ONGOING PROJECT -1-ROB AT PARAPPANANGADI-PROGRESS GRAPH
ONGOING PROJECT-1-PROGRESS PHOTOS-ROB AT PARAPPANANGADI
5 PARAPPANANGADI ROB-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity DescriptionTotal Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done-Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1Pile-calicut Side Pile-NH Side Pile-calicut Side(Railway) Pile-NH Side (Railway) Pile cap-calicut Side Pile cap-NH Side Pile cap-calicut Side (Railway) Pile cap-NH Side (Railway) Pier-Calicut Side Pier-NH Side Pier-Calicut Side (Railway) Pier-NH Side (Railway) Pier Cap-Calicut Side Pier Cap-NH Side Pier Cap-Calicut Side (Railway) Pier Cap-NH Side (Railway) Girder-Calicut Side Girder-NH Side Girder-Calicut Side (Railway) Girder-NH Side (Railway) Deck Slab-Calicut Side Deck Slab-NH Side Deck Slab-Calicut Side (Railway) Deck Slab-NH Side (Railway) Handrails & Kerb-Calicut side100% 0% 10% 0% 26Handrails & KerbNH side100% 0% 27Handrails & Kerb-Calicut side (Railway)0% 28Handrails & KerbNH side (Railway)0% 29RE Wall-Calicutside100% 0% 30RE Wall-NH side100% 0% 31RC Wall-Calicut side100% 0% 32RC Wall-NH side100% 0% 33Road work-WBM-Calicutside100%0%100% 30%0%30% 34Road Work-WBM-NH side100% 0% 35Road work-Calicutside (Railway)0% 36Road Work-NH side (Railway)0% 37Dirt wall AP2100% 0% 38Dirt wall AP1100% 0% 39Painting100% 0% 40Expansion joint Miscellaneous works100% 0%
ONGOING PROJECT -2-ROB AT SULTANPET-PALAKKAD TOWN- PROGRESS GRAPH
ONGOING PROJECT -2-ROB AT SULTANPET-PALAKKAD TOWN- THIRD ARM-PROGRESS GRAPH
ONGOING PROJECT-2-PROGRESS PHOTOS-ROB AT SULTANPET- PALAKKAD TOWN
9 SULTANPET ROB-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity DescriptionTotal Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done-Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1PCC for Raft MOYAN Side PCC for Raft Palakkad side Raft Palakkad Side Raft Moyans Side Pile - Bus Stand side Pile Cap- Bus Stand side Pier- Bus Stand side Pier Palakkad Side Pier Moyans side Pier Cap- Bus Stand side Pier Cap Palakkad Side Pier Cap Moyans side Girder- Bus Stand side Girder-Land Span-Palakkad Side Girder-Land Span-Moyans Side Deck Slab- Bus Stand side Deck Slab-Land Span-Palakkad Side Deck Slab-Land Span-Moyans Side Girder-Railway span Deck Slab-Railway Span Bowstring girder Casting of Bow arch bem Casting of cross girders (RP4-RP5) Casting Bracings-RP4-RP RE/R WALL PALAKKAD SIDE100% 0% 26RE/R WALL MOYAN SCHOOL SIDE100% 0% 27HR/FP/KERB Pkd SIDE100% 0% 28HR/FP/KERB Moyen's SIDE100% 0% 29HR/FP/KERB RAILWAY SPAN100% 0% 30Expansion Joint-Land span BC/PAINTING100%75%25% 0% 32Road works-Moyans side100% 0% 33Road works-Pkd side100% 0%
ONGOING PROJECT -3-ROB AT KOILANDY-PROGRESS GRAPH
ONGOING PROJECT-3-PROGRESS PHOTOS-ROB AT KOILANDY
12 KOILANDY ROB-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity DescriptionTotal Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done-Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1Pile-Muthambi Side Pile-Thamarachery Side Pile-NH Side Pile cap-Muthambi Side Pile cap-Thamarachery Side Pile cap-NH Side Pier-Muthambi Side Pier-Thamarachery Side Pier-NH Side Pier Cap-Muthambi Side Pier Cap-Thamarachery Side Pier Cap-NH Side Girder-Muthambi Side Girder-Thamarachery Side Girder-NH Side Deck Slab-Muthambi Side Deck Slab-Thamarachery Side Deck Slab-NH Side Handrails & Kerb-NH side Handrails & Kerb-Baluchery side Handrails & Kerb-Muthambi side RC Wall-NH side100%90%10% 100% 0% 14RC Wall-Baluchery side100%50% 100%50% 15RCWall-Muthambi side100%0%100% 25%0%25% 16Expansion Joint-NH side Expansion Joint-Baluchery side Expansion Joint-Muthambi side Road work-NH side100%0%100% 0% 20Road Work-Baluchery side100%0%100% 0% 21Road Work-Muthambi side100%0%100% 0%
ONGOING PROJECT -4-ROB AT CHERUVATHUR-PROGRESS GRAPH
ONGOING PROJECT-4-PROGRESS PHOTOS-ROB AT CHERUVATHUR
15 CHERUVATHUR ROB-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity DescriptionTotal Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done-Sep12Delay in Qty in Sep 12 Work Planned for next Month Remarks 1Pile-Cheruvathur side Pile-Padanna side Pilecap-Cheruvathurside Pilecap-Padanna side Pier-Cheruvathur side Pier-Padanna side Piercap-Cheruvathur side Piercap-Padanna side Girders-Cheruvathur side Girder-Padanna Side Deck Slab-Cheruvathur side Deckslab-Padanna Side Handrails on Cheruvathur side100%90%10% 0% Adjacent span to be done 14 Kerb-Cheruvathur side100% 0% 15Handrails on Padanna side100%90%10% 0% Adjacent span to be done 16Kerbs - Padanna side100% 0% 17Handrail on Approch portion-Cheruvathur side100% 0% 100% 0% 18Handrail on Approch portion-Padanna side100% 0% 100% 0% 19Expansion joint-Cheruvathur side Adjacent span,Approach to be done 20Expansion joint-Padanna side Adjacent span,Approach to be done 21RE Panel Erection - Cheruvathur side100% 0% 15% 0% 22Retaining Wall -Cheruvathur side100% 0% 23RE Panel Erection - padanna side100%0%100% 24Retaining Wall Padanna side100% 0% 5% 0% 25Road work Cheruvathur side100%0%100% 30%0%30% 26Road work Padanna side100%0%100% 0%
ONGOING PROJECT -5-ROB AT DEVADHAR-PROGRESS GRAPH
ONGOING PROJECT-5-PROGRESS PHOTOS-ROB AT DEVADHAR
18 DEVDAR ROB-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity DescriptionTotal Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done-Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1Pile-calicut Side Pile-Thirur Side Pile cap-calicut Side Pile cap-Thirur Side Pier-Calicut Side Pier-Thirur Side Pier Cap-Calicut Side Pier Cap-Thirur Side Girder-Calicut Side Girder-Thirur Side Deck Slab-Calicut Side Deck Slab-Thirur Side Handrails -Calicut side Handrails -Thirur side Kerb-Calicut side KerbThirur side RC Wall-Calicut side100%65%35% 0% 16RC Wall-Thirur side100%95%5% 25%20%5% 17Expansion Joint-Calicut side Expansion Joint-Thirur side Road work-Calicutside100%0%100% 0% 20Road Work-Thirur side100%0%100% 0%
ONGOING PROJECT -6-ROB AT THIRUNNAVAYA-PROGRESS GRAPH
ONGOING PROJECT-6-PROGRESS PHOTOS-ROB AT THIRUNNAVAYA
21 THIRUNAVAYA ROB-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity DescriptionTotal Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done-Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1Pile-kanjipura Side30 0 2Pile-kuttipuram Side33 0 3Pile cap-kanjipura Side10 0 4Pile cap-kuttipuram Side11 0 5Pier-kanjipura Side10 0 6Pier-kuttipuram Side11 0 7Pier Cap-kanjipura Side Pier Cap-kuttipuram Side Girder-kanjipura Side Girder-kuttipuram Side Deck Slab-kanjipura Side Deck Slab-kuttipuram Side Handrails on kanjipura side Kerb-kanjipura side Handrails on kuttipuram side Kerb kuttipuram side RC Wall-kanjipura side100%0%100% 18RC Wall-kuttipuram side100%26%74% 19Expansion Joint-kanjipura side Expansion Joint-kuttipuram side120 21Road work-kanjipuraside100%0%100% 22Road Work-kuttipuram side100%0%100%
ONGOING PROJECT -7-ROB AT PONNURUNNI-PROGRESS GRAPH
ONGOING PROJECT-7-PROGRESS PHOTOS-ROB AT PONNURUNNI
24 PONNURUNNI ROB-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity DescriptionTotal Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done- Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1 PILE Palarivattom side(Approach portion) PILE Palarivattom side(railway portion) PILE vytilla side(Approach portion) PILE vytilla side(railway portion) PILE CAP Palarivattom side(Approach portion) PILE CAP Palarivattomside(railway portion) PILE CAP vytilla side(Approach portion) PILE CAP vytilla side(railway portion) PIER Palarivattom side(Approach portion) PIER Palarivattomside(railway portion) PIER Vytilla side(Approach portion) PIER vytilla side(railway portion) PIER CAP Palarivattom side(Approach portion) PIER CAP Palarivattomside(railway portion) PIER CAP Vytilla side(Approach portion) PIER CAP vytilla side(railway portion) GIRDER Palarivattom side(Approach portion) GIRDER Vytilla side(Approach portion) Including Soild slab 19 DECK SLAB Palarivattom side(Approach portion) DECK SLAB Vytilla side(Approach portion) Including Soild slab 21RE Wall Panel RE Wall Panel erection Palarivattam side100%16%84% 0%1 23Pile Load Test on RP Dirt wall Expansion joint Handrail
ONGOING PROJECT -8-ROB AT ANAYARA-PROGRESS GRAPH
ONGOING PROJECT-8-PROGRESS PHOTOS-ROB AT ANAYARA
27 ANAYARA ROB-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity DescriptionTotal Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done-Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1Pile-Pettah Side Pile-Anayara Side Pile cap-Pettah Side Pile cap-Anayara Side Pier-Pettah Side Pier-Anayara Side Pier Cap-Pettah Side Pier Cap-Anayara Side Girder-Pettah Side Girder-Anayara Side Deck Slab-Pettah Side Deck Slab-Anayara Side Handrails & Kerb-Pettahside100%0%100% 0% 14Handrails & KerbAnayara side100%0%100% 0%100% 15RE panel casting100% 0% 16RE Wall-Pettah side100%88%12% 0% 17RE Wall-Anayara side100% 0% 18RC Wall-Pettahside100% 0% 19RC Wall-Anayara side100% 0% 20Expansion Joint-Pettahside100%0%100% 0% 21Expansion Joint-Anayara side100%0%100% 0% 22Road work-Pettah side100%25%75% 0% 23Road Work-Anayara side100%25%75% 0%
ONGOING PROJECT -9-ROB AT KORATTYANGADI-PROGRESS GRAPH
ONGOING PROJECT-9-PROGRESS PHOTOS-ROB AT KORATTYANGADI
30 KORATTYANGADI ROB-PROJECT STATUS REPORT AS ON KORATTY 2012 Si NoActivity Description Total Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done-Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1 Pile (approach portion) Pile (Railway portion) Pile cap (approach portion)550 5 Pile cap (Railway portion)440 7 Pier (approach portion)550 8 Pier (Railway portion)440 9 Pier cap (approach portion) Pier cap (Railway portion) Approach SPAN DECK Railway Span Deck Re wall towards NH side100%95% 5% 16 R0AD WORK100%50% 17Kerb/handrail (approach portion)N.H side100%90%10% 0%10%
ONGOING PROJECT -10-RIVER BRIDGE ACROSS THOOTHAPUZHA CONNECTING EDAPPALAM AND MOORKKANAD-PROGRESS GRAPH
ONGOING PROJECT-10-RIVER BRIDGE ACROSS THOOTHAPUZHA CONNECTING EDAPPALAM AND MOORKKANAD-PROGRESS PHOTOS
33 EDAPPALAM-MORRKKANAD RIVER BRIDGE-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity DescriptionTotal Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done-Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1Pile48 0 2Pilecap11 0 3Pier11 0 4Piercap Girders Deckslab Handrails & footpath slab casting100%0%100% 10Retaining Wall Edapalam side100% 0% 10% 0% 11Retaining Wall Moorkanad side100%25%75% 0%25%-25% 12 Drain Works Moorkanad side100%0%100% 0%100% 13Expansion Joint Road work Edapalam side100%0%100% 15Road work Moorkanad side100%0%100%
ONGOING PROJECT-11-RIVER BRIDGE ACROSS PERIYAR CONNECTING STATIONKADAVU & VALIYAPAZHAMPILLITHURUTHU-PROGRESS GRAPH
ONGOING PROJECT-11-RIVER BRIDGE ACROSS PERIYAR CONNECTING STATIONKADAVU & VALIYAPAZHAMPILLITHURUTHU-PROGRESS PHOTOS
36 STATIONKADAVU RIVER BRIDGE-PROJECT STATUS REPORT AS ON SEPTEMBER 2012 Si NoActivity Description Total Quantity Cumulative progress upto Sep12 Balance work up to Sep 12 Cumulative delay in days from Baseline Work planned for Sep 12 Actual work done- Sep12 Delay in Qty in Sep 12 Work Planned for next Month Remarks 1Pile Pilecap Pier Piercap Girders Deckslab Handrails & footpath slab casting100%0%100% Retaining Wall Paliyam side100%0%100% Retaining Wall Thrissur side100%0%100% Road work Paliyam side100%0%100% Road work Thrissur side100%0%100% 0%
37 THANK YOU