asiri/SLAC Acknowledgment: Atsushi.
Global Design Effort1 September 20-22, 2006 MAC Review Power and Water breakout (mixed results) Marc Ross GDE.
27 Nov 07 VM Workshop Global Design Effort 1 ILC – Superconducting Linear Collider Marc Ross, Project Manager GDE Fermilab.
6-10 Nov. 06 ILCWS Valencia Global Design Effort 1 RDR Management Board Overview K. Yokoya KEK.
BAW1 RDR Confg For Mntn Rgn (S. Fukuda) 1 RDR configuration for Mountain Region S. Fukuda/KEK.
ILC BDS Kickoff Meeting Magnet Power Supplies RDR Concepts and Completeness Paul Bellomo SLAC Power Conversion Department October, 2007.
Aug 23, 2006 Half Current Option: Impact on Linac Cost Chris Adolphsen With input from Mike Neubauer, Chris Nantista and Tom Peterson.
Global Design Effort - CFS TILC08 Working Group 1 - March 5, CFS Cost Reductions Conventional Facilities and Siting Group A. Enomoto, V.
Global Design Effort - CFS Damping Ring Baseline Technical Review 1 DAMPING RING BASELINE TECHNICAL REVIEW CONVENTIONAL FACILITIES AND SITING.
COOLING & VENTILATION FOR THE DRIVE BEAM TUNNEL M Nonis – EN/CV – 16/9/2009 CLIC TWO BEAM MODULES REVIEW
L-band test stations in End Station B Richard Swent.
Karl Williams Mechanical Engineer AD/MS Fluids Group Absorber RAW Cooling Systems.
KCS and RDR 10 Hz Operation Chris Adolphsen BAW2, SLAC 1/20/2011.
Global Design Effort - CFS Oct IWLC ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto.
M. Ross, N. Walker, A. Yamamoto th ATF2 Project Meeting Accelerator Design and Integration – New Baseline Proposal for ILC – ‘Strawman Baseline.
Jan Low Energy 10 Hz Operation in DRFS (Fukuda) (Fukuda) 1 Low Energy 10Hz Operation in DRFS S. Fukuda KEK.
Aug 23, 2006 Low Power HLRF System and Impact on Distributed RF System Shigeki Fukuda and Task Force Team of DRFS in KEK KEK.
Global Design Effort - CFS ILC CFS and Global Systems Meeting 1 ILC CFS AND GLOBAL SYSTEMS MEETING CONVENTIONAL FACILITIES AND SITING GROUP CFS.
ME444 ENGINEERING PIPING SYSTEM DESIGN CHAPTER 10 : CONTROL VALVES IN CLOSED LOOP SYSTEMS.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Ullrich, DESY Dubna GDE XFEL The European X-Ray Laser Project X-Ray Free-Electron Laser 1 Water cooling XFEL Desingn of the XFEL water cooling.
704 MHz cavity design based on 704MHZ_v7.stp C. Pai
Pulsed Magnet Power Supply Feasibility Study
1 CFS Utilities – What’s included in RDR for IR July CFS Utilities – IRENG WG C WATER COOLING: none. Unknown loads on IR. Only have water plants.
E Huedem, June RDR PROCESS WATER & VALUE ENGINEERING ITEMS June 5, 2008 GDE Meeting-ILC CFS Workshop in Dubna, Russia Emil Huedem, Fermilab.
CFS EDR KICK OFF MEETING Air Treatment August 23, 2007 Lee Hammond, FNAL CFS.
E- source kick-off meeting e- Source RDR- Conventional Facility & Siting Overview Fred Asiri/SLAC.
Areal RF Station A. Vardanyan
ILC Power and Cooling VM Workshop
Review of the International Linear Collider (ILC) Electrical and Mechanical System Design to be held at CERN on 21 March, 2012 The purpose of the Review.
Conventional Facility & Siting (CF&S) Overview for the Positron Source
CFS EDR KICK OFF MEETING Process Water August 23, 2007
Americas KlyCluster Cost Analysis Overview
Water Cooling issue (Klystron Cooling)
Chris Adolphsen Sergei Nagaitsev
CONVENTIONAL FACILITIES presented by Peter H. Garbincius
COOLING & VENTILATION INFRASTRUCTURE
General presentation about recent status of DRFS
Extract from today’s talk given to DCB
ILC Cryogenics -- Technical Design Report Planning
ILC - Global Design Effort
Presentation transcript:

Process Water VE Updates (Main Linac Only) Emil Huedem FNAL ILC Meeting - CHICAGO Nov E. Huedem 2008

Brief History - Process Water cooling Dec 2006 RDR Cost finished Oct 2007 Update ML heat table – (evaluate DT) Nov 2007 Value Engineering. PM select VE items (Dec 07 stop work) Aug 2008 Cost Kly Cluster Sep & Oct 08 VE Costing exercise Re-visit VE, & Performed a comparative cost estimate to understand the delta and impacts on selected VE/ PM items, for the goal of First-Cost reduction only. Focus on costing rather than design (Specific VE selected is for Main Linac only RDR-twin-tunnel) E. Huedem 2008

Oct WATER AND AIR HEAT LOAD (all LCW) and ML MAIN LINAC - ELECTRON & POSITRON To Low Conductivity Water to Chilled Water keith Jobe load to air Nov To Air (chilled water) Components Quantity Per 36m Heat Load to Water (KW) Max Allowable Temperatu re ( c) Supply Temp (variation) ( C ) Supply Temp ( C ) Delta Temperat ure (C delta) Water Flow (l / min) Maximum Allowable Pressure (Bar) Typical (water) pressure drop Bar Acceptable Temp Variation delta C Heat Load to Water (KW) Power fraction to Tunnel Air (0-1) Power to Tunnel Air (KW) He at Lo ad to Air (K W) Max Space Temp ( C ) Non-RF Components LCW Skid Pump 1 per 4 rf -Motor/Feeder Loss0.250N/A None # I^2R Loss and Motor Loss (misc)10N/A None # Fancoils (5 ton Chilled Water) 1.5 Hp20N/A None0 # Rack Water Skid0.250N/A None # Lighting Heat Dissipation ~1.3W/sf 0N/A None # AC Pwr Transformer kV None # Emerg. AC Pwr Transformer kV 0N/A None01.00 # RF Components RF Charging Supply 34.5 Kv AC-8KV DC1/36 m F (a) Switching power supply 4kV 50kW1/36 m Modulator1/36 m n/a Pulse Transformer1/36 m n/a Klystron Socket Tank / Gun1/36 m n/a0 0.2 Klystron Focusing Coil (Solenoid ) 1/36 m n/a Klystron Collector1/36 m (inlet temp 25 to 63) n/a Klystron Body & Windows1/36 m to 40C C 0 Relay Racks (Instrument Racks)1/36 m 0N/A None Attenuators2/36 m0 N/A None 0.0 Waveguide (in service tunnel)1/36 m Waveguide (in penetration)1/36 m0.676 Waveguide (in beam tunnel)1/36 m C0 5.9 Circulators With loads (isolator)26/36 m per load 3 per load C0 0.0 Loads24/36 m per load 8 per load C 0.0 Subtotal RF unit Only Total RF RF Component only Loads NOTE : Loads, Circulators and Klystron Body Supply Temperature is critical (should have very slow supply temp variation) **Oct Jensen,Oleg & Shigeki Main Linac HLRF Heat Load Table Reduced by 50% (Mar 2008) Data from a number of people

E. Huedem 2008 RDR Process Water System Basis: Shaft thin Sch 10 Stainless Std Sch (40) Carbon Steel * * * * = cost drivers Selected VE target cost drivers

E. Huedem 2008 VE ITEMS – Nov 2007 Additional PM items- Mar Eliminate chilled water system. Use process water as the primary rejection, Use process fancoils, warmer tunnel temperature 104 F (up to ~113F/ 45C) during normal operation, and portable cooling for workers Increase water system Delta T = 30 D F (16.7 D C) up to 72 F D T (40 D K) 2 Use localized cooling unit Remove LCW Skid Restore rack cooling only to less than ½ of the rack power load (50% reduction rack load) Consider using low mineral content water instead of LCW (pipe material) Allow different type of pipe materials (CPVC)

E. Huedem 2008 Process Water Only for VE Schemes cost evaluation RF WATER SYSTEM OVERALL WATER SYSTEM Scheme 5 Scheme 6 Shaft 7 VE (SS? Or CPVC? Or CS?) Std Sch (40) Carbon Steel Copper > 2”

MEANS BOOK SAMPLE PIPE COST 1” (25DN) to 4” (100DN) E. Huedem 2008 Smaller piping to fancoils, racks use copper, even RF water Per unit cost

VE Item. PIPE MATERIAL in tunnel ?? ResisitivityConductivity ppm TDS M-Ohmsmicrosiemens Ultra Pure Main Injector & TeV LCW Pure CPI notes/ Thales Keith Tap water , , Sea water , Stainless /Copper/ plastic Means Cost Book has cost for limited size steel, stainless, copper, iron, some plastic. Used Stainless 304 sch 10, CPVC sch 80, carbon steel ? E. Huedem 2008 Tesla VE

E. Huedem 2008

gpm= BtuH/ (500 x D T F) lpm = KW / D T K Was 20.6 gpm, higher flow reqmnt RF WATER SYSTEM

E. Huedem gpm higher flow reqmnt gpm= BtuH/ (500 x D T F) lpm = KW / D T K

E. Huedem 2008

20.6 gpm, higher flow reqmnt

E. Huedem 2008

Used this for costing evaluation

E. Huedem 2008 Aug Revisit Pre-RDR (Aug 2006) scheme of self contained cooling unit Discussion with Vendor,Mike Bordenet, VP of Zonatherm, (Liebert& Knurr Equipment) -suggest XDF version, no specific off-the-shelf that match the size, but can provide to whatever size you want -BUT this typically comes/purchased with racks -This simplify the CFS piping, but impact the rack arrangement, -similar to localized coolng unit, less efficient than centralized chilled water system ASSUMPTION WITH RACK COOLING Simplified Piping to Main Rack Cooling Unit Racks PLAN VIEW

E. Huedem 2008

Scheme to consider effect of reduction of heat load to air by 50%

E. Huedem C DT (45 0 F DT) RF Water model40 0 C DT (72 0 F DT) RF Water model Scheme 5Scheme 6Scheme 7Scheme 5Scheme 6Scheme 7 Actual RF Water delta T C ( F ) C ( F ) C ( F ) 40 0 C (72 0 F ) Overall Water delta T C ( F ) C ( F ) C ( F) C ( F ) C ( F ) C ( F ) DIFFERENCES BETWEEN SCHEMES process cooled fancoilsYesNO YesNO localized compressorized cooling unit NOYes NOYes service tunnel space temperature 45 C (113 F)29 C (85 F) 45 C (113 F)29 C (85 F) available from cooling unit in service tunnel KW

E. Huedem 2008 RF Water Delta T25C D T (45F D T)40C D T (72F D T) Kly Cluster- Aug 2008 Impact / Issues (by others) Scheme 5Scheme 6Scheme 7Scheme 5Scheme 6Scheme 7 Cost to be added (could be by others?) Major IMPACT/ Issues? SSCPVCCSSSCPVCCSSSCPVCCSSSCPVCCSSSCPVCCSSS SS=Sch Stainless in Tunnel only ; CPVC=Sch 80 CPVC plastic pipe; CS= Std Sch (40) Carbon Steel Overall Water Delta T oDCoDC oDFoDF "First-Cost" Savings in % - Process/Air Treatment WBS & %30%31%23%25%26%30%32%33%31%33%32%26%28%27%35%-47% RF Loads and Circulators reduced flow RF Modltrs and Plse Transfm-flow/temp Watercooled wvgde cooling design (by others) Kly Clstr's RF Pipe Cooling by others High Space Temperature ok? ~45 o C (113 o F) Equipment Insulations?? 50% reduction in air heat load possible? Finalize HLRF Heat Load table? Collector issue? Rack chiller impact ok? / Rework rack arrngmt?? Confirm reduced Heat load from racks? Cost for increased maintenance due high space Cost of portable cooling for maintenance Pump Recirc loop at Collector~ $2M?? Pump Recircloop (modul/P.Transfmr)~ $2M ?? Electrical Reduction~ ( MW) Operational cost reduction~ ( - ??) Electrical addition ~ + 3 MW~ + 1 MW ~ + 3 MW ~ + 1 MW ?? Operational cost addition + ?? Pipe Press & Temp limit issues "Clean Water" Compatibility Issue MATRIX SUMMARY (as of Nov :30pm) – Cost Savings vs Impact/Issues Savings % still need to be checked ! XX XXX XXXXX

Cost savings comparison note that the resultant overall cost savings were result from a number of VE items (not just one item), but following is an attempt to shows various delta between some VE items E. Huedem 2008

RF Water Delta T25C D T (45F D T)40C D T (72F D T) Kly Cluster- Aug 2008 Impact / Issues (by others) Scheme 5Scheme 6Scheme 7Scheme 5Scheme 6Scheme 7 Cost to be added (could be by others?) Major IMPACT/ Issues? SSCPVCCSSSCPVCCSSSCPVCCSSSCPVCCSSSCPVCCSSS SS=Sch Stainless in Tunnel only ; CPVC=Sch 80 CPVC plastic pipe; CS= Std Sch (40) Carbon Steel Overall Water Delta T oDCoDC oDFoDF "First-Cost" Savings in % - Process/Air Treatment WBS & %30%31%23%25%26%30%32%33%31%33%32%26%28%27%35%-47% RF Loads and Circulators reduced flow RF Modltrs and Plse Transfm-flow/temp Watercooled wvgde cooling design (by others) Kly Clstr's RF Pipe Cooling by others High Space Temperature ok? ~45 o C (113 o F) Equipment Insulations?? 50% reduction in air heat load possible? Finalize HLRF Heat Load table? Collector issue? Rack chiller impact ok? / Rework rack arrngmt?? Confirm reduced Heat load from racks? Cost for increased maintenance due high space Cost of portable cooling for maintenance Pump Recirc loop at Collector~ $2M?? Pump Recircloop (modul/P.Transfmr)~ $2M ?? Electrical Reduction~ ( MW) Operational cost reduction~ ( - ??) Electrical addition ~ + 3 MW~ + 1 MW ~ + 3 MW ~ + 1 MW ?? Operational cost addition + ?? Pipe Press & Temp limit issues "Clean Water" Compatibility Issue XX XXX XXXXX COST SAVINGS COMPARISON (basic schemes) 5% D

E. Huedem 2008 RF Water Delta T25C D T (45F D T)40C D T (72F D T) Kly Cluster- Aug 2008 Impact / Issues (by others) Scheme 5Scheme 6Scheme 7Scheme 5Scheme 6Scheme 7 Cost to be added (could be by others?) Major IMPACT/ Issues? SSCPVCCSSSCPVCCSSSCPVCCSSSCPVCCSSSCPVCCSSS SS=Sch Stainless in Tunnel only ; CPVC=Sch 80 CPVC plastic pipe; CS= Std Sch (40) Carbon Steel Overall Water Delta T oDCoDC oDFoDF "First-Cost" Savings in % - Process/Air Treatment WBS & %30%31%23%25%26%30%32%33%31%33%32%26%28%27%35%-47% RF Loads and Circulators reduced flow RF Modltrs and Plse Transfm-flow/temp Watercooled wvgde cooling design (by others) Kly Clstr's RF Pipe Cooling by others High Space Temperature ok? ~45 o C (113 o F) Equipment Insulations?? 50% reduction in air heat load possible? Finalize HLRF Heat Load table? Collector issue? Rack chiller impact ok? / Rework rack arrngmt?? Confirm reduced Heat load from racks? Cost for increased maintenance due high space Cost of portable cooling for maintenance Pump Recirc loop at Collector~ $2M?? Pump Recircloop (modul/P.Transfmr)~ $2M ?? Electrical Reduction~ ( MW) Operational cost reduction~ ( - ??) Electrical addition ~ + 3 MW~ + 1 MW ~ + 3 MW ~ + 1 MW ?? Operational cost addition + ?? Pipe Press & Temp limit issues "Clean Water" Compatibility Issue XX XXX XXXXX COST SAVINGS COMPARISON (reduction of heat load to air by 50%) 7 to 8% D

E. Huedem 2008 RF Water Delta T25C D T (45F D T)40C D T (72F D T) Kly Cluster- Aug 2008 Impact / Issues (by others) Scheme 5Scheme 6Scheme 7Scheme 5Scheme 6Scheme 7 Cost to be added (could be by others?) Major IMPACT/ Issues? SSCPVCCSSSCPVCCSSSCPVCCSSSCPVCCSSSCPVCCSSS SS=Sch Stainless in Tunnel only ; CPVC=Sch 80 CPVC plastic pipe; CS= Std Sch (40) Carbon Steel Overall Water Delta T oDCoDC oDFoDF "First-Cost" Savings in % - Process/Air Treatment WBS & %30%31%23%25%26%30%32%33%31%33%32%26%28%27%35%-47% RF Loads and Circulators reduced flow RF Modltrs and Plse Transfm-flow/temp Watercooled wvgde cooling design (by others) Kly Clstr's RF Pipe Cooling by others High Space Temperature ok? ~45 o C (113 o F) Equipment Insulations?? 50% reduction in air heat load possible? Finalize HLRF Heat Load table? Collector issue? Rack chiller impact ok? / Rework rack arrngmt?? Confirm reduced Heat load from racks? Cost for increased maintenance due high space Cost of portable cooling for maintenance Pump Recirc loop at Collector~ $2M?? Pump Recircloop (modul/P.Transfmr)~ $2M ?? Electrical Reduction~ ( MW) Operational cost reduction~ ( - ??) Electrical addition ~ + 3 MW~ + 1 MW ~ + 3 MW ~ + 1 MW ?? Operational cost addition + ?? Pipe Press & Temp limit issues "Clean Water" Compatibility Issue XX XXX XXXXX COST SAVINGS COMPARISON (by Pipe material) 2% D

Plastic Pipe ratings E. Huedem 2008 Schedule 80 CPVC: Water Pressure Rating (psi) Schedule 40 CPVC: Water Pressure Rating (psi) 130 F to 140 F return water ~140 psi system

LENGTHS OF PROCESS WATER PIPES IN SERVICE TUNNEL ONLY (MAIN LINAC ONLY) Length of Pipe in meter 42 o C D T (75 o F D T) Scheme 5 40 o C D T (72 o F D T) Scheme 6 40 o C D T (72 o F D T) Scheme 7 40 o C D T (72 o F D T) Scheme 4 25 o C D T (45 o F D T) Scheme 7 25 o C D T (45 o F D T) Scheme 6 26 o C D T (47 o F D T) Scheme 5 25 o C D T (45 o F D T) Scheme 4 RDRKly Cluster OVERALL WATER DELTA T C SCHEMES 10” (250 DN) 8” (200 DN) 12” (300DN) 5” 4” (100 DN) 3” (80 DN) 2” (50 DN) 1-1/2” (40 DN) 1-1/4” (32 DN) E. Huedem ” (150 DN ) 2-1/2” (65 DN) Check: ~2Km x 4 total Length for Shaft 7 distribution

E. Huedem 2008 Pipe Size – Overall Water System RDR 25C D T (45F D T)40C D T (72F D T) Kly Cluster Aug 2008 Scheme 5 Scheme 6 Scheme 7 Scheme 5 Scheme 6 Scheme 7 Kly Cluster Process Water Delta T (F) Process Water Delta T (F) Pipe Main Size 350 DN (14") 300 DN (12") 350 DN (14") 300 DN (12") 200 DN (8") (less surface RF Load) Largest Pipe size in Tunnel 300 DN (12") 250 DN (10") 200 DN (8") 150 DN (6") Chilled Water Delta T (F) 18 none Pipe Main Size 250 DN (10") none Largest Pipe size in Tunnel 200 DN (8") none

Summary A Matrix (cost savings vs issues) resulted from the VE cost evaluation, showing the corresponding issues and impact. This will be check and updated and the effort will be documented. Close the loop on the VE items from Dec 06. Cost savings comes from a combined number of VE items not just from single one, mainly from removal of Centralized Chilled Water Loop & LCW skid, & reduced heat loads BUT has impacts that need to be investigated. Only considered first-cost savings. Placeholders and Impacts can affect cost later. (such as watercooled waveguide placeholder, heat loads, etc). This VE cost evaluation is only for selected VE items. Other VE (Cogeneration) may be worth pursuing by experts in those fields. The VE is only for Main Linac. Other heat loads/ water system for other area system remain immature (nothing done since RDR). E. Huedem 2008

THE END E. Huedem 2008

BACKUP SLIDES E. Huedem 2008

To account for all VE items=2 basic schemes for overall water system Scheme 5Scheme 6 COMMON TO BOTH SCHEMES Eliminate chilled Water. Use only process water Yes Remove LCW SkidYes Reduce Rack Heat load by 50%Yes DIFFERENCES BETWEEN SCHEMES process cooled fancoilsYesNO localized compressorized cooling unitNOYes service tunnel space temperature45 C (113 F)29 C (85 F)

Where did we get this data? E. Huedem 2008 based on (1) 30 HP per 4 RF from Clay Table dated Clay's Nov (2) 1.5 HP per RF (Table 4 Ashrae Chap 28) placeholder based on (1) 5 HP per 4 rf (table4 Ashrae Chap 28) placeholder * Clay - 14 W per sq m**Nov Keith Added Value * Clay typical 112.Kva oil xfmr * Nov Keith Added Value * Clay typical 112.Kva oil xfmrKeith J * C.Jensen kVa 0.84pf oil ps xfmr **Shigeki Apr ** Clay LLRF meeting ** Sep 18 move all to LCW per Marc Ross ** Move load to Dirty Water per RCassell Oct , **Nov Keith Jobe Wag on load to Air**Nov C. Adolphsen ** RCassell Oct ** Move load to Dirty Water per Rcassell Oct LCW for now **Nov Keith Jobe wag on load to air **Chris Jensen Post meeting notes **Nov C. adolphsen ** Rcassell Oct **Oct fix delta T * Shigeki Fukuda **Shigeki Apr **Nov Keith Jobe wag on load to air** C. Adolphsen ** from Chris Jensen ****supply temp, water flow, press drop from Chris Jensen mtg **Shigeki Apr ** Nov Keith Jobe wag on load to air** C.Adolphsen ****supply temp, water flow, press drop from Chris Jensen mtg **Shigeki Apr ** Marc& Keith -remove load to air/chilled - transfer all load to water**Nov Keith Jobe wag on load to air** C. adolphsen **supply temp, water flow, press drop from Chris Jensen mtg * Shigeki Fukuda **Nov Keith Jobe wag on load to air** C. Adolphsen *Shigeki Oct * Shigeki Fukuda **Nov Keith Jobe wag on load to air** C. Adolphsen * Shigeki Oct * Shigeki Fukuda ** Keith Jobe added stability Oct * * HLRF 11/16 /06 meeting** C. Adolphsen *Shigeki Oct **Oct Fix Supply temp *Shigeki Oct * Shigeki Fukuda **Shigeki Apr (chilled water) ***Rlarsen ** RayLarsen except reduced by 40% per Marc * Ray HLRF Meeting 11/16/06** C. Adolphsen *C. Nantista Oct * C. Nantista Oct **Shigeki Apr **HLRF 11/16/06 meeting update from 24.3 to 29.8 KW** C. Adolphsen **C. Nantista Oct ** Oct Flow, Supply Temp per Oleg, NO Press drop *Chris Nantista Oct liter per min per load, 10 bar press, no press drop, but 30 C for circulator? (a) HLRF meeting Nov

MEANS BOOK SAMPLE PIPE COST 1” (25DN) to 8” (200DN) E. Huedem 2008

RF Water Delta T RDR 25C D T (45F D T)40C D T (72F D T) Kly Cluster RDR Aug 2008 RF Water Main Flow 128 lpm (34 gpm) 58 lpm (15.3 gpm)37 lpm (9.77 gpm) RF Water Pipe Main 50 DN (2")32 DN (1-1/4") Pipe Size – RF Water System