Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker October 21, 2015.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 Low-energy RHIC electron Cooler (LEReC) Update November 17, 2014.
Scientific Goals: V. Litvinenko’s RHIC retreat talk Commissioning Goals: I. Pinayev presentation last week Run 14 Goals: Complete assembly of 112 MHz SCRF.
GlueX Solenoid Update George Biallas May 12, 2010 GlueX Collaboration Meeting.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting Approved Labyrinth Fresh air pulled through “chicken wire” gate.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF ODH Discussion How to avoid ODH2 conditions? August 5, 2015.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
Bubble Chamber Installation Kick-Off Meeting May 28, 2014, Grames Let’s discuss two jobs between the cryounit and injector gate. Bubble chamber (5D) New.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
1 LEReC Funded! From: Fedotov, Alexei Sent: Thursday, May 14, :04 PM Subject: LEReC project approved Dear All, FYI. The LEReC project is now formally.
’ tall Empty space below this metal sheet 66’ 14’ 4’ 10’ Ceiling tiles = 24 Concrete blocks 14’ long There are two “styles” of Ceiling tile,
09/13/20111 Status of high intensity polarized electron gun project at MIT-Bates Evgeni Tsentalovich MIT.
Upgrade Injector Test Facility: UITF Why Build It? HDIce commissioning Bubble chamber physics with Bremsstrahlung x-rays: photo-disintegration of oxygen.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker July 31, 2015.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
MINU GPP WBS 1. Main Injector Neutrino Upgrades - Infrastructure Project Dixon Bogert APD Department Report – March 7, 2007 Russ Alber - FESS Engineering.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting Re-scoping UITF Matt Poelker November 14, 2015.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
Development of High Current Bunched Magnetized Electron DC Photogun MEIC Collaboration Meeting Fall 2015 October 5 – 7, 2015 Riad Suleiman and Matt Poelker.
CEBAF Source and Injector Status PREx-II Collaboration Mtg Feb. 26, 2016 Matt Poelker and Joe Grames Center for Injectors and Sources.
CMTF Infrastructure Jerry Leibfritz PIP-II Machine Advisory Committee 9-11 March 2015.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
CMTF GROUNDING FOR PIP-II K. Carlson PXIE Electrical Coordination Meeting December 19 th, 2013.
PX FY14 Budget PXIE Infrastructure R. Stanek J. Leibfritz.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker April 12, 2016.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker February 23, 2016.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting What we started with… UITF as imagined Upgraded Injector Test Facility - UITF.
UITF ODH Assessment UITF Safety Review May 10, 2016.
Thomas Jefferson National Accelerator Facility Page 1 Dana Arenius Cryogenics Control Account Manager 12 GeV Upgrade Project X Collaboration September.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting What we started with… UITF as imagined Upgraded Injector Test Facility - UITF.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Upgrade Injector Test Facility: UITF Why Build It? HDIce commissioning Bubble chamber physics with Bremsstrahlung x-rays: photo-disintegration of oxygen.
ELENA installation progress F. Butin / ELENA collaboration.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker July 12, 2016.
Report Technical Director Storage-Ring-Installation Completed
CBETA Technical Review
LERF as Cryomodule Testing Facility Set-Up and Installation Logistics
UITF – Upgrade Injector Test Facility
Why are we removing our very good gun?
UITF Project Status Meeting
UITF Project Status Meeting
Upgraded Injector Test Facility
NEG-coated gun: Black R30 arc at 227kV, white R30 arc at 164 after refurbishing and second bake Carlos Wednesday, August 10, 2018.
Upgraded Injector Test Facility
J. Seeman Assistant Director for PPA/LCLS
A. Freyberg Aug 2016 ECT’16 =>
Uses of UITF 10 MeV spin-polarized electron accelerator, beam current up to 100 uA M. Poelker December 12, 2018.
Polarized Source: Recent Activities
Ciprian Plostinar Workshop on Testing and Commissioning
CTF Users’ Perspective
Upgraded Injector Test Facility
UITF Conduct of Operations Review
Accelerator Installation Schedule
SNS-PPU upgrades the existing accelerator structure
Polarized 3He target installation
Presentation transcript:

Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker October 21, 2015

Thomas Jefferson National Accelerator Facility Page 2 UITF Progress meetingOutline Purpose: to inform Lab Leadership of the UITF status Action Items (from previous meetings) Project Update –Progress Update –Milestones Update –Budget Update –Highlights & Concerns –Next meeting agenda

Thomas Jefferson National Accelerator Facility Page 3 UITF Progress meeting To refresh your memory… What we started with… UITF as imagined

Thomas Jefferson National Accelerator Facility Page 4 UITF Progress meeting Action Items – From August 31, 2015 Minutes New Action Items: Matt will provide the UITF Oct/Nov/Dec spend plan to Allison & Lyn ASAP Andy will provide information at the next meeting on the Physics Division response to his updated request for resources

Thomas Jefferson National Accelerator Facility Page 5 UITF Progress meeting Major components Facilities Engineering Mech Design Cryo Safety Systems I&C DC Power Low Level RF systems High Power RF Survey & Alignment SRF Commission with RF Operations Network and communications Progress Update Green means we can see progress

Thomas Jefferson National Accelerator Facility Page 6 UITF Progress meeting Major components Source Group Reliable 350kV ops Beam to cup in front of ¼ CM Beam to cup in front of HDIce EHSQ Shielding approval, ODH assessment  Global hazard review FSAD Accel Readiness Review Commissioning Plan HDIce Installation at Cave Beam on HDIce Progress Update Green means we can see progress

Thomas Jefferson National Accelerator Facility Page 7 UITF Progress meeting Cave 1 cleared out

Thomas Jefferson National Accelerator Facility Page 8 UITF Progress meeting Installation Group LCW, compressed air, and GN2 plumbing installed Cave1 Platforms for Electronics racks Shielding plates beneath penetrations Attach PSS conduit Cable trays above beamline

Thomas Jefferson National Accelerator Facility Page 9 UITF Progress meeting Cave 2

Thomas Jefferson National Accelerator Facility Page 10 UITF Progress meeting Facilities Electricity to top of Cave1, and inside Cave1. Procurement Dept. setting up site visit for contractors, who will submit bids. Site visit within 2 weeks, work complete by end of November. Jason W. estimates $109k

Thomas Jefferson National Accelerator Facility Page 11 UITF Progress meeting Rack layout clearly defined 11 Electricity to racks by end of November Plus outstanding PR for $18k for communications conduit… Brad would then install communications network, IOCs Pam loads software… System owners can then populate the racks

Thomas Jefferson National Accelerator Facility Page 12 UITF Progress meeting Control Room Facilities added carpet, relocated air conditioner, moved a door (thanks) Work station purchased and installed Terminals can now be installed Electricity and network connections coming soon, then IOCs, then software

Thomas Jefferson National Accelerator Facility Page 13 UITF Progress meeting Simple ODH solution? vent pipes Large entry/exit with chain-link gate Install elbow-shaped vent pipes inside pre-cast concrete Can Cryo/EHS&Q specify vent dimensions? How many? Radcon must approve from shielding perspective Two 30” vent pipes in Cave1 Six 10” dia. cable penetrations

Thomas Jefferson National Accelerator Facility Page 14 UITF Progress meeting Big Chimney near HDIce Helium source terms identified for ¼ CM and CTF, and also HDIce Strategy still focused on using passive exhaust vents to maintain ODH0 (or ODH1) conditions Large vent 30 ft 2 near HDIce, 10 ft 2 vents inside Cave1, ceiling penetration with chimney, chain link gate, Test Lab high bay equivalent to “outside” Will Oren working with Cryo, SRF, HDIce to complete the assessment

Thomas Jefferson National Accelerator Facility Page 15 UITF Progress meeting

Thomas Jefferson National Accelerator Facility Page 16 UITF Progress meeting Combine the two features that provided incremental success: shed and doped insulator Next test late September

Thomas Jefferson National Accelerator Facility Page 17 UITF Progress meeting Tedious polishing complete. Next: vacuum degas electrode components, assemble on insulator and install on gun at GTS, align photocathode puck manipulator, bake gun, patiently high voltage process the gun Repeat when black, mildly conductive insulator arrives late November Next test late October

Thomas Jefferson National Accelerator Facility Page 18 UITF Progress meeting Milestones Update WBSItemMilestone DescriptionStart Date Projected Finish % Complete Days Float? Change (%) Change (Days) 1.04.xx x FacilitiesCivil work complete6-4-15Feb %10 to 50% GunDemonstrate gun ok at 350 kW at FEL GTS Dec %0 CMCommission cold ¼ CM, no beam Jan %10 to 20% Beam from Gun to Cup in front of ¼ CM Mar %10 to 20% Beam thru MeV energy delivered to cup in front of HDIce Jun Beam to HDIceAug Tom Renzo happy with ODH vent plans, now working on aspects of Cave2 structure, taking credit for Electricity procurement Not as much progress on Gun Plan Y: my guys working on LERF, bubble chamber and CEBAF

Thomas Jefferson National Accelerator Facility Page 19 UITF Progress meeting Carryover = $81k Cancelled $71k trim card PR

Thomas Jefferson National Accelerator Facility Page 20 UITF Progress meeting Month by Month Spending Profile

Thomas Jefferson National Accelerator Facility Page 21 UITF Progress meeting Schedule Ramifications Current status: Responding to CR Working to resolve some lingering Cryo-related issues: 2K vs 4K red-herring, how best to provide LHe to HDIce, “parking” the ¼CM when not in use, 4K cold box upgrade schedule, ODH assessment Next month activities (November) Perimeter of Cave2 complete Tom Renzo finalizing Cave2 structural design (precast concrete, bracing, anchoring, roof planks) Electricity delivered to racks Find a way to purchase Communications conduit, so network and IOCs can be installed (or done by in-house folks?) ODH assessment complete, ideally with ODH0 assignment Old cryo transfer lines removed Voltage applied to gun at GTS, plan Y

Thomas Jefferson National Accelerator Facility Page 22 UITF Progress meeting Schedule Ramifications In two months (December): Source group building keV beamline Klystron rack finished, R. Nelson building control panel Low level rf boards complete, installation in racks begins IOCs installed, Software group installing software Installation group working opportunistically: shield plates, PSS conduit, cable trays, some demolition Safety System Group working on ODH system Cryo group installing new transfer lines… Procurements for Cryo controls approved Recall, next big milestone…commission ¼ CM (no beam), scheduled for Feb (cryo, ODH, LL and HP RF, software, adequate shielding, EHS&Q approvals)

Thomas Jefferson National Accelerator Facility Page 23 UITF Progress meeting Schedule Ramifications Commission ¼ CM (no beam), scheduled for Feb 2016 Electric/FM – ($109k + $23k for com. conduit) 132 k$ Control room – - SRF checkout of ¼ CM present condition – - Low Level RF – 16 k$ High Power RF – 25 k$ Network controls – 33 k$ Software control of RF – - adequate shielding (Cave2 with a roof) – - Cryo – (controls and pipe) 68 k$ Installation group 9 k$ ODH - SSG 2 k$ EHS&Q approvals… - Total 285 k$

Thomas Jefferson National Accelerator Facility Page 24 UITF Progress meeting Status Cryo Related to ¼ Cryomodule Poelker’s suggestion to operate at 4K was a distraction A challenge: appreciating the best way to connect to CTF, so as not to do it again How to cool HDIce (need to downselect) “Parking” the ¼ CM can influence design Anticipated CTF upgrades Related to HDIce Purchase LHe (expensive), Cryo group provides dewars (was our Plan A), connect HDIce to CTF Message1: Need to stop thinking and start marching Message2: 4K cold box work scheduled for August 2016

Thomas Jefferson National Accelerator Facility Page 25 UITF Progress meeting Labor-focused Tasks Installation Group Cable trays, PSS conduit, penetration shielding, rack prep in advance of electric work, removal of rails and LCW piping Cave2, silver solder the quad magnet cooling tubes Have our electricians install communications conduit Have Ops staff install network switch and IOCs Magnet Mapping, quads and solenoids Mechanical Design: finish keV region, resume MeV region design DC Power: refurbish the racks for trim cards, re-install trim cards Low Level RF – finish construction of rf control boards High Power RF – work on the control panel and klystron rack Cryo: remove old transfer lines

Thomas Jefferson National Accelerator Facility Page 26 UITF Progress meeting Design work was stopped…would like it to continue

Thomas Jefferson National Accelerator Facility Page 27 UITF Progress meetingSummary Despite CR, there is continued progress and it is becoming more obvious, visible But the schedule is slipping… Appreciating the impact of CTF 4K cold box replacement. Scheduled start date is our scheduled “beam on HDIce” target date, August 2016 BNL has asked “me” to demonstrate their high current, long lifetime, polarized beam milestone for eRHIC. Could we use this to our advantage?

Thomas Jefferson National Accelerator Facility Page 28 UITF Progress meeting Backup Slides Backup slides from past meetings, P&C meetings

Thomas Jefferson National Accelerator Facility Page 29 UITF Progress meeting “Shed” triple- point protection Doped insulator SF6 R350 epoxy receptacle Combination of doped insulator and shed, SF6 and epoxy receptacle, plus added length Yan Wang has modeled the shed, a good design… …then in October

Thomas Jefferson National Accelerator Facility Page 30 UITF Progress meeting Original vs Current Cost Estimate Presented at UITF meeting May 13, 2015: Total cost estimate. The specific allocations for FY15 and 16 are not correct Original Est. by Hari Areti FTEsLaborProcTotalLaborProcTotal on FY , FY , FY Total , , , , , Revised Est. FTEsLaborProcTotalLaborProcTotal by Matt PoelkerFY % on FY , , , % FY , , , , % Total17.7 2, , , , , , Dfference from original estimate (11.5) (1,263.46) (645.93) (1,909.39) (1,719.10) (1,014.40) (2,919.25) Loaded $Direct $

Thomas Jefferson National Accelerator Facility Page 31 UITF Progress meeting Revised Estimates Breakdown Original request to DOE: $2.6M (loaded) Current estimate for completion: $5.6 M (loaded) Delta increase of $2.9M (loaded) Labor estimates Underestimated effort by 11.5 FTEs Increased labor by $1.7M (loaded) Procurements Underestimated by ~$1M (loaded) Several sub-system components were not included in the original estimate and later determined were necessary to complete the scope

Thomas Jefferson National Accelerator Facility Page 32 UITF Progress meeting Comparison Procurement Estimates (Direct $) SystemPrevNowDeltaComment Facilities (numbers are Proc and Labor) Safety System RF Systems rf control boards, klystron PS Cryogenics Pipe, heat exchanger Polarized Source Gun insulators, beamline parts I&C BPMs, viewers, picoammeters DC Power Trim cards and parts Magnets Addl. quads, correctors, dipoles SRF HDIce50-5 Network, IOCs CIS FY14 Actuals FY14 actuals Total1,0281,

Thomas Jefferson National Accelerator Facility Page 33 UITF Progress meeting FY14 and FY15 UITF Procurements FY14FY15 Addl. expected FY15 procurements Solid Works CAD2.2Insulator flange1 Contract Mech Designer~ kV HV power supply31.1bpm components7.6 stairs~ 20 semiconducting R30 insulators52.6 semiconducting R30 insulators_v222.3 trim cards~100 gun HV chamber7.8 Klystron HV power supply55.5 quad magnets (machine shop)70 to 130 ion pumps15.1concrete wall removal32 Chopper rf amplifiers (x2)44 beamline Y chamber5LLRF parts15.1 water skid for chopper3 photocathode prep chamber4.5steering magnets19.3 keV beamline support structure6.5 drill penetrations in concrete4.2SF6 tank11.3 Addl. FY15 procurement total303.5 assorted3.9waveguide3.8 Credit card21.8SSG sensor1 Machine shop40.8assorted9.4 total189total178.3 FY14 + FY15 Procurements: UITF Total Procurements 1682

Thomas Jefferson National Accelerator Facility Page 34 UITF Progress meeting FY16 Procurements? ~ required spent in FY14 FY15 To purchase in FY16 Facilities: Cryo90.80 waiting for update RF Gun includes beamline components + contract designer I&C Hope to reduce this number using PLC technology SSG DC power Trim cards… Magnets shop to make quads, assumed 100k but could be less Still need three dipoles Network58 0 Total Of course, hope the number comes in lower: 750 k$