F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF, TF, & Trim Coil Supports (WBS-15) Core Base Support Structure (WBS-17) F. Dahlgren NCSX Coil.

Slides:



Advertisements
Similar presentations
NCSX Machine Platform FDR June 15, 2005 Erik D. Perry.
Advertisements

MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Far Detector Assembly Block Pivot Table Design Review WBS Dave Pushka April 2 nd 2008.
FDR Station 3 lift fixture, laser screens and brackets T. Brown and L. Morris with analysis support from A. Brooks December 3, 2007.
NCSX Vacuum Vessel Overview Paul Goranson WBS 12 Manager Vacuum Vessel Manufacturing Study Kickoff meeting April 29, 2003.
NCSX Office of Science Project Review Cryostat, WBS171 August 15-17, 2007 NCSX Fabrication, Operations, and Maintenance Division Engineering Department.
NCSX NCSX Planar Coil "ASIPP" Presentation 1 December 8-10, 2005 Michael Kalish NCSX TF and PF Coils.
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Progress Report V. Kashikhin for Superconducting Magnet Team.
PDR - NCSX Base Support Structure 6 Mar F.Dahlgren J.Rushinski T.Cruickshank H.M. Fan 1.
SC Project Review of NCSX, April 8-10, 2008 NSCX Poloidal Field Coils Michael Kalish.
1 Stage 3 Peer Review October 26, 2006 T. Brown. 2 Field Period Assembly (FPA) 1.Make sure the requirements for the tooling is well defined (including.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 5.1 Grid Box Design 1 GLAST Large Area Telescope:
NSTX TF Flag Joint Design Review INTRODUCTION C Neumeyer 8/7/3.
WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/ SBS DOE Review.
1 Dimensional Control for the National Compact Stellarator Experiment R. Ellis, A. Brooks, T. Brown, W. Reiersen, S. Raftopoulos, B. Stratton Presented.
1 Stage 3 Peer Review October 26, 2006 T. Brown. 2 Field Period Assembly (FPA) – Stage 3 1.Make sure the requirements for the tooling is well defined.
1 WBS 1 Design Analysis Status NCSX Analysis Meeting Dec 3, 2003.
Modular Coil Assembly Bolted Joint PDR 2/22/07. Objectives The review objectives include... Define the location of additional inboard bolts Finalize the.
SC Project Review of NCSX, April 8-10, 2008 NCSX Coil Services P.L. Goranson Work Package 161.
Metrology Milestones Metrology Task Force –Vacuum vessel manufacture - P. Goranson –Mod. Coil Form manufacture - D. Williamson –Mod. Coil winding- S. Raftopoulos.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62)
1 MC Assembly over the VV FPA Station 3 FDR Review July 17, 2007 T. Brown.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
SC Project Review of NCSX, April 8-10, 2008 NCSX Fueling and Vacuum Pumping Systems W. Blanchard WBS 21 and 22 Manager.
NCSX NCSX TF Coil Procurement 1 February 3, 2006 Michael Kalish NCSX TF Coil Procurement.
NSTX NSTX Center Stack Upgrade Ensure fatigue resistant Welds: minimum # of locations shown, could be more. Various Weld Reinforcements & Hardware Replacement.
Conceptual Design Requirements for FIRE John A. Schmidt FIRE PVR March 31, 2004.
ITER In-Vessel Coils (IVC) Interim Design Review Thermal Structural FEA of Feeders A Brooks July 27, 2010 July 26-28, 20101ITER_D_353BL2.
SC Project Review of NCSX, April 8-10, 2008 Job 1260 Neutral Beam Transition Duct (NBTD) P. L. Goranson.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
Nonlinear Analyses of Modular Coils and Shell structure for Cooldown and Modular Coil EM Loads Part 2 – Results of Clamp Assembly, Wing Bags, Poloidal.
NCSX Operation of the C1 Modular Coil in the Coil Test Facility Peer Review June1, 2006 NCSX.
NCSX David Johnson August 18, 2004 Discussion of Co-Wound Flux Loops.
Peer Review NSTX TF Hub Assembly Friction Coating C Neumeyer 10/27/04 Requirements Testing Calculation Update Implementation.
RHIC 56 MHz HOM Damper Fundamental Damper Fundamental Power Coupler Pick-ups S. Bellavia January 19 th, 2010.
FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.
TVAC Trolley Design Review1 GLAST LAT Project8 September 2005 TVAC Trolley Design Status Review 8 September 2005 TVAC Trolley Design Status Review 8 September.
IRMOS Diffraction Grating Integral Tab Design  Performance of an optical system is highly sensitive to the surface distortion of the optics in the system.
SCH Controls Readiness Review- Cryostat Nov 4-5, 2015 Kurt Cantrell.
SBS Magnet and Infrastructure Status Robin Wines July 2015.
1 NCSX WBS HANDLING/SUPPORT UPDATE PLG 7/23/03 STATUS Study is for 120 degree VVSA field period assembly. Vessel Installation Support Concept.
1 Field Period Assembly Office of Science Project Review Princeton Plasma Physics Laboratory Princeton, NJ November 2, 2005 T. Brown Princeton Plasma Physics.
NCSX NCSX Trim Coil Peer Review 11/6/07 1 Tom Brown Art Brooks Raki Ramakrishnan Mike Kalish NCSX Trim Coil Peer Review.
Shear Test Assembly update
1 MC Assembly over the VV FPA Station 3 FDR Review July 13, 2007 T. Brown.
SC Project Review of NCSX, April 8-10, 2008 NCSX Field Period Assembly Mike Viola NCSX Field Period Assembly Manager NCSX Project Review April 8-10, 2008.
LAT Transport Container1 GLAST LAT Project8 September 2005 LAT Transport Container Design Review 8 September 2005 LAT Transport Container Design Review.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62) Manager.
NCSX NCSX Preliminary Design Review1 Conventional Coils and Structure Phil Heitzenroeder, Len Myatt, and Mike Viola for the NCSX Engineering Team.
SC Project Review of NCSX, April 8-10, 2008 NCSX Machine Assembly E. D. Perry.
NCSX November 18-20, 2003NCSX Performance Baseline ReviewMichael Viola 1 NCSX Vacuum Vessel R&D, Risk Management and Manufacture Mike Viola, Phil Heitzenroeder,
1 Assembly Tooling PU Workshop on NCSX Cost & Schedule Princeton Plasma Physics Laboratory Princeton, NJ Mar 1-4, 2007 T. Brown Princeton Plasma Physics.
AWB Dimensional Control Requirements for the Modular Coils and TF coils Field Period Assembly Peer Review October 11-12, 2006 Art Brooks.
NCSX VACUUM VESSEL PL Goranson Final Design Review November 17, 2005 Man Access Port /Lateral Supports NCSX.
Field Period Assembly Wayne Reiersen SC Project Review PPPL May 2006.
Nonlinear Analyses of Modular Coils and Shell structure for Coil Cool-down and EM Loads Part 1 – Results of Shell Structure and Modular Coils H.M. Fan.
1 FPA Stage 2 Peer Review May 12, 2006 T. Brown. 2 FPA Stage 2 Status Summary of Stage 2 activities Review current design status Review schedule details.
A View of NCSX Structural System and Load Path for the Base Support Structure.
NCSX 21 March 2003 Reiersen - 1 PDR Preparations Wayne Reiersen NCSX Engineering Meeting 21 March 2003.
NCSX Strykowsky 1Cost and Schedule Rebaseline April 25, 2005 NCSX Project Re-baseline Review April 25, 2005 Cost and Schedule Ron Strykowsky.
NCSX VVSA / MCWF FDR A Systems Engineering Perspective Wayne Reiersen Bob Simmons NCSX VVSA / MCWF FDR May 19-20, 2004 PPPL.
1 WBS 1 Preparation for FDRs NCSX WBS 1 Engineering Meeting March 17, 2003 What establishes the plan? What are near term deliverables? How will we status.
1 VV Support Fixture FPA Stage 1 PDR Review August 10, 2005 T. Brown.
SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile NCSX Startup (WBS 85) C.A.Gentile NCSX CD-4 Startup.
Panda Solenoid Content Interface Box Cold Mass Layout Cooling Lines
ProtoDUNE – DSS Installation, Alignment and QA
SNS PPU Cryomodule Thermal Shield
SNS PPU Cryomodule Vacuum Vessel
SNS PPU Cryomodule Space Frame
SNS PPU Cryomodule Space Frame
Presentation transcript:

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF, TF, & Trim Coil Supports (WBS-15) Core Base Support Structure (WBS-17) F. Dahlgren NCSX Coil & Core base support structures

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 Requirements: PF, TF, Trim Coil Supports The coil support structure provides the means for accurately locating and supporting the TF, PF, & Trim coils. It must provide adequate support for the EM loads arising from the coil operational scenarios and fault conditions. It must have sufficient compliance to accommodate cooldown from room temperature to 77 deg.K It must be sufficiently rigid to limit coil deflections to acceptable values per field error criteria. It must have a relative magnetic permeability less than 1.02 It must limit eddy currents to effectively limit field errors at the plasma boundary. It must meet the NCSX seismic & Structural Design Criteria.

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 Requirements: Base Support Structure Functional requirements: Provides the gravity load path from the NCSX core to the test cell floor. It must not exceed the maximum test cell floor loading of 4,500 lbs/sq.ft. It must have a relative magnetic permeability less than 1.05 It must meet the NCSX Structural Design & Seismic Criteria. It must provide support & clearance for the three period assembly tooling.

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 Interfaces PF,TF, & Trim Coil Supports The coil supports interface with the MCWF shell which provides the load path to react all coil EM and gravity loads. It will also interface with the mounting hardware for supporting the coil buswork, cryogen lines & cryostat. PF5 PF6 TF Coils MCWF Base Supports Assembly cart

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 Interfaces PF5 & 6 support brackets are cantileverd off the TF outer brackets PF5 PF6

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 Interfaces The interface between the MCWF and Base Support columns Spherical Bearings provide translational connections and avoid introduction of rotational moments on the MCWF shell. Low friction PTFE sheets provide a low compliance radial interface to allow for differential thermal contraction from room temperature base supports to 77 K core. TF Coil bracket & clamp interface PF4 Coil bracket & clamp interface Lateral TF coil clamp

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 Interfaces Base Support Structure The base support structure interfaces with the test cell floor, and TF support brackets. It also provides the mounting pads for the three period assembly fixtures. Mounting pads for 3-period assembly cart rails Test cell floor psf) Spherical bearing Housings

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 Design Status PF,TF, & Trim Coil Supports Peer review held on 01/18/07 PDR held on 07/20/07 FDR scheduled for 06/16/08 Pro-E design integration complete. Preliminary drawings issued for review. Minor revisions being implemented to accommodate trim coil support mounting hardware. Design in final detailing awaiting interface information for buswork, cryogen lines, and cryostat mounting hardware. FEA modeling utilizing a single period fully integrated model is complete. FEA analysis of various EM and fault loading conditions is underway (~ 30% complete) with the fully integrated FEA model.

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 Design Status Base Support Structure Peer review held on 01/18/07 PDR held on 03/06/08 FDR scheduled for 04/30/08 Pro-E design integration complete. Preliminary drawings issued for review. Minor revision to accommodate cryostat interface underway. FEA modeling (w/testcell floor & structure) complete. FEA analysis complete.

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 Procurement Plans PF,TF, & Trim Coil Supports Current plan for a fixed price subcontract. At least two potential vendors have been identified and budgetary estimates have been received. RFQ & CSPEC are being prepared, with a projected procurement cycle of 6 weeks starting mid-July ‘08 (subsequent to FDR). Base Support Structure Procure main columns & beams from Stainless Structurals, LLC (~ 13 weeks) Fabricate parts in-house (welding, drilling, & assembly).

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 Cost & Schedule - Coil Supports PF,TF, & Trim Coil Supports - Design PF,TF, & Trim Coil Supports - Fabrication/Procurement Total: 1,439k$ (FY’09)

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 Cost & Schedule - Base Support Structure Base Support Structure - Design Base Support Structure - Fabrication Total: k$ (FY’09)

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 Risks & Mitigation PF,TF, & Trim Coil Supports & Base Support Structure Both these jobs are comprised of conventional weldments and bolted assemblies. As such they are classified as relatively low risk components with minimal probability of cost escalation or scheduler delay associated with their procurement and fabrication. Risk: The main source of cost escalation would be tied to increased commodity prices for Nickel and Molybdenum and the weakening value of US dollar vs. the Euro. Mitigation: Expedite procurement of stainless structurals and Inconel hardware. US Dollar vs. Euro Nickel Price Since January

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 Backup slides

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 Strip heaters (4 per column) will be used to maintain R.T. (40 to 60 F) of columns

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 Bottom surface slides on Teflon sheet

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 Inner TF coil mtg. brkts. Outer TF Coil mtg. brkts. PF4 Coil Mtg. off inner TF brkts.

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF Coils are shimmed & clamped to the support brackets PF5&6 are shimmed & clamped. Brackets are cantilevered off the outer TF bracket assembly. All bolted Joints on bracket bracing are now welded.

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 Trim Coils are shimmed & clamped to the support brackets Trim coils mount to PF5 &6 cantilevered bracket assemblies. Vertical channels provide additional support between the top and bottom brackets. Inbd.Trim coils mount to TF-bracket assemblies.

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF-TF Coil Supports -Cost estimate breakdown

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF-TF Coil Supports -Cost estimate breakdown -con’t. Supplemental parts Inner & Outer TF Lateral Pre-load: $125,876

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF-TF Coil Supports -Cost estimate breakdown -con’t.

F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF-TF Coil Supports -Cost estimate breakdown -con’t. Cost estimates are based primarily on budgetary quotes from prospective vendors: