From Bare Chambers to Installable Chambers Muon Barrel Week Bologna April 11 th 2003 Alberto Benvenuti INFN Bologna.

Slides:



Advertisements
Similar presentations
Davide Piccolo INFN Napoli Muon Annul Review Cern 15 September 2003 Chamber Production QA/QC MUON ANNUAL REVIEW On RESISTIVE PLATE CHMABERS CERN, 15 September.
Advertisements

Winter shutdown 08/09 Summary of HV interventions Barrel Muon Workshop, 02/09 Jesús Puerta-Pelayo, CIEMAT 17-February-2009.
Procedures during Tracker Connection WPA meeting 3 rd December 2007, Michael Eppard, CERN Installation sequence Manpower needs for installation work.
Plan for MRPC Production Yongjie Sun Center of Particle Science and Technology University of Science and Technology of China.
Davide Piccolo - INFN NapoliSIENA maggio 2004 Production and Quality control of RPCs for the CMS muon barrel system Davide Piccolo – INFN Napoli.
Walls crates cables gas chambers electronics CERN adb.
TP4-ENERSOL-TD/PV double function
Barrel Maintenance Scenario for LS1 MUON-IB CMS week 11 December 2012 A. Benvenuti (INFN Bologna)
ISR Work Progress Report Muon Week April 10 th 2003 A. Benvenuti INFN Bologna.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
Upgrade news and Proposed interventions during YETS for the Muon Barrel Alignment Szillási Zoltán, Béni Noémi (ATOMKI ) This project is supported by Hungarian.
VELO workshop, Amsterdam, april ‘00M.Ferro-Luzzi Difficulties with current mechanical design recent FEA results: to obtain sufficient stiffness of center.
J A Hill – EID RAL 1-2 September EE End Cap Mechanical Design ECAL EE End Cap Engineering CMS-UK Collaboration Meeting Brunel University September.
Activities Status and Plan for the week D. Giugni / INFN Milano D. Giugni Monday Meeting
Endcap Integration Workshop: June 11-14, CSC Commissioning Andrey Korytov.
1 E906 Pre-Amplifier Card 2009/10/07. 2 E906 Wire Chambers Station1 MWPC: –build a new E906 MWPC. –4500 channels in total. Station2 DC: –recycle old E866.
ATLAS Endcap Muon System WBS 3.5 Frank Taylor MIT M&O Request FY06 Toronto August 3, 2005 V1.1.
Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling on YB Fabio Montecassiano INFN PH/CMM.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
ATLAS Muon System WBS 3.5 DoE/NSF M&O Evaluation Group Review BNL 19-Jan-06 Frank Taylor MIT V1.3.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
Shandong University TGC Site Review Review team General impression Material presented Possible improvements Action items Conclusions.
16/04/20031PNPI / LHCb Muon EDR Wire Pad Chambers PNPI design for regions R4 in Stations M2,M3,M4  4 gas gaps of 5mm±70µm;  Active area: 1224x252.8 mm².
Straw Working Group Status assembly at CERN Plans 10/2/14Straw WG.
Mechatronics Task Force, 26-nov-02 Olivier Teller, CERN EP-CMA1 Cooling Mechatronics Schedule.
1 DT critical items status: HVBoards Control and Trigger Boards Assembly in Torino fgasparini june 2004.
Test beam setup: status report 31/03/2009 M. Alfonsi (CERN)
LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,...
Chiho Wang Duke University 1 TRT Barrel integration Status / Schedule Chiho Wang.
Update on the Triple GEM Detectors for Muon Tomography K. Gnanvo, M. Hohlmann, L. Grasso, A. Quintero Florida Institute of Technology, Melbourne, FL.
19 January 2006VELO installationEddy Jans 0 VELO-installation meeting CERN, January 17, 2006 preparation IP8-area SX8 moving SX8 -> IP8.
Production Readiness Review at PNPI Chamber assembling: Main production and quality control steps 30 January 2004 – G.Alkhazov 1.Input components control.
2/4/2001Ludovico Pontecorvo INFN Roma1 Plans for the H8 system test: 2001/2002 Goals for the 2001/2002 Test beam Beam layout Chamber Supports 2001 Schedule.
CLAS12 Drift Chamber Prototyping
October 18, Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
Zaragoza, 5 Julyl Construction of and experience with a 2.4 x 1 m² micromegas chambers Givi Sekhniaidze On behalf of the Micromegas community.
CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling,
M1 Central Part Cable Routing R3 FAR R2 CLOSE R2 FAR + GEM A3 B From chain GEM R2 CLOSE R2 FAR A1 20 A1 A1 A2 A CHAIN Access Front Dané.
Executive Committee, Toronto August 3, 2005 TRT Barrel WBS 1.2/3.2 Harold Ogren Indiana University.
11/02/2005M. Alfonsi - LNF1 DETECTOR CONSTRUCTION M. Alfonsi - LNF.
Installation of the T600 at Fermilab CSN2, September 22,
Trigger efficicency on double tracks Trigger efficiency on isolated tracks Final results of the Trigger Test on the 25ns beam Bx NUMBER Fraction of Triggers.
Chiho Wang ATLAS TRT Duke University CERN, Sep Barrel integration status.
Update: Puck and Gun Magnet March 1, Magnetized Gun 2 K 2 CsSb Preparation Chamber HV Chamber.
T2 Status Report IP5 Installation Future plans. IP5 installation The mechanical structure has shown problems on installation and should be changed slightly.
Meeting at Chooz PMTs Mechanical support on the Buffer. Updates. Enrique Calvo Alamillo
IRC/SAC status Venelin Kozhuharov for the SAC/IRC working group NA62 Meeting
2010/12/14 Caltech Massimo Benettoni FDIRC FBox (almost) ready for production Box design finalized (as possible) Gives precise Fblock positioning wrt guiding.
1 Drift Tubes TC activities up to LS2 1.Implement remaining Phase 1 upgrades :  in USC ⁻ TwinMux ⁻ microROS 2.Refurbish HV & LV Power Supply Systems ⁻
Magnetized Beam LDRD: Design Tasks February 19, 2016.
1 Status of RPC Construction & Cassette Assembly Qingmin Zhang Argonne National Laboratory
H.-G. Moser, April 25, 2016 Gemba Summary 1 Plan: Shipment (sea transport in summer) 6-8 weeks => arrival August/September Commissioning: After October.
Integration and Services RE3/1 and RE4/1
Service channels between Tracker and PP1
Integration and Services RE3/1 and RE4/1
Service channels between Tracker and PP1
VELO-installation meeting CERN, January 17, 2006
- STT LAYOUT - SECTOR F SECTOR A SECTOR B SECTOR E SECTOR D SECTOR C
CMS WEEK Sept. 24 Opening session CMS MUONS: Barrel Drift Tubes
Mini-drawers, FE-ASIC , Integrator
G. Carboni for the Muon Group
ESR for the muon DT Minicrate System
DT Infrastructure: LV, HV, Gas
Pierluigi Paolucci - I.N.F.N. Naples
RPC HV&LV status Introduction HV power supply tender
Well Repair Installation of Well Liners
Limited Streamer Tube Project Summary
Plans for the 2004 CSC Beam Test
Presentation transcript:

From Bare Chambers to Installable Chambers Muon Barrel Week Bologna April 11 th 2003 Alberto Benvenuti INFN Bologna

Bare Chambers (August 2002), the bubbler has improved

Most Chambers are either Plus or Minus by construction (Wheel specific) Once services are attached they acquire parity (Left/Right) Complete with RPCs they are sector specific (gravity)

Installable Chamber Gas Circuit Cooling Loop HV cables Alignment and gas manifold cables Alignment forks and electronic boards Alignment Calibration Grounding straps Finished Theta SL: Front end cables Test pulse cables Low Voltage cable Slow Control cable Cable protection (carter) ancillary supports on SLs tap holes to attach MiniCrate attachment to rails (balance beam and bearings) attach RPCs and test that all works

Hans R. March 03

Cables and gas pipe fit in available space but check for interferences (90^ gas connector in front) The insertion must be done in sequence  Flat cables  Polypropylene protection 0.9mm thick  gas pipe  HV cables All items must be available before work on HV connectors can begin

Gas Connection: flat cables protected by plastic strip, insertion sequence: flat cables, copper pipe, HV cables

Gas pipe shape fits well Must be ordered ASAP, procure copper pipe (4 to 6 weeks!), identify firm to produce them, get prototype Dimensions must be checked wrt present routing but present knowledge sufficient to start the procedure. Flat cable procurement is pending on fixing PADC position and MiniCrate position:  fix PADC position, not much freedom anyway  attach variable pigtail at MiniCrate (MB type dependent) and fix the last 6core flat cable length, find/build jumper connector. Begin insertion of HV cables and connectors

Hans R Gas manifolds under calibration in Aachen. Connecting hoses to SLs are defined/approved by TIS? Position of front manifold has been defined? Connection to PADC?

HV Cables 4 single ended, Beta, cables required per chamber and 2 complete, Gamma cables (Theta SL). Beta cables for first installation are almost completed in Legnaro (Marco + Enrico Borsato + 2 Chinese technicians). Will be shipped to CERN. HV test station, one set complete and under commissioning, second set to be ready early June. To be decided if first set goes to ISR or China. Test station to identify correct wire/pin map at soldering stage almost completed in Bologna. Preparatory work on connectors to speed-up soldering under way. Soldering stations under procurement, strict clones of the ones used in Legnaro Aim for 2 chambers/day but rate will depend on chamber handling and available personnel

100 ready beginning of May

Baseline Cooling Loop MiniCrate is the largest Heat source, water flows through SL front-ends before entering MiniCrate BUT only in one side

Hans R. April 02 Tried to implement using copper pipes for but it proved too difficult. Since cooling flow is reversed on one sector (MiniCrate to SL front-end) then cooling capacity must be sufficient independently of what heat source is first. Choose cooling path most appropriate in view of interference of cables and MiniCrate

IP Phi 2 Phi 1 RPC 2 RPC 1 Theta MiniCrate From RPC1 in Adjacent Sector IP Phi 2 Phi 1 RPC 2 RPC 1 Theta MiniCrate To RPC1 in Adjacent Sector Proposed Cooling Circuit  Cooling Connection to MiniCrate at opposite end from Theta SL front-end cables  MiniCrate can be positioned close to Theta SL FE

Cooling from adjacent sector (RPC1 =>MiniCrate => Phi1 connections)

Cooling from adjacent sector (Phi1=>Theta => Phi2 connections)

Cooling from manifold (RPC2=> Theta => Phi2 connections)

Cooling from manifold (Phi1=>MiniC=>Phi2 connections)

Cooling Connections Connections to the MiniCrate are always on the opposite side of the Theta front end cables. This allows also to position the MiniCrate as close as possible to the Theta front end side. For MB1 this configuration looks like a must not an option. The connecting pieces are all realistic and can be improved with the appropriate tooling. The exercise was done without cables from the Theta SL: signal, pulse and especially low voltage It must be repeated with all components in place. Connections to and interference with the RPCs is a major worry. We should consider the use of the flexible hose for the connection DT/RPC. Slots instead of holes should be used on the support pieces of the MiniCrate otherwise they cannot be installed At least 2 x 5 different pieces in stainless steel are needed. Going from models to executive drawings is an URGENT and time consuming job.

Alignment Chamber handling is labor intensive and time consuming. Support piece is very heavy 2 people to hold plus one to put the screws There is not sufficient space between chambers to mount the support pieces on the stacks. 2 additional pieces (20cm) must be inserted under the chamber or move to the floor. An additional set is needed to streamline the operation

Chamber supports Mounted before shipping to SX5 It requires one hour and two technicians once the pieces are pre-assembled 2 pieces

Alignment A significant sample of chambers (each type) should be calibrated ASAP to gain experience and verify the method. There is no reason why cable lengths should not be defined NOW. Even if cables are not available, chambers should be calibrated anyway with external cables. Some work is still required on the chambers: Clean the alignment passages (NOT trivial) Remove excess glue from reference blocks ( gas leaks? Overpressure test again?) Insert missing alignment pins and replace the odd ones Handling chambers is not easy and the logistic is painful since chambers get re-stacked. Competition for crane usage will become an issue. The work must be planned in advance and technical support scheduled (2 technicians).

Chambers to be installed in 2003 Torino

January – March 2004 Torino Priority

Chamber Tests Acceptance (HV, OverPressure) Scaler (Noise), Front-End Slow Control Cosmic ray tests: Must accelerate to 4 Chambers/week Full time technical support to move chambers More physicists to perform/analyze data Experts to fix HV / Front end problems Prepare a buffer of Certified chambers

Manpower Requirements Assuming that all pieces are on the shelf : Gas, Alignment PADC, HV cables, HV connectors 3 technicians (1 + 1 for soldering, 1 mechanic) 6 Chambers / week Cooling circuit 2 technicians 10 Chambers / week Cabling Front-end, Low Voltage, Protections 1 physicist + 1 technician 6 Chambers/week ???? Tests with cosmics Coupling to RPCs will be done as last operation

Summary The list of missing items is very long and still incomplete: Front-end cables, Test pulse cable, Low Voltage Splitter Board Low voltage cable for MiniCrate Cable protections Supports for LV splitter board, Gas manifold on MiniCrate At least one chamber of each type must be checked with everything on including RPCs to make sure that there will be no interferences once the chamber is installed and we try to mount the MiniCrate. It should not come as a surprise that Summer is approaching and our technical staff has vacation days due.