LHC Sector Test Mike Lamont. LHC sector test - MAC June 072 14/6/2007 Outline Overview Motivation Pre-requisites/preparation Tests with beam Organisation.

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
RF de-bunching problem  The Beam Phase module measures the phase of each individual bunch and makes an average that is passed to the Low Level for updating.
Injection test? Mike Lamont For initial discussion.
Beam Instrumentations: Requirements for Proton and Electron Beams C. Bracco, E. Gschwendtner, B. Goddard, M. Meddahi, A. Petrenko, F. Velotti Acknowledgements:
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
Injection test1 Injection test in 2006 The installation schedule version 1.7 recently approved includes a ‘possible injection test’ - foreseen in April.
Massimo GiovannozziChamonix XV, January Electrical circuits required for the minimum workable LHC during commissioning and first two years.
LHC Sector Test1 LHC Sector Test - Beam IntroductionMike LamontIntroductionMike Lamont Proposed tests with beamBrennan GoddardProposed tests with.
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Commissioning Samuel Krinsky-Accelerator Physics Group Leader NSLS-II ASAC Meeting October 14-15, 2010.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
R. Assmann - LTC Two Beam Operation R.W. Aßmann with W. Venturini and V. Kain LTC Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P.
EPPOG - LHC Machine LHC machine (and some outreach) Mike Lamont.
The Stripping Foil Test Stand in the Linac4 Transfer Line
LHC Sector Test 1 Roger Bailey, Helmut Burkhardt, Paul Collier, Brennan Goddard, Stephen Jackson, Lars Jensen, Rhodri Jones, Verena Kain, Alex.
Schedule IT General Schedule 9 th, September 09 Today.
LHC Workshop, Jan '05P. Collier AB-OP/LHC1 450 GeV P. Collier AB/OP  Prerequisites  First Turn  Getting Closure  RF Capture  Preliminary Commissioning.
Running scenario 2009/10 Run through components – and then synthesis.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
Overview Extraction tests: TT40 and TT60, week 21 –controls and data, interlocking, extraction, MKE6 transfer function and energy tracking, high intensity,
1 Sector Test – Preparation Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
MD Wed – Sat DayTimeMD Wed06:00UPS repair, ATS optics checks w/o beam 12:00Cycle, test ATS optics w/o beam 16: TeV: BPM offset determination for.
Beam-beam compensation at RHIC LARP Proposal Tanaji Sen, Wolfram Fischer Thanks to Jean-Pierre Koutchouk, Frank Zimmermann.
( LHCMAC Chamonix Summing-upLHC MAC June 15, Third LHC Project Workshop January 2006.
Chamonix 2006, B.Dehning 1 Commissioning of Beam Loss Monitors B. Dehning CERN AB/BDI.
Transfer Line Test preparation meeting V. Kain, R. Alemany.
LHC sector test - summary 1 14/03/2008 Possible injection into part of the machine Options etc.Mike Lamont Stopping the beamStefano Redaelli Proposed Tests.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Commissioning Strategy - Chamonix LHC Commissioning with Beam Overall Strategy Mike Lamont AB-OP 17 th January 2005 Chamonix XIV B.D.S.
LHC Commissioning Status Gianluigi Arduini CERN – AB Department For… 23/10/20081LHC Commissioning Status - G. Arduini.
26 January 2006Chamonix LHC Project1 Chamonix 2006 – LHC Project Workshop Proposed tests with beam B.Goddard AB/BT Input from L.Bottura, B.Dehning,
Expected field quality in LHC magnets E. Todesco AT-MAS With contributions of S. Fartoukh, M. Giovannozzi, A. Lombardi, F. Schmidt (beam dynamics) N. Catalan-Lasheras,
HiRadMat Summary of Phase-I and plans for Phase-II commissioning J. Blanco, N. Conan, V. Kain, K. Cornelis, B. Goddard, C. Hessler, M. Meddahi, C. Theis,
HiRadMat Primary Beam Overview C. Hessler, B. Goddard, M. Meddahi On behalf of the HiRadMat Primary beam line working group HiRadMat Project Review
Options for Possible Sector Test Mike Lamont. LHC sector test
LHC Commissioning with Beam
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Minimum Hardware Commissioning – Disclaimer
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
LHC schedule.
The LHC - Status Is COLD Is almost fully commissioned
Powering the LHC Magnets
Summary of week 7 Hardware Commissioning:
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
Machine plans - Alignment workshop
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
LHC Commissioning Phases
UPDATE ON DYNAMIC APERTURE SIMULATIONS
Thursday morning – optics correction
Machine availability reaching well over 80%
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
Interpretation and use of BLM Data
Sector Test - General objectives
Remote setting of LHC BLM thresholds?
Verification of the Beam Loss studies at start-up
Week 35 – Technical Stop and Restart
Wire almost entirely through beam before BLM triggers dump
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
1st HiLumi LHC / LARP Collaboration Meeting 2011 Nov 17th
LHC Beam Operations Past, Present and Future
Global aperture measurements at 450 GeV with 170 mrad crossing angle
450 GeV Preliminary Commissioning: Measurement Programme
Machine plans - CMS startup workshop
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Wednesday 23/2 Thanks CRYO!!!.
Beam commissioning plans, 2007 and 2008
Daniel, Gianluca and Belen (for the Collimator team)
Presentation transcript:

LHC Sector Test Mike Lamont

LHC sector test - MAC June /6/2007 Outline Overview Motivation Pre-requisites/preparation Tests with beam Organisation Conclusions

LHC sector test - MAC June /6/2007 TI8 – injection L8 – LHCb - arc 7-8 – IR7 2 weeks with beam Close sectors 8-1, 7-8 and 6-7 Beam  Pilot Beam for the most part: single bunch of x 10 9 protons  Total intensity: 3 x protons - comparable with one nominal intensity LHC extraction from the SPS TI8 – injection L8 – LHCb - arc 7-8 – IR7 2 weeks with beam Close sectors 8-1, 7-8 and 6-7 Beam  Pilot Beam for the most part: single bunch of x 10 9 protons  Total intensity: 3 x protons - comparable with one nominal intensity LHC extraction from the SPS Overview…

LHC sector test - MAC June /6/2007 Injection

LHC sector test - MAC June /6/2007 Triplets & LHCb Aiming for minimal losses in LHCb

LHC sector test - MAC June /6/2007 Sector 7-8 X 23

LHC sector test - MAC June /6/2007 IR7 layout 1. Intercept the beam with the three TCP’s and with the TCSG’s 2. Invert the polarity of D3 3. Switch OFF all the quadrupoles Nominal orbit D3 OFF D3 inverted Stefano Raedelli Ralph Assmann

LHC sector test - MAC June /6/2007 Intercepting the beam with the TCP’s

LHC sector test - MAC June /6/2007 IR7 Three TCPs closed “smartly”, D3 in opposite polarity, quadrupoles off  All beam particles interact with >1m of C (typical=1.8m; max=3m)  Additional protection from the next secondary collimators EM showers are expected to be absorbed by MBW and MQW yokes (no issues for magnet). Detailed estimates should confirm that. Minimum impact on the machine: - D3 polarity change (cable). - Lock collimators in position - Local activation - simulations to be performed.

Motivation

LHC sector test - MAC June /6/2007 Integration Full test of a majority of subsystems over more than one eighth of the ring Allows staged approach to the full problem space Time to fully resolve problems before the real thing  Analysis, improvements, resolution, adjustment The lessons learnt will reduce the time needed for full commissioning Buys breathing space if there are any serious problems

LHC sector test - MAC June /6/2007 Integration & commission with beam: Full-blown system wide integration test

LHC sector test - MAC June /6/2007 Beam – the ultimate diagnostic Polarity of magnetic elements Aperture in the cold machine Response of key beam instrumentation Magnet field quality "What like a bullet can undeceive?" Herman Melville

LHC sector test - MAC June /6/2007 Milestone Machine Protection Controls++ Magnets (model etc.) Beam Instrumentation BT: Kickers, Septa, TDI Collimation Radiation Protection Access Operations Hardware Commissioning

Required circuits

LHC sector test - MAC June /6/2007 IR8 RQ5.R8Q5 quadrupole RQ4.R8Q4 quadrupole RD2.R8D2 recombination dipole RD1.R8D1 recombination dipole RQX.R8Inner triplet RQX.L8Inner triplet RD1.L8D1 recombination dipole RD2.L8D2 recombination dipole RQ4.L8Q4 quadrupole RQ5.L8Q5 quadrupole RQ6.L8MQM MQML Plus dipole correctors

LHC sector test - MAC June /6/2007 DS left IP8 RQ7.L82*MQM RQ8.L8MQML RQ9.L8MQM MQMC RQ10.L8MQML RQTL11.L8B2MQTLI RQT12.L8B2MQT RQT13.L8B2MQT Plus dipole correctors Item: Two lips, indifferent red Item: Two grey eyes with lids to them Item: One neck, one chin, and so forth.

LHC sector test - MAC June /6/2007 Circuits Number of circuits Priority Main bendsMBRB.A7811 Main quadsMQRQF, RQD21 Skew quadsMQSRQS [B2]11 Trim quadsMQTRQTF,RQTD [B2]21 Orbit correctorsMCBRCB [B2]23 H & 24 V1 Lattice sextupolesMSRSF,RSD [B2]42 Lattice octupolesMOROD, ROF [B2]13 Skew sextupolesMSSRSS [B2]13 b3 spoolMCSRCS [B2]13 b4 spoolMCORCO [B2]13 b5 spoolMCDRCD [B2]13 Arc 7-8

LHC sector test - MAC June /6/2007 DS/LSS - right of 7 RQT13.R7B2QT RQT12.R7B2QT RQTL11.R7B2QTLI RQTL10.R7B2QTLI RQTL9.R7B2QTLI RQTL8.R7B2QTLI RQTL7.R7B2QTLI RQ6.R7B26* QTLH Q7,Q8,Q10,Q11: one MQTL alongside the MQ quadrupole Q9: two MQTLs Plus dipole correctors

LHC sector test - MAC June /6/2007 Required circuits To get beam through sector 78, the main circuits listed above are required to be commissioned to 450 GeV. For limited recycling, it would be preferable for listed circuits to be available to, say, the equivalent 1 TeV level. Beam 2 Circuits only Circuits commissioned to 450 GeV+ only

LHC sector test - MAC June /6/2007 Other systems Injection elements: septa, kickers Collimators Machine Protection Beam Instrumentation:  BPMs, BLMs, BTV, BCT, BST Magnet Model:  Transfer functions, harmonics Controls Software/tools Access system Radiation Protection Radiation Monitoring Optics, aperture model Sector Test is another progressive milestone to be used for testing key functionality Work in progress but most of this is in good shape. Effort in these areas is essentially orthogonal to HWC.

LHC sector test - MAC June /6/2007 Access Sector 6-7.  Interlocked gate right of IP 6 Point 7 (PM76)  Access system operational. Point 8 (PM85)  Access point fully operational. PZ85  Interlocked door in shielding wall Sector 1-8:  Interlocked gate left of IP 1 Sector 6-7.  Interlocked gate right of IP 6 Point 7 (PM76)  Access system operational. Point 8 (PM85)  Access point fully operational. PZ85  Interlocked door in shielding wall Sector 1-8:  Interlocked gate left of IP 1 Final Configuration

LHC sector test - MAC June /6/2007 Radiation Protection All major installation will have finished and access to the zones affected after the test will be limited. Dose maps for collimators in IR7 to be carefully evaluated. Given analysis, and measurements during and after the test, it is envisaged that:  Certain areas might be declared controlled areas for the first few days after the test;  Thereafter these areas would join the rest of the sectors involved as supervised areas  LHCb remains an undesignated area Traceability restrictions come into force Need for additional RP instrumentation to be evaluated. Work in progress. NB amount of beam is minimal.

Beam

LHC sector test - MAC June /6/ Commission injection region Steer into ring, onto TDI Check instrumentation, septa, kickers, aperture… D2 BTVSS Q5 Jan Uythoven

LHC sector test - MAC June /6/ Thread to IR7 Commission trajectory acquisition and correction Thread beam Jorg Wenninger

LHC sector test - MAC June /6/ Linear optics measurements Trajectory response using correctors and BPMs  BPM + corrector polarity and calibration errors  Phase, coupling Dispersion measurement with  p and BPMs Betatron matching measurement with BTVs

LHC sector test - MAC June /6/ BLM system tests Get the system up and running, recording losses  Prior calibration with source: expect reasonable numbers  Acquisition & display of beam losses  Some crosstalk studies possible (in principle ‘beam 1’ monitors available…) Bernd Dehning

LHC sector test - MAC June /6/ Aperture measurement First iteration : oscillation from 2 correctors at 90º to probe ‘all’ phases Second iteration if needed/time :  bumps (local anomalies, specific regions) TI 8 and sector 7-8 V-aperture and 8  oscillation MSI Brennan Goddard

LHC sector test - MAC June /6/ Momentum Aperture Transmission vs momentum offset by changing SPS RF frequency Re-scale TI 8 to new momentum  p/p = (1  m  n )

LHC sector test - MAC June /6/ Field quality checks Kick-response and trajectory analysis LOCO – might be able to get a handle on average a2, b2 and b3 field errors of MBs, b2 of MQs  Possibly extend method to check multipole corrector polarities (possibly via strong excitation)) MB b3 field error effect (mean -9.6 units, rms 1.4 units). H trajectory change for 40  rad H kick (top) and 40  rad V kick (bottom) Jorg Wenninger

LHC sector test - MAC June /6/ Effects of magnetic cycle Machine reproducibility and persistent current effects at injection for reduced pre-cycle

LHC sector test - MAC June /6/2007 Quenches with beam motivation: - safe and efficient operation - avoid quenches and damage Controlled, well defined tests to establish: Absolute quench limits BLM threshold values Model and understanding of correlation of loss pattern, quench level, BLM signals Test important for efficient commissioning of BLM system with circulating beam 9. Quench limits and BLM response

LHC sector test - MAC June /6/2007 Other possibilities… 10. Energy offset versus time on flat bottom 11. Transfer line collimation studies 12. Injection projection studies 13. Separation and crossing angle bumps  Injecting onto vertical separation bump  Bump closure, induced dispersion, aperture 14. Commission multi-bunch injection

LHC sector test - MAC June /6/2007 Beam tests - summary

LHC sector test - MAC June /6/2007 Near test schedule Phase Time Sector checkout, interlock & machine protection tests etc. T start - 2 weeks Close sectors 6-7, 7-8, 8-1 T start – 3 day Access system tests & qualification T start – 2 day Beam to end TI8 T start – 1 day Tests with beam 2 weeks Radiation survey T end + 1 day Establish supervised areas T end + 2 day

LHC sector test - MAC June /6/2007 Schedule.. Operation testing of available sectors Mar. Apr. May Jun. Jul. Aug. Oct. Sep. Nov. Dec. Jan. Apr. Feb. Mar. May Jun. Jul. Aug. Sep. Nov. Dec. Oct. Mar. Apr. May Jun. Jul. Aug. Oct. Sep. Nov. Dec. Jan. Apr. Feb. Mar. May Jun. Jul. Aug. Sep. Nov. Dec. Oct Machine Checkout Beam Commissioning to 7 TeV Consolidation Interconnection of the continuous cryostat Leak tests of the last sub-sectors Inner Triplets repairs & interconnections Global pressure test &Consolidation Flushing Cool-down Warm up Powering Tests

LHC sector test - MAC June /6/2007 Impact 1/2 Given the state of installation, the sector test should have minimal impact on transport, interconnection work etc. Deliberately chosen solution in IR7 which avoids additional interventions Restricted access to sectors 8-1, 7-8, 6-7 during beam tests ~ 14 days 7-8 and injection region part of 8-1 become supervised areas after test (film badge etc.) Work/Commissioning can clearly continue in other sectors during the test

LHC sector test - MAC June /6/2007 Impact 2/2 Sector test makes clear demands on:  what is needed to be cold  on what is needed to be hardware commissioned  and to what level Cryogenics, QPS, HWC support required during test Could take time out of HWC program  HWC would have to stop in 7-8 during test Test preparation, other than cold mass, largely orthogonal to HWC

LHC sector test - MAC June /6/2007 Details Sector test with beam Overview, motivation and schedulingMike Lamont Proposed tests with beamBrennan Goddard Magnet quenches with beamAlex Koschik Beam InstrumentationLars Jensen Magnet requirementsLuca Bottura Controls requirementsRobin Lauckner Sector test preparationChair: Pierre Strubin PlanningEsther Barbero Soto Global Hardware StatusMiguel Jimenez Layout in LSS7Jan Uythoven Hardware CommissioningRoberto Saban State of LHCb for the testMassimiliano Ferro-Luzzi Radiation IssuesHelmut Vincke Access systemPierre Ninin Team in place which is examining implications, requirements and details of planned beam tests Chamonix

LHC sector test - MAC June /6/2007 Conclusions A sector test is surely a very useful exercise  Undoubtedly speed full commissioning It could prove to be a vital exercise  If any major problems are uncovered Requirements have clearly stated and are being addressed Planned beam tests have been detailed The potential impact would be minimal.  Machine as is or as will be. Work carries on elsewhere.  However, for the test to take place this year (if the schedule allows) Hardware Commissioning would have to be tailored to provide necessary circuits to the necessary level.

LHC sector test - MAC June /6/2007 Acknowledgements MagnetsLuca Bottura Beam InstrumentationRhodri Jones, Lars Jensen, Stephen Jackson InjectionBrennan Goddard, Jan Uythoven Radiation ProtectionDoris Forkel-Wirth, Helmut Vincke INB Ghislain Roy AccessPierre Ninin LHCbRolf Linder HWCRoberto Saban & team Installation Katy Foraz PlanningEsther Barbero Soto VacuumPaul Cruikshank, Miguel Jimenez ControlsRobin Lauckner ++ OP/APRoger Bailey, Verena Kain, Massimo Giovannozzi, Stephane Fartoukh, Helmut Burkhardt, Alex Koshick, Stefano Raedelli, Ralph Assmann, Frank Zimmerman… and the rest of the commissioning team.