GTPE 04/06/15 L. Scibile 04/06/ EDMS:
Items IPP Status Parking 4-5 NEWS – Ex BP station NEWS - Mobility Centre NEWS – On-going projects 04/06/ EDMS:
IPP Process status 04/06/ EDMS:
IPP Status: Approved for study The two projects clearly identified as having safety implications: – IPP : Relocation of the coating laboratory to a more adequate working area on the first floor of Bldg 101. (X) – IPP : Replacement of Bldg 195 and refurbishment work on associated buildings (196 and 232) and infrastructure Two projects with consolidation implications: – IPP : RAMSES Office, storage and laboratory space – IPP : Refurbishment of Bldg 156 And seven new projects: – IPP : Second network hub (X) – IPP : Extension of radioactive equipment storage building capacity (X) – IPP : Modification of Bldg 238 and tank for gensets (X) – IPP : New building for metallurgy laboratory. – IPP : Conversion and refurbishment of chemical laboratories in Bldg 3 for the safe handling of nano-materials. – IPP : ALICE R&D O2 lab. (X) – IPP : ALICE visitor space in Point 2. 04/06/2015EDMS:
IPP Status: Not approved Projects not considered for this round of IPP: – IPP Storage building for rewinding line, cables and connectors – IPP Construction of a New Assembly Hall in Prévessin near Building 867 – IPP New Training Centre Prevessin – IPP CMS 3585 Annexe (Workshops and Tooling storage) – IPP Building 287 Extension – IPP Building Annex 04/06/2015EDMS:
Parking /06/ EDMS:
PARKING (Consolidation program) Safety For Pedestrians and cyclists For kids from the kindergarten For car traffic on and around the parking (entrance, exit, junction) Continuous sidewalk from Entrance A & Building 33 to main building No reduction of number of parking spots Dedicated parking spots for kindergarten drop-off (3m wide instead of 2.5) Dedicated car sharing parking spots Disabled parking spots Emergency services road marking Energy saving and high performing led lighting ENTRANCE A (security & mobility program) Access control for cars, pedestrians and cyclists Car plate reader for in- and out-going cars Fully automated gates (car, bike, pedestrians) Program 04/06/2015EDMS:
Existing parking layout 04/06/2015EDMS:
New parking layout 04/06/2015EDMS:
PARKING 234 parking spots m 2 of parking surface 500+ ml of sidewalk 9 high-rise lighting masts on car park 10 low-rise lighting masts along sidewalk ENTRANCE A 2 automated turnstiles for bikes and pedestrians 2 automated gates and barriers for cars 2 car plate readers Surveillance cameras 1 high-rise lighting masts Technical specification 04/06/2015EDMS:
Phased execution Phase 1 Phase 2 Phase 1’or 2’ 04/06/2015EDMS:
Planning Option 1 – Requiring early supply of automated equipment Start of work Phase 1 & 1’: 6-07 End of work Phase 1: Start of work Phase 2: End of work Phase 1’: End of work Phase 2: Option 2 – If early supply of automated equipment not possible Start of work Phase 1: 6-07 End of work Phase 1: Start of work Phase 2 & 2’: End of work Phase 2’: End of work Phase 2: /06/2015EDMS:
Ex BP station 04/06/ EDMS:
Ex BP station Agreement to use the space as is (not blacktop) 04/06/2015EDMS:
Mobility Centre 04/06/ EDMS:
CERN Mobility Centre Pole échange multimodale Trams, navettes, voitures, vélos Réception voiture location Stations à vélo 04/06/2015EDMS:
Overview 04/06/2015EDMS:
On-going projects 04/06/ EDMS:
On-going projects PolimerLab – CE tenders out, HVAC and EL should be published this week. Bat 311 – CE detailed studies on-going for call for tender as planned. Extension ENH1 - CENF extension – Works on-going as planned. Globe renovation – Globe closed and preparatory works started. Bat 107 – Building closed, final resolutions with previous contractor to be presented at next FC. Being passed new contracts for engineering support. Bat LIU Injectors – CE construction contract passed and works starting next week. Bat – CE tenders out. 04/06/2015EDMS: