The Building 180 Cryogenic infrastructure water cooling system Stefano Moccia, EN-CV Coordination meeting 26/09/14
Raw water Raw or Demi water Demi water EquipmentLocationP [kVA] M [m 3 3 bars Required ΔT (K) Filtration degree (μm) Compressor for cold boxBat Compressor for pre-cooler #1Bat Compressor for pre-cooler #2Bat Pump for purgeBat Pump for insulation vacuum, pre- pumping Bat Power Converters 500 A (3 total)Bat Power Converters 600 A (6 total)Bat Energy Extraction switchBat Total ~1260 Users Requirements
Bat 279 Bat 180 Raw water production Raw water distribution Demi water production Demi water distribution System Layout and WBS WBS 1.1 Tendering procedure 1.2 Raw water production (EN-CV, EN-EL) 1.3 Raw water distribution (EN-CV, EN-EL) 1.4 Demineralized water production (EN-CV, EN-EL) 1.5 Demineralized water distribution (EN-CV, EN-EL) 1.6 Controls (EN-ICE) 1.7 Civil engineering (GS-SE-CEB)
Raw water production Cooling tower Skid mounted pumping system Interface with the raw water distribution.
Raw water distribution EN-CV limit of supply Piping to the demi water skid heat exchanger
Demi water production Interface with the demi water distribution. Demi water distribution At the present time, the demi water distribution details are not defined yet. The integration effort is ongoing.
Procurement and Planning Full blown CERN tender procedure for Raw water production, distribution and Demi water production. Market Survey dispatched mid September, – MS-4047, EDMS N o : IT to be dispatched by mid November, 2014 The contract is foreseen to be awarded in April 2015 after Finance Committee approval in March Demi water distribution to be done within the framework of EN-CV small jobs contract or via an amendment of the main contract. System fully operational by December 2015.
Detailed users requirements Equipment name Location (Building number) Max Power (KW) dissipated in water Required min Water flow [l/min] Required Delta T (K) Max. Supply Temp. [°C] Water quality (raw or demi) Min. filtration degree required (microns)CommentsMan in charge Required by (date) Compressor for cold box Bat Raw25 A. PerinSep-14 Compressor for pre-cooler #1Bat Raw25 A. PerinSep-14 Compressor for pre-cooler #2Bat Raw25 A. PerinSep-14 Pump for purgeBat Raw or Demi25 loop to be decidedA. PerinSep-14 Pump for insulation vacuum, pre- pumpingBat Raw or Demi25 loop to be decidedA. PerinSep-14 Power converter 500 A # 1Bat Demi25 H. ThiesenSep-14 Power converter 500 A # 2Bat Demi25 H. ThiesenSep-14 Power converter 500 A # 3Bat Demi25 H. ThiesenSep-14 Power converter 600 A # 1Bat Demi25 H. ThiesenSep-14 Power converter 600 A # 2Bat Demi25 H. ThiesenSep-14 Power converter 600 A # 3Bat Demi25 H. ThiesenSep-14 Power converter 600 A # 4Bat Demi25 H. ThiesenSep-14 Power converter 600 A # 5Bat Demi25 H. ThiesenSep-14 Power converter 600 A # 6Bat Demi25 H. ThiesenSep-14 Energy Extraction switchBat Demi25 K. Dahlerup- PetersenSep-14