Team Hotel: Russell Cabral, Tomi Damo, Ryan Kosak, Vijeta Patel, Lipi Vahanwala Advisors: Bill Keesom – Jacobs Consultancy Jeffery Perl, PhD – UIC Dept. Of Chemical Engineering April 26,
What we are doing? Producing syngas from petcoke Using entrained flow gasifier Implementing a rigorous syngas cleaning Why we are doing this? Making syngas for acetic acid production Chemical production team specs ▪ H2 to CO molar ratio of 2.5 ▪ CO2 and N2 mixed in 2 gasification/ 4/26/2011
How was the PFD generated? What is our feedstock prices? 4/26/2011 3
PFD’s Control Schemes Plant Layout Calculations Refined Individual Economics Joint Econ Presentation 4 4/26/2011
5 Overview of the project from day 1 till the end Brief backgrounds Brief process description ▪ Aspen Simulation overview Economics Overview Recommendations
Mission Statement: Design a process to produce syngas ▪ Determine if this is a practical process Meet the requirements of Team Golf Decide profitability Decide practicality 4/26/20116
Feedstock Choice Petcoke Gasifier Choice Shell Entrained Flow (Membrane Wall) Extent of Simulation Solvent Selexol Syngas Price Location 4/26/20117
Petcoke is a byproduct of oil-refining Heating value of 28 MMBtu/ton More than 55 million tons in 2005 were produced in U.S. oil refineries The sulfur content is relatively high and must be removed during processing in order to create a usable synthesis gas for the chemical production team as well as to meet the requirements of the EPA. 4/26/20118
Gasification covers the conversion of any carbonaceous fuel to a gaseous product. This is not a complete combustion process since there is no residual heating value. 4/26/20119 Shell Entrained Flow Gasifier
Pressure Driven Process Reduction of Pumps High Conversion of Feedstock Highly Efficient Sulfur Removal Sulfur removal to 2 ppm 4/26/201110
11 4/26/2011
12 Gasifier H2S Removal Water Gas Shift Claus Process CO2 Capture and Sequestration
4/26/201113
4/26/201114
Total Equipment + Installation Cost ProcessCost in $MM Gasification Process 135 H 2 S Removal14 Claus Process3 CO 2 Capture26 WGS Reaction4 Total Direct Cost 182 Economic Analysis Capital Cost$ 321 MM Interest Rate on the Loan 8.00 % Inflation3.00 % *Syngas Price ($/ton) $ **Sulfur Price ($/ton) $ 70 NPV$1,534 MM IRR29.79 % Payback Period~ 5.2 years 4/26/201115
4/26/201116
First prices were generated by comparing heating values with natural gas This proved to be too low of a price Negotiations with Team Golf Joint Presentation afterwards ▪ Price determined by creating an equal IRR 4/26/201117
Equipment Sizing and Cost – Aspen Amount of Required Catalyst and Solvent - Aspen & Hand Calculations Economics - Used sheet provided by Mr. Jerry Palmer as a basic template & Microsoft Excel to calculate NPV and IRR PFD, BFD, and Control Scheme – Aspen, Visio, Microsoft Excel
Price for Selexol – UOP ($3.20/lb) Price for Zinc-Oxide – UOP ($55/lb) Price for Petcoke – Dover ($75/ton) Amount of Selexol & Equipment Required for CO 2 Capture – Dow Oil & Gas (~4 MMlb/day Selexol)
4923 Port Rd., Pasadena, TX 2.5 Miles West of Trinity Bay Existing Roads and Railroads 140 Acres with Acetic Acid Production (Team Golf) 4/26/201120
High yield of syngas CO 2 capture makes the process environmental friendly Advantage of location: Supply and ease of transportation of feedstock and product Feedstock Advantage: Byproduct of oil refining It has high calorific content 4/26/201121
Petroleum coke is high in Sulfur content Expensive Gasifier Cost of Petroleum coke fluctuates with crude oil prices Water-Gas shift reaction yields higher amount of CO 2 4/26/201122
Combining the facilities early on There is no such thing as a stand alone gasifier plant Finishing up some of the loose ends of the project Chemical Disposal ▪ Sulfur ▪ Zinc Oxide Tail Gas Slag ▪ Heavy Metals Complete Heat Integration 4/26/201123
4/26/
( ower/gasification/gasifipedia/4-gasifiers/ _shell.html) ower/gasification/gasifipedia/4-gasifiers/ _shell.html 4/26/
Final Report: Executive SummaryDone DiscussionDone Recommendations Done Appendices Design Basis: Done Block Flow Diagram: Done Process Flow Showing Major Equip.: Done 26 4/26/2011
Appendices (Continued) Material and Energy Balances:Done Calculations: Done Annotated Equip. List: Done Econ. Eval. Factored from Equip. Costs: Done Utilities: Done Conceptual Control Scheme: Done Major Equipment Layout: Done 27 4/26/2011
Appendices (Continued) Distribution and End-use Issues:Done Constraints Review: Done Applicable Standards: Done Project Communications File: Done Information Sources and References:Done 28 4/26/2011
Ultimate Analysis ComponentWeight Percent Carbon83.3 Hydrogen4.00 Nitrogen1.49 Sulfur6.14 Oxygen4.44 Proximate Analysis ComponentWeight Percent Fixed Carbon84.8 Moisture6.00 Volatile Matter8.60 Ash0.6 Element VNiFCuMgSeBePbAsCdHg PPM < <.01 Average Petcoke Metal Makeup (5) 29
30 4/26/2011
31
32 4/26/2011
33 4/26/2011
34 4/26/2011
35 4/26/2011
36
4/26/201137
4/26/201138
4/26/201139
4/26/201140
Inlet Fraction Clean Syngas Component Flow for WGS Reactor(lbmoles/hr) for WGSCp (btu/lbmole* F) Outlet Syngas Comp (lbmole/hr) from (WGS) CO H2O N H2* CO CH4* H2S0.000 COS0.000 Total /26/2011
Gasifier EquipmentHeat Load (MMBtu/hr) Gasifier-34.7 HP Steam Heat Exchanger139.0 MP Steam Heat Exchanger281 Cooler Flash2.99 Sulfur Clean Up EquipmentHeat Load (MMBtu/hr) Sulfur Stripper Reboiler57.0 Sulfur Stripper Cooler Selexol Cooler-40.7 Rich / Lean Heat Exchanger /26/
CO2 in our syngas is absorbed on Selexol to be selectively removed Delete only one CO2 slide. 434/26/2011
44 _lg.jpg 4/26/2011