MS PROJECT 2013 Project Planning, Scheduling, Monitoring and Control ASSOC. PROF. DR. İBRAHİM YİTMEN FACULTY OF ENGINEERING DEPARTMENT OF CIVIL ENGINEERING.

Slides:



Advertisements
Similar presentations
Microsoft Project Tutorial for Chapters 6 & 7
Advertisements

Academic Computing Services 2009 PROJECT MANAGEMENT CONCEPTS.
USING MS PROJECT Project management software programs such as Microsoft Project can be used to compute the earliest and latest start and finish times and.
PERTEMUAN 3 PPSI Microsoft Project Presentation. What is a Gantt Chart? A Gantt Chart is a visual tool to help Plan, Manage, and Track a project or projects.
MS Project Tutorial EMEN. Entering Project Properties Choose File Properties Click the Summary tab You can now enter general information about the project.
CPM, Crashing, Resource Leveling using MS Excel & MS Project
Microsoft Project Tutorial for Chapters 4 & 5 This Tutorial explains how to: Build a MSP Project Network Build a Probabilistic MSP Network Use the Calendar.
Microsoft Project.
McGraw-Hill/Irwin © The McGraw-Hill Companies, All Rights Reserved Creating Gantt Charts With Microsoft Project Technology Plug-In T12.
Projmgmt-1/18 DePaul University Evaluating Schedule In MicroSoft Project Instructor: David A. Lash.
PROJECT TIME CONTROL. PROJECT SCHEDULING REFERENCES PRIMARY REFERENCE IN THIS PRESENTATION IS Operations Management, Ed 6, Heizer & Render, Prentice Hall,
ELC 347 DAY 2. Agenda Questions Working with MS Project 2003 Making a PB & J Sandwich.
1 Project Management – Part 2 Yale Braunstein School of Information Management & Systems UC Berkeley.
OPSM 639, C. Akkan1 OPSM 639 Project Management Introduction to Microsoft Project - Part 2: Developing a Network Plan.
Microsoft Project Presentation By Corey Johnson 10/11/00.
USING MS PROJECT Project management software programs such as Microsoft Project can be used for developing the project schedule We demonstrate the use.
Project Planning Using MS Project Creating a project plan URBS 609 Project, Unit 3.
Copyright © Software Process Group 1 Software Process Group Microsoft Project Tutorial Steve Meyers
Microsoft Office Project 2007: Managing Projects.
CS 160: Software Engineering October 20 Class Meeting Department of Computer Science San Jose State University Fall 2014 Instructor: Ron Mak
USING MS PROJECT 2010 Project management software programs such as Microsoft Project 2010 can be used for developing the project schedule and budget, and.
ERT461 BIOSYSTEMS ENGINEERING DESIGN 1 ERT424 BIOPROCESS PLANT DESIGN 1.
1 Microsoft Project 2010 Demo Part 1. 2 Project: Initial Screen To start click Project/Project Information. Add start date.
EGNR 300 Project Management Planning & Scheduling ENGR 300 Dept. of Computer Science and Engineering University of Bridgeport,
~ pertemuan 6 ~ Oleh: Ir. Abdul Hayat, MTI 03-Apr-2009 [Abdul Hayat, Project Time Management, Semester Genap 2008/2009] 1 PROJECT TIME MANAGEMENT.
Fourth R Inc. 1 WELCOME TO MICROSOFT OFFICE PROJECT 2003 INTERMEDIATE COURSE.
TA. MARAM AL-KHAYYAL NET481 MS Project Overview. Outline Introduction to project management.  Project 2007 can help you manage project time, resources,
Microsoft Project Tutorial for Chapters 4 & 5 This Tutorial explains how to: Build a MSP Project Network Build a Probabilistic MSP Network Use the Calendar.
Project Management Software Application PRM 705 Lecture 32 1.
Microsoft Project 2010 ® Tutorial 6: Sharing Project Information with Other People & Applications.
Fourth R Inc. 1 WELCOME TO MICROSOFT OFFICE PROJECT 2003 INTRODUCTORY COURSE.
Microsoft Project 2007 Class Schedule of Topics. Topics Day 1 Review of MS Project Basics 1:00 – 1:30 Constraints 1:30 – 2:15 Dead Lines 2:15 – 2:30 Identify.
Creating a project plan URBS 609 Project, Unit 3.
An-Najah National University Faculty of Engineering Civil Engineering Department Construction Project Management “Medical Center In Al-Daheria” Prepared.
Microsoft Project – Tutorial 4 Leveling Overallocations In some cases, a resource could be assigned more work in a given time period than it has working.
MS Project Tips & Tricks Presenter: Natalie Wieland PMP, MCSD, MCDBA, OCPDBA, MCT.
Chapter 6: Project Time Management Information Technology Project Management, Fourth Edition Using Critical Chain Scheduling, PERT, and MS Project 2003.
Microsoft Project – Tutorial 4 Assigning Resources and Costs we will now add resource management information and project cost data to our project a cost.
Office Management Tool - II Institute of Management Sciences Muhammad Shahzad Ali Lec 7: Introduction to MS - PROJECT L E C T U R E 7 INTRODUCTION TO MS.
MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering September 17, 2009.
PRJ566 Project Planning & Management Dependencies, Network Diagrams & Critical Path.
Prof Ralph V. Locurcio, PE CON 2001 CVE Sequence Single Family House - 3,000 square feet Duration 1 General Conditions 21 2 Apply for Permits.
A tutorial on MS Project James Burns. 22 Learning Objectives  Entering Tasks in the Gantt View  Task subordination  Linking of Tasks  Setting start.
DECISION MODELING WITH MICROSOFT EXCEL Chapter 14 Copyright 2001 Prentice Hall Publishers and Ardith E. Baker Part 3 andand PERT CPM.
1 EASTERN MEDITERRANEAN UNIVERSITY FACULTY OF ENGINEERING DEPARTMENT OF CIVIL ENGINEERING CIVL 493 Construction Management Assoc. Prof. Dr. Ibrahim YITMEN.
CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)
1 Copyright © 2015 Pearson Education, Inc. Module 1 Workshop 2 Creating a Detailed Project Plan Series Editor Amy Kinser by Kristyn Jacobson.
Microsoft Project Tutorial for CSCI 577 Fall 2006 Jesal Bhuta
Microsoft Project 2010 ® Tutorial 4: Assigning Resources and Costs.
Microsoft Project 2010 ® Tutorial 1: Planning a Project.
Microsoft Project 2010 ® Tutorial 5: Tracking Progress and Closing the Project.
Scheduling and Budgeting Engineers Without Frontiers CEE 402.
Microsoft Project Mastering Microsoft Project 2010 Instructor: Tom Vorves Dial In:1 (800)
© 2008 Prentice HallAppendix A -1 Introduction to Project Management Appendix Microsoft Project Tutorial Information Systems Project Management: A Process.
Using MS-Project INFS MS-Project: 3 Major Parts 1. Project Planning 2. Project Execution & Tracking 3. Project Reporting.
CE 332 – Construction Engineering and Management
MICROSOFT PROJECT MODULE 2 - BUILD A HOUSE.
Microsoft Project 101: How to Build a Project Plan
MICROSOFT PROJECT MODULE 7 – CRITICAL PATH.
A tutorial on MS Project
MS Project 2016 Level II
In this tutorial you will:
ENGINEERING MANAGEMENT (GE 404)
Guide to Project.
In this tutorial you will:
New Perspectives on Microsoft Project 2007: Planning a Project
Introduction to Project Management ECE 480 Erik Goodman.
Microsoft Project 2007 Demo Part 1
ENGINEERING MANAGEMENT (GE 404)
Expedite Project Updates Using a Custom Status View
Presentation transcript:

MS PROJECT 2013 Project Planning, Scheduling, Monitoring and Control ASSOC. PROF. DR. İBRAHİM YİTMEN FACULTY OF ENGINEERING DEPARTMENT OF CIVIL ENGINEERING FALL SEMESTER CIVL493 CONSTRUCTION MANAGEMENT

BASIC INFORMATION Project View

BASIC INFORMATION Dialog box

BASIC INFORMATION Command Tabs Contextual Tabs

BASIC INFORMATION File Tab

BASIC INFORMATION File Save

BASIC INFORMATION Print

BASIC INFORMATION Create New Project

INTRO TO MS PROJECT Charts –Gantt Chart –Network Diagram –Resource Graph

INTRO TO MS PROJECT Gantt Chart

INTRO TO MS PROJECT Network Diagram

INTRO TO MS PROJECT Resource Diagram

INTRO TO MS PROJECT Forms (Task Information)

INTRO TO MS PROJECT Tables (Task Sheet)

INTRO TO MS PROJECT Understanding Project Management Input/Output Model

INTRO TO MS PROJECT Microsoft Project Language Clarification of Terms

INTRO TO MS PROJECT Non-critical Tasks Critical Tasks Critical Path

INTRO TO MS PROJECT Views and Tables View Menu Options

INTRO TO MS PROJECT Views and Tables Gantt İzleme Görünümü

INTRO TO MS PROJECT Resource Tab Project Tab View Tab

PROJECT PLANNING Task Attributes Objectives Time constraints Milestones Task(s) on which this Task is Dependent Estimated Duration Task(s) that are dependent on this task Optimistic estimate Itemised task Budget Pessimistic Estimate Resources required to complete the Task The ability to manage the progression of the tasks in terms of their resources, start times and finish times.

PROJECT PLANNING WBSTask Name DurationPredecessorResources Project Plan - Template Unit Rate Qty

CREATE NEW PROJECT New Project Screen

CREATE NEW PROJECT New Project – Gantt Chart View

CREATE NEW PROJECT Project Info Dialog Box

CREATE NEW PROJECT Project Statistics Dialog Box

CREATE NEW PROJECT Project Calendar – Change Working Time

CREATE NEW PROJECT Create New Base Calendar

CREATE NEW PROJECT Project Working Time Adjustments

CREATE NEW PROJECT Project Working Time Adjustments

TASK ENTRY AND LINKS Project Options – Schedule (manual)

TASK ENTRY AND LINKS Task Entry – Task Information Form

TASK ENTRY AND LINKS Create New Task

ENTER TASK DURATION Enter Task Durations

LINKING TASKS Link types A aktivitesi tamamlandıktan sonra B aktivitesi başlar. Örneğin beton döküm işi, kalıp ve demir donatı tamamlandıktan sonra başlar. A aktivitesi ve B aktivitesi birlikte başlar. Örneğin beton döküm işi ve beton düzeltme işi birlikte başlar. A aktivitesi ve B aktivitesi birlikte tamamlanır. Örneğin asma tavan içi elek. kablolama ve data kablolama işleri birlikte tamamlanır. B aktivitesi, A aktivitesi başlamadan önce tamamlanamaz. Örneğin çatı montajı, çerçevenin sahaya getirilmesinden önce tamamlanamaz.

LINKING TASKS Preceeding Task– FS link

CREATE SUMMARY TASKS– WBS Create Main Task

CREATE SUMMARY TASKS– WBS

ENTER MILESTONES Enter Milestones

RESOURCE MANAGEMENT Assigning Resources – resources tab

RESOURCE MANAGEMENT Resource Information Dialog – General

RESOURCE MANAGEMENT Resource Information Dialog – Cost

RESOURCE MANAGEMENT Resource Graph

RESOURCE MANAGEMENT Resource Assignment

RESOURCE LEVELLING Resource Levelling

CREATE COST INFORMATION Cost Entry– Fixed Cost

CRITICAL TASKS Critical Tasks

DETERMINATION OF SLACKS (FLOATS) Detailed Gantt – Free Slack, Total Slack

SET BASELINE Set Baseline

SET BASELINE Set Baseline and clear baseline

TRACKING PROGRESS – UPDATE PROJECT Update Task – Actual Start, Finish, %

TRACKING PROGRESS – UPDATE PROJECT Update Project

TRACKING PROGRESS – UPDATE PROJECT Tracking Gantt

SLIPPED ACTIVITIES Detailed Gantt – Slipped Activities

SORT, FILTER VE GROUP Sort

SORT, FILTER VE GROUP Filter

SORT, FILTER VE GROUP Groups

PRINT Print Options– Page Setup

REPORTING Report Menu– Dashboards

REPORTING Report Menu– Work Overview

REPORTING Report Menu– Resource Overview

REPORTING Report Menu– Critical Tasks

SAMPLE PROJECT – HOUSE BUILDING WBS – Work Breakdown Structure (Main Structural Framework)

SAMPLE PROJECT – HOUSE BUILDING WBS – Work Breakdown Structure– Finishing Works

SAMPLE PROJECT – HOUSE BUILDING Proje Programlama Bilgileri - 1 WBSTask DesriptionFixed CostCrew Standard Rate DurationPredecessorsLink TypeLag 0000Villa Building$946, Ground Works 1100Concrete Works$49,600RMIX$20.0/hr21220FS 1200Excavation$46, Pool$23,200 EXC $500/hr61220FS 1220Foundations$23,200EXC$500/hr6 7100, 7200, 7300 FS 1300Landscaping$89, Pool construction and landscaping$54,400GAR$30.0/hr241210FS 1320Yard landscaping, lawN etc.$17,400GAR$15.0/hr68220FS 1330Planting and gardens$18,000GAR$15.0/hr31320SS1 day 2000Materials$7, Delivery$5,000PUR$15.0/hr FS 2200 Storage $2,000PUR$15.0/hr SS 3000Structure$225, Timber parts of structure including exterior and interior walls $124,000TİM$25.0/hr483200FS 3200 Masonry parts of structure including basement walls $60,000MAS$25.0/hr301100FS6 days 3300 Steel parts of structure including major spans $41,000STE$25.0/hr123100SS 4000 Project Management including budget, scheduling, site management $118,200PMPM$40.0/hr SS 5000Interior Fitout of house$135, Lining including walls, ceilings and doors $29,600PAI$20.0/hr , 3200, 3300 FS 5200 Kitchen and bathroom cabinets and doors $42,200CAR$30.0/hr125100FS2 days 5300 Storage cabinets, closets, built-in shelving $9,900CAR$30.0/hr65200FS 5400Decorating including all painting, carpeting, tiling $54,000PAI, CRP, TIL $20.0/hr, $20.0/hr, $25.0/hr FS2 days

SAMPLE PROJECT – HOUSE BUILDING Proje Programlama Bilgileri - 2 WBSTask DesriptionFixed CostCrewStandard RateDurationPredecessorsLink TypeLag 6000Services to building $ 113, Plumbing and drainage services 6110 Water suplly hot and cold $ 13,000PLU $ 25.0/hr93100FF9 days 6120 Waste removal, sanitary and foul $ 12,000PLU $ 25.0/hr66110FS 6130 Gas supply $ 11,000GAS $ 25.0/hr36120FS 6200 Electrical supply to site and distribution thorough building including power outlets, switches, lights, major appliance supplies $ 19,500ELE $ 25.0/hr93100FF9 days 6300 Data services including telephone and LAN cabling $ 13,400DATDAT $ 35.0/hr36200FS 6400 Entertainment services including speaker cabling and installation $ 15,400ELE $ 25.0/hr36300FS 6500 Security including perimeter, building and access control $ 15,800SEC $ 35.0/hr66300SS 6600 Pool equipment installation $ 13,200MEC $ 30.0/hr66110SS 7000 Permits and sign-off from government bodies $ 3, Energy sign-off $ 1,000ENG $ 50.0/hr Building envelope sign-off $ 1,000ARC $ 50.0/hr Steuctural integrity sign-off $ 1,000ENG $ 50.0/hr Cladding of building including roofing 8100 Roofing including tiles and insulation $ 53, Roof tiles $ 38,600TLE $ 15.0/hr38120SS 8120Roof installation $ 14,800INS $ 15.0/hr3 3100,3200,33 00 FS 8200 Walls including cladding and insulation $ 62, Wall exterior ladding $ 47,200CLA $ 15.0/hr128220SS 8220Wall insulation $ 14,800INS $ 15.0/hr65100FS2 days 8300Joinery including exterior doors $ 33,600DOO $ 30.0/hr65100FS2 days 8400Exterior paint and painting $ 27,000PAI $ 15.0/hr68210FS