JACKSBORO TO WEST DENTON and WEST LEVEE TO NORWOOD 345-kV PROJECTS April 20, 2004 Transmission Services Operations.

Slides:



Advertisements
Similar presentations
Houston Region Import Capacity Project Planning for Reliable Power.
Advertisements

March 26, 2014 Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting.
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
March 6, 2008 Technical Advisory Committee Luminant Energy & Oncor Tyler Grande Autotransformer Addition and 138 kV Line Upgrade Project Jay Teixeira Manager,
January 6. January 7 January 8 January 9 January 10.
Regional Planning Group Project
Houston Import Evaluation Cross Texas Transmission & Garland Power & Light ERCOT RPG Meeting August 27th, 2013.
Texas Deregulation – A Success Story The ERCOT Market Framework Has Been A Success Implementation  Bilateral Contracts - Participants contract up to 100%
Economic Criteria for Transmission Planning in the ERCOT Region Public Utility Law Seminar DeAnn Walker August 3, 2012.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
Oncor Electric Delivery Company LLC TOGETHER WE DELIVER ODESSA UPDATE Jan 22, 2013 Presentation to ERCOT Regional Planning Group Austin, TX Mike Juricek.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
January 5, 2012 TAC Cross Valley 345 kV Project Jeff Billo Manager, Mid-Term Planning.
BRAZOS ELECTRIC COOPERATIVE Dobbin 345 Project David Albers, P.E. Manager – System Planning.
Valley Import Overview Jeff Billo Regional Planning Group Meeting July 22, 2014 Preliminary1.
The Status Of The Electric Grid In ERCOT The Electric Reliability Council Of Texas Sam R. Jones, P.E. ERCOT – Retired As a retiree of ERCOT this presentation.
Texas Lignite Industry. Texas Lignite  Because >95% of lignite mining operations in Texas are in support of electric generation…..whatever impacts the.
Transmission planning in Vermont Past, present and future Docket 7081 workshop By Dean LaForest 9/19/05.
JACKSBORO TO WEST DENTON 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
Warren Lasher Director, System Planning October 4, 2014 Our Energy Future.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
10/03/ Report on Existing and Potential Electric System Constraints and Needs Within the ERCOT Region October 3, 2002.
Arizona ACC Biennial Transmission Assessment Navajo Transmission Project Update May 22, 2008 Presentation by Ben Hoisington Project Administrator, DPA.
April 16, 2010 RPG Meeting ERCOT Five-Year Transmission Plan Update Jeff Billo.
Rocky Mountain Power Five Year Study Findings and Kick Off Meeting December 2013.
RPG Meeting Five Year Plan Extension Brad Schwarz.
Texas Wind Energy American Meteorological Society Summer Community Meeting – Norman Oklahoma Henry Durrwachter, P.E. August 12, 2009.
LAREDO PLANT RMR EXIT STRATEGY Presentation to Board of Directors March 16, 2004 Transmission Services Operations.
Topics  Renewable Energy  Electricity prices and retail competition  TXU Acquisition  Legislative Session.
June 19, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
Kurten Switch Project ERCOT Board of Directors Bill Bojorquez System Planning December 13, 2005.
October 16, 2009 RPG Meeting ERCOT 2009 Five-Year Transmission Plan Update Jeff Billo.
TPIT using Model On Demand Jay Teixeira Manager Model Administration Regional Planning Group 5/21/13.
POWER SYSTEM PLANNING CHARTER AND PROCESSES UPDATES Presentation to TAC Sept 9, 2004 Transmission Services Ken Donohoo, Manager of System Planning
Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting.
WEST LEVEE TO NORWOOD 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
April 16, 2010 RPG Meeting Lamesa Area Upgrades ERCOT Independent Review Jeff Billo.
LAREDO RMR EXIT STRATEGY Presentation to Technical Advisory Committee March 4, 2004 Transmission Services Operations.
Jeff Billo Manager, ERCOT Transmission Planning Kenedy to Nixon to Seguin Line Upgrade Project Regional Planning Group (RPG) Review; ERCOT Independent.
AEPSC Live Oak County Transmission Project – ERCOT Independent Review TAC September 24, 2015.
2011 Calendar Important Dates/Events/Homework. SunSatFriThursWedTuesMon January
February 13, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
LCRA TSC/ CPS Energy Transmission System Addition Regional Planning Group Project Jeff Billo Sr. Manager, Transmission Planning TAC ERCOT Public March.
Criteria for Economic Transmission Additions Bill Bojorquez May 4, 2006.
RPG: September 24, Long-Term System Assessment Introduction Jeff Billo, Manager, Transmission Planning September 2013 Regional Planning Group.
Coordinated Planning Concept (For Discussion Only) revised 11/30/04 07/01/04.
Jeff Billo Manager, Transmission Planning
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
OPSTF – Issue 7 Long-term unavailability of autotransformers.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
Oncor Transmission Service Provider Kenneth A. Donohoo Director – System Planning, Distribution and Transmission Oncor Electric Delivery Co LLC
POWER SYSTEM PLANNING CHARTER AND PROCESSES Presentation to TAC May 6, 2004 Transmission Services Ken Donohoo, Manager of System Planning Dan Woodfin,
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
Transmission Services Report: North and West RPG Projects Bill Bojorquez TAC July 7, 2005.
June 26, 2008 Technical Advisory Committee American Electric Power Service Corporation Presidio Area Reliability Improvements Project James Teixeira Manager,
LINE 69H REBUILD AND CONVERSION PROJECT ERCOT Regional Planning Group April 21,2016.
03/06/2008 TAC CREZ Transmission Optimization (CTO) Study Update Dan Woodfin Director, System Planning.
4/16/2010 Regional Planning Group Meeting Long-Term Planning Study of the ERCOT Interconnection Warren Lasher Manager, System Assessment.
Houston Import Project – ERCOT Independent Review
Houston Area Constraint Mitigation Project ERCOT Board of Directors March 15, 2005.
Nacogdoches to Lufkin SS 345 kV Line Project
ONCOR Electric Delivery/ Texas New Mexico Power East Bell County to TNP One 345 kV Line Upgrade Projects Board of Directors July 17, 2007.
Description of Project
Barrilla Junction Area Transmission Improvements Project
Compliance Report to ERCOT BOD December 2006
SYSTEM PLANNING THE KEY TO RELIABILITY AND A LIQUID ELECTRIC MARKET
Warren Lasher Manager, Long-Term Planning and Policy
Modifications to Planning Charter
2015 January February March April May June July August September
Presentation transcript:

JACKSBORO TO WEST DENTON and WEST LEVEE TO NORWOOD 345-kV PROJECTS April 20, 2004 Transmission Services Operations

© ERCOT 20043/31/2004 Goals and Objectives Maintain reliable service to customers ERCOT Planning Criteria NERC Planning Standards and Guidelines Good Utility Practice Support load growth in DFW Metroplex Support increased imports from 345 kV system Currently in compliance with planning criteria requirements but will not be in 2006 without projects

© ERCOT 20043/31/2004 Scope of Projects Build a double-circuit 345 kV line from Oncor’s Jacksboro Switching Station to TMPA’s West Denton 345/138-kV Switching Station Approximately 50 miles kcmil ACSR conductor with one circuit in place Estimated cost: $46.5 Million (TCOS: $7.7 M) Build a double-circuit 345-kV transmission line from West Levee Switching Station to Norwood Switching Station (within Oncor) Approximately 7 miles kcmil ACSR conductor with one circuit in place Estimated Cost: $10.2 Million (TCOS: $1.7 M)

© ERCOT 20043/31/2004 Open Process North Regional Planning Group analysis and input Jacksboro to West Denton Project scope sent to North Regional Planning group on August 27, 2003 West Leeve to Norwood Project scope sent to North Regional Planning group on October 22, 2003 Questions and comments were received and addressed North RPG open meeting held on December 11, 2003 ERCOT independent analysis sent to RPG Jacksboro to West Denton on January 21, 2004 West Leeve to Norwood on February 27, 2004 ERCOT acceptance letter sent to RPG Jacksboro to West Denton on February 25, 2004 West Leeve to Norwood on March 1, 2004 No dissenting comments received

© ERCOT 20043/31/2004 Independent Analysis ERCOT Staff has performed independent analysis using in-house expertise, models and software tools of these projects Thermal studies Using Shaw PSS/E & MUST

© ERCOT 20043/31/2004 North Texas

© ERCOT 20043/31/2004 Proposed Project

© ERCOT 20043/31/2004 Alternative 1

© ERCOT 20043/31/2004 Denton/DFW Area Denton County Load – 1,600 MW in 2003 Growth to 1,830 MW in 2008 (2.8%/yr) DFW Load – Denton, Tarrant, Dallas, Collin – 17,850 MW in 2003 Growth to 20,100 MW in 2008 (2.4%/yr) Generation limits due to emission reductions mandated by TCEQ Further reduction of generation by TXU energy for economic operation No new generation development in area

© ERCOT 20043/31/2004 Central and South Dallas

© ERCOT 20043/31/2004 Project Close Up

© ERCOT 20043/31/2004 Dallas/DFW Area Dallas County Load – 8,600 MW in 2003 Growth to 9,550 MW in 2008 (2.1%/yr) DFW Load – Denton, Tarrant, Dallas, Collin – 17,850 MW in 2003 Growth to 20,100 MW in 2008 (2.4%/yr) Generation limits due to emission reductions mandated by TCEQ Further reduction of generation by TXU energy for economic operation No new generation development in area

© ERCOT 20043/31/2004 Recommendation Endorse the need for the Jacksboro to West Denton and the West Levee to Norwood 345-kV projects

© ERCOT 20043/31/2004 Questions Due to its very nature, transmission planning is a continuous process and is constantly changing due to the addition (or elimination) of plans for new generation, transmission facilities, equipment, or loads. Benefits of good planning are not realized until transmission projects are completed and placed in service.