CVE 4070 Construction Engineering Risk Management Prof. Ralph V. Locurcio, PE.

Slides:



Advertisements
Similar presentations
1 CLIENT CONSULTANT AGREEMENT. 2 Negotiations Types of Consulting Contracts Standard Form of Contract Form of Contract General Conditions Special Conditions.
Advertisements

Managing Risk CHAPTER SEVEN Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Museum Presentation Intermuseum Conservation Association.
A Joint Code of Practice Objectives and Summary Presentation
THE HELP PROCESS. Professional medical equipment project management is the systematic, knowledgeable process through which all items of capital equipment.
CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension.
1. Among the most important advisors to a construction firm are: –Professional surety bond producer –Knowledgeable construction/surety attorney –Construction-oriented.
Design-Build: RISKS OR REWARDS for the Consulting Engineer?
PROJECT RISK MANAGEMENT
CON 4003 CVE 4073/5073 The Estimating Process Prof. Ralph V. Locurcio, PE.
Chapter 14 Schedule Risk Management Dr. Ayham Jaaron Second Semester 2010/2011.
DPW General Conditions Articles 32 through 37. Articles Covered Today  32 Owner’s Right to Withhold Payment  33 Owner’s Right to Stop Work and Terminate.
Risk Analysis & Management. Phases Initial Risk Assessment Risk Analysis Risk Management and Mitigation.
Facilities Institute July , 2012 Houston, Texas Click to edit Master title style
Chapter 7: Managing Risk
Project Cost Management Estimation Budget Cost Control
Managing Project Risk.
Performance Monitoring All All Contracts require basic monitoring once awarded. The Goal of contract monitoring is to ensure that the contract is satisfactorily.
Managing Risk to Reduce Construction Claims (And Improve Project Success) Presented by Laurie Dennis, PE, CVS-Life, FSAVE.
Systemise your compliance management Peter Scott Consulting
Project Risk Management. Learning Objectives  Understand what risk is and the importance of good project risk management.  Identify project risks, describe.
Construction Engineering 221 Contracts & Contractor Procurement.
Construction Engineering 221 Cost Estimating and Bidding.
Don Cole Risk Assessment and Mitigation Project Management for ARA Engineers and Scientists.
Syed M. Ahmed, Ph.D. Department of Construction Management Risk Management in Construction Syed M. Ahmed, Ph.D. Department of Construction Management Florida.
CVE 1000 Construction Engineering The Project Delivery System Prof. Ralph V. Locurcio, PE.
Construction: Legal Issues. Legal Issues In the Bidding Process Timing of various activities has legal implications. During the bidding process: –A bid.
Contract Pricing Methods Ch 2. Lump Sum –Contractor bids 1 price for entire project –Estimate needs to be detailed –Design needs to be finished before.
Presentation to SSC Procurement Benchmarking Committee
Resource Planning & Management Associates, LLC. Project Management, Reporting, and Controls Resource Planning & Management Associates, LLC.
Managing Risk. Objectives  To Describe Risk Management concepts and techniques  To calculate and analyze a project using Probability of completion 
Risk Management - the process of identifying and controlling hazards to protect the force.  It’s five steps represent a logical thought process from.
CONTROLLING TIME. ”Remember that time is money” Benjamin Franklin 1748.
Introduction Time Quality Cost Project Constraints Success Introduction.
CVE 5074 Leading Construction Operations TEAM LEADERSHIP PART VII – RISK MANAGEMENT.
CON 2001 & CVE 4070 Construction Methods & Engineering L-3 Construction Contracts & Controls Prof. Ralph V. Locurcio, PE.
Compensation events and claims Presented by Prof. Khem Dallakoti.
Delay In Construction Project In West Bank. Outline:  Background.  Research objective & methods.  Important factors that cause time and cost overrun.
Foundations of Technology.  To familiarize students with the function, applications, and requirements of construction management.
CVE 4070 Construction Engineering Test-2 & Review Prof. Ralph V. Locurcio, PE.
Risk Assignment in The Delivery of a Project  RISK! –Construction projects have lot of it –Contractors manage it –Owners pay for it.
Construction Cost Estimating Class #2: The Estimating Process Prof. Ralph V. Locurcio, PE.
King Fahd University of Petroleum & Minerals
CVE 4070 Construction Engineering Shop Drawings Quality Control
The Natural Habitat of Brevard The Stormwater Management System A Private Community in Rockledge, FL Prepared for: Mr. Fran Lemieux.
Risk Management for Business
CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE.
CVE 4070 Construction Engineering Value Engineering Prof. Ralph V. Locurcio, PE.
CON 4003 CVE 4073/5073 Construction Cost Estimating Class #2: The Estimating Process Prof. Ralph V. Locurcio, PE.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
DISASTER PLANNING LESSONS LEARNED September 16, 2014 Carol Musumeci, Risk Manager, Brookfield Properties Jim Boccher, VP Commercial Disaster Restoration,
Ch 10 - Risk Management Learning Objectives You should be able to: List and describe risk management processes, inputs, outputs, and tools List and describe.
Managing Risk CHAPTER SEVEN Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Defending dignity. Fighting poverty. Managing Risk in Shelter Programming.
RISK MANAGEMENT YULVI. Introduction Time Quality Cost Project Constraints Success Introduction.
Introduction to Project Management Chapter 9 Managing Project Risk
Risk Management Phase Risk management Assessment, tracking and control – Tools: Risk Hierarchical modeling: Risk breakdown structures Risk matrixes Contingency.
CON 2001 & CVE 4070 Construction Engineering Risk Management Prof. Ralph V. Locurcio, PE.
CVE 4070 Construction Engineering Course Review Prof. Ralph V. Locurcio, PE.
SCOPE DEFINITION,VERIFICATION AND CONTROL Ashima Wadhwa.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
CVE 4070 Construction Engineering HW #6 review Test-2 & Review Prof. Ralph V. Locurcio, PE.
Presented by: Jane Bachynski March 1, 2016 Avoidance and Management of Construction Claims – Fact or Fiction?
PRE-PLANNING FOR CONSTRUCTION PROJECTS. OVERVIEW ASSESSING OWNER CAPABILITIES ANALYSIS OF RESOURCES REGULATORY REQUIREMENTS SITE DEVELOPMENT REVIEWING.
APARTMENT BLOCKS – DEALING WITH DEFECTS
RISK ASSESSMENT TOOL PREVIEW
Construction Projects
Chapter 34 Risk Management
Directed Change Constructive Change
TOTAL COST CONTROL ON CONSTRUCTION PROJECTS
Presentation transcript:

CVE 4070 Construction Engineering Risk Management Prof. Ralph V. Locurcio, PE

Views of risk taking…

What is risk???  An outcome different from what you expected or estimated…  Or… different from what you bid!

Sources of risk in construction…  Construction operations are hazardous  Labor capacity, capability, competence…  Subsurface conditions; physical factors  Contractual provisions; timing, LDs…  Economic conditions; prices, labor…  Political & public; new laws, opposition

Basic premise…  All risks accrue to the owner unless assigned by contract to another party  In assigning risk to another they must be (a) able to assess the risk fairly, (b) competent to do the task, and (c) result in a better solution

Risk allocation… at start Owner DesignerBuilder Not yet involved

Risk allocation… traditional Owner DesignerBuilder

Risk allocation… design-build Owner Designer+ Builder

Risk Management Tools  Best Value procurements  Two stage bid process  Contractor helps finalize design  Incorporates VE  Risk Management  Risk identification  Analysis  Response

Pareto Principle  80/20 rule…  States that 80% of the value comes from 20% of the activities.  Therefore, we need a method to focus on the 20% of the activities that have the most influence on the outcomes.  And… we should avoid the 80% of activities that produce little gain

Best Value Process Understand Client Requirements & Intent Brainstorm Possible Areas for Adding Value Find & Include Experts in Key Areas Develop Options With Pros & Cons ID Preferred Solution & Obtain Needed Design Info Present to Exec Team For Decision Preliminary Design Detailed Design Development Plans & Specs Final Review By Exec Team Final Approval By Client Construction Contractor

Risk identification  Identify areas of risk intensity 1.Buildability, logistics, health & safety 2.Environmental, permits 3.Cost environment  Develop risk registers 1.Catalog all risk factors 2.Assign responsibility to team members

Risk analysis  Use decision & simulation theory  Quantify maximum effect of each risk  Identify probability of occurrence  Determine economic impact of each  Determine impact of combinations

Risk response  Plan mitigation strategies  Specific action to be taken  Avoidance, sharing, protection, etc.  Accountable team member  Account for inter-relationships  Account for multiple risk scenarios

Construction Risk Management Avoidance Retention Insurance Education & Training Exemption Clauses Risk sharing Protection Clauses Retention Money Liquidated Damages Rescind contract Contingencies

Basic risk management-1…  Build a Risk Allocation Matrix  Identify all potential risk of loss  Assign to Owner, Contractor or Designer  Quantify your potential loss  Develop a risk management strategy

Basic risk management-2  Management strategies…  Avoid the potential loss  Transfer the risk  Share risk with another firm  Mitigate the potential for loss  Recover any unavoidable loss Claim Insurance Litigation

Basic risk management-3  Keys to allocation of risk…  Must be a reward for any risk assigned  Asignee must be able to control risk  Must produce “best” solution  Must have financial capability  Must follow terms assigned

Risk Management Strategies  Avoidance  Transfer or Sharing  Mitigation  Insurance  Recovery

Avoidance…  Careful estimating & bidding  Study the contract terms  Study the owner’s style & record  Study limits of insurance  Prior planning for construction  Examine the plans, specs & conditions  Examine the contract requirements  Examine the site for unknowns & hazards  Examine each process & plan your method

Transfer or sharing…  Reduce source & size of risk  Use the contract terms  General conditions  Plans & specs  Negotiate new terms  May not work with government  Change strategic approach  Merger or joint venture with another firm  Hire subcontractor for high risk work  Purchase additional insurance

Mitigation…  Good planning & communication  Quality control processes  Use/acquire the right skills  Use/acquire the right equipment  Use your experience wisely  Act promptly if the unexpected occurs

Insurance…  Covers unexpected situations  Situations beyond your control  Your track record is important  Cost is a factor  Do not overuse

Recovery…  Read the contract  Good record keeping… especially impacts  Follow correct procedures  Demonstrate mitigation efforts  Make a convincing presentation  Attempt settlement at lowest level  Seek legal help

Cost recovery 101 (a)…  Detailed Work Breakdown Structure (WBS) for estimating  List & code each activity & duration  Establish start & finish dates & labor hours  List materials required & procurement lead  Labor hours for shop drawings & submittals  Have accounting code for each of above

Cost recovery 101 (b)…  Develop change/claim spreadsheet  Use bid data as base line  List all estimated activities & costs in a WBS  Calculate “actual” duration & costs for WBS  Establish % triggers to identify problems  Notify owner’s rep immediately of problems

Cost recovery 101 (c)…  Use data to analyze source of problem  Defective plans & specs  Differing site conditions  Interruption of work flow  Unusual weather conditions  Delay in receiving EI or submittal response  Problems with labor  Bad bid

Cost recovery 101 (d)…  Read the contract  Begin mitigation immediately to minimize loss  Stay within contractor’s authority  Determine risk allocation for each problem  Comply with all notification requirements  Request contract change when required  Establish new activity code for all added work  Track cost of new work  Quantify delay to other work

Pyramid Cost Estimate-1… =SUM(E8/F8+G8*E8+H8* E8)*B8 =SUM((E8/F8*I8)+(G8*E8*J8+10)+(H8*E8*K8+ 10))B8 Labor CostConst Laborers(L)Labor Rate Time (Note1)($/day)Labor Days S/ U Man- days L/da yProd Sup erMgtLSMCost Planning 550S37, $5$15$30$240,625 Master Plan 400S27, $5$15$30$175,000 Site Selection 500S53, $5$15$30$312,500 Build Camp 200U84, $2$10$20$184,667 Demob Camp 150U63, $2$10$20$138,500 Hire Workforce 1800S48, $5$15$30$325,800 Train Team 1 500S65, $2$10$20$170,000 Train Team 2 700S91, $2$10$20$238,000 Train Team 3 650S85, $2$10$20$221,000 Prep Const Site 550U929, $3$12$25$2,948,000 Const Core 3000U 12,144, $3$12$25$38,100,000

Pyramid Cost Estimate-2… Trim Exterior 2400U2,428, $3$12$25$7,656,000 General Design 2000S137, $5$15$30$875,000 Design Structure 520S17, $5$15$30$118,950 Open Quarry 200U33, $3$12$25$110,800 Cut Blocks 2400U971, $3$12$25$3,091,200 Cut Trim 2000U809, $3$12$25$2,576,000 Interior Design 1000S34, $5$15$30$228,750 Room Constr 2500U2,138, $3$12$25$7,025,000 Int Finishes 2200U842, $4$14$30$4,022,857 Final Inspection 200S27, $8$20$50$254,000 Demob Const Site 400U161, $2$10$20$350,400 Bury Pharoah 100S13, $10$30 $10 0$183,111 Labor Sub-total 21,247,55 7 $69,546,160

Pyramid Cost Estimate-3… =SUM(B34*E34 ) Stone Cost #stone s T/ston eTons $/To n =SUM(F34*G3 4) Cut core 2,556, ,670, 964$20$153,419,280 Place Core- Note(3) 2,556, ,670, 964$12$92,051,568 Cut trim 45, ,985$10$229,850 Place Trim-Note(3) 45, ,985$45$1,034,325 Stone Sub-total $246,735,023

Pyramid Cost Estimate-4… =SUM(D8+D9+D10+D13+D14+D15+D16+D20+D2 1+D25+D28+D30) Support Cost#man days $/man-day Skilled Workers(S) 638,856 $10 $6,388,561 Unskilled Workers(U) 20,608,701 $4 $82,434,804 Support Sub-total 21,247,557 $88,823,365 Grand Total $405,104,548

Questions?