Rantoul Street / 1A Reconstruction Project December 10, 2015
Project Background History of Rantoul Street Deterioration of roads and sidewalks How the project is being funded Allocation of project responsibilities City of Beverly Designed with consultant Dewberry Pre-work due diligence Constituent support MassDOT Approved design Selected General Contractor Providing Project Management Middlesex Corp The General Contractor
Looking back Rantoul St. at Broadway in the 1920s Rantoul St. in the 1940s
Existing Conditions
Project roadways Rantoul Street: 5900 ft. / 66 ft. ROW Cabot Street: 3800 ft. / 50 ft. – 66 ft. ROW Elliot Street: 1000 ft. / 66 ft. ROW Five (5) existing traffic signals Utilities – underground and overhead Rail crossings Historic properties
Scope of Project
New Design – Roads and Infrastructure Drainage improvements Reconstruction traffic signals / New traffic signals Rail grade crossings Gloucester Crossing improvements Complete Streets design
Gloucester Crossing Improvements
Typical Complete Streets Cross Section
New Design – Streetscapes What it includes Lighting Elements Sidewalks Street Trees Goals Improve Economic Development Enhance Pedestrian Environment Safety Improvements
Lighting
Elements
Sidewalks
Street Trees
Rendition of Rantoul Street at Odell Park
Rendition of Cabot Street at Herrick Street
Work Schedule
Impact of work on Residents and Businesses New traffic patterns Two way traffic Single lane traffic Full street closures and detours No parking at times Sidewalk closures at times Staging locations
Outreach/Updates and Reporting Issues How to find out information: Website – Twitter Sign up for weekly notifications Concentrated Reverse calls Day-to-day outreach by onsite contractor Project signage 1A Committee Kevin Harutunian, Chief of Staff Open for Business Campaign: Upcoming Business forums Beverly Main Streets efforts