Loss of EMS Events 2015 System Operator Seminar. Training Objectives 2 System Operators will be able to identify the ERO Event Analysis Process Category.

Slides:



Advertisements
Similar presentations
Interchange Authority Recommendations Board of Directors Meeting December 7, 2007.
Advertisements

Brett Wangen, Director of Engineering WECC RC Update to PCC Planning Coordination Committee Meeting October 24, 2013.
Phase II – Analyze the Identified Issues from Perspectives of Alternative Approaches Determine which of the identified issues remain under alternate approaches.
Revised Event Analysis Process Event Analysis Subcommittee (EAS) Process Update Team (EUT) Hassan Hamdar – FRCC Reliability Engineer, EAS Vice-Chair FRCC.
PER
FRCC Fall Compliance Workshop October , 2013
1 PER-005 Update Impact on Operators System Operator Conference April and May 1-3, 2012 Columbia, SC Margaret Stambach Manager, Training Services.
1 Reliability Coordination (IRO Standards) 2011 System Operator Conferences #3 and #4 September & 20-22, 2011 Nashville/Franklin TN Rocky Williamson.
Goshen Area Bus Reconfiguration
Reliability Software1 Reliability Software Minimum requirements & Best practices Frank Macedo - FERC Technical Conference July 14, 2004.
August 14, 2003 Blackout Final Report
PacifiCorp-CAISO EIM Initiative Overview
@TxSchoolSafety Continuity of Operations Planning Workshop Devolution & Reconstitution.
Recent ERCOT Events Lessons Learned
1 JULY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT – WORK IN PROGRESS Session 4 Discussion of Alternatives and Implementation Activities for Real- Time.
1. 11/26/2012: NERC Board of Trustees adopted CIP v5 CIP thru CIP CIP and CIP Version 5 Filing FERC requested filing by 3/31/2013.
System Operator Conference NERC Standards Review for: Simulator Drill Orientation 2014 System Operator Conferences Charlotte NC & Franklin TN SERC/SOS.
Andy Meyers Interchange Scheduling and Accounting Subcommittee Chair Discussion Item: Use of Emergency eTags January 2015 Salt Lake City, UT.
NERC Lessons Learned Summary March NERC lessons learned published in March 2015 Two NERC lessons learned (LL) were published in March2015 LL
NERC Lessons Learned Summary
Supervisory Systems.
GOP and QSE Relationship Jeff Whitmer Manager, Compliance Assessments Talk with Texas RE June 25, 2012.
ERCOT Compliance Audits Robert Potts Sr. Reliability Analyst March 23, 2005.
FRCC Seasonal Transmission Assessment & Operational Seasonal Study Winter 2012.
Determine Facility Ratings, SOLs and Transfer Capabilities Paul Johnson Chair of the Determine Facility Ratings Standard Drafting Team An Overview of the.
NERC PER-005 Overview May 10, Who, What, When, Where, Why WHO: RC, TOP, BA WHAT: –R1: Systematic Approach to Training –R2: Verify operator capabilities.
IT Business Continuity Briefing March 3,  Incident Overview  Improving the power posture of the Primary Data Center  STAGEnet Redundancy  Telephone.
Recommendations from 2011 Southwest Outage Heather Polzin, FERC Office of Enforcement Dave Nevius, Senior Vice President, NERC Member Representatives Committee.
NERC Congestion Management Congestion Management Option 3 Vendor Meeting Julie Pierce – NERC IDCWG Chair.
Joe Mercer Operations Planning Engineer III Operation Planning Analysis PHAAUG Meeting Mar 12 th, 2015.
APPA RELIABILITY STANDARDS & COMPLIANCE SYMPOSIUM Case Study: City Utilities of Springfield, MO January 11, 2007.
Peak RCCo Performance Metrics Draft –November 2013.
Assessing Compliance. 2 NERC Compliance Workshop 11/02/07 Documentation of Compliance with NERC Reliability Standards Jeff Whitmer.
Effective Communications and Declaring EEAs 2016 System Operator Seminar.
Status Report for Critical Infrastructure Protection Advisory Group
Project System Protection Coordination Requirement revisions to PRC (ii) Texas Reliability Entity NERC Standards Reliability Subcommittee.
Bill Lewis, Compliance Team Lead NERC Reliability Working Group May 16, 2013 Texas RE Update Talk with Texas RE April 25, 2013.
Project Cyber Security Order 706 Version 5 CIP Standards Potential to Adversely Impact ERCOT Black Start Capability.
COMPLIANCE ROLLOUT Vann Weldon Compliance Training Administrator March 23, 2005 NERC FUNCTIONAL MODEL REVIEW.
EAS Lessons Learned Summary Lessons Learned Published in June 2014.
2013 Wind Conference. Congestion Management & Communication Processes CJ Brown.
High Availability in DB2 Nishant Sinha
NERC Project S ystem Protection Coordination - PRC-027​ Presentation to the NSRS Conference Call April 20, 2015 Sam Francis Oncor Electric Delivery.
Managing of Limits during Loss of Analysis Tools/ EMS April 23, 2014.
NERC Lessons Learned Summary LLs Published in September 2015.
Grid Reliability Metrics by Jim Dyer Electric Power Group, LLC January 29, 2004 Washington, DC Transmission Reliability Research Review.
Loss of EMS Events 2015 System Operator Seminar. Training Objectives 2 System Operators will be able to identify the ERO Event Analysis Process Category.
Operating Topics Part 2 Mike Oatts May 9, 2008 Transmission Customer Forum Destin, Florida Part 2 Mike Oatts May 9, 2008 Transmission Customer Forum Destin,
Projects System Protection Coordination Draft 2 of TOP Texas Reliability Entity NERC Standards Reliability Subcommittee November 2, 2015.
NAESB BPS Yasser Bahbaz– IDCWG Chair January 5 th, 2016.
RAWG Agenda Item LAR Data WECC Staff. Data Elements Generator information – Existing – Changes Monthly Peak Demand and Energy (actual year and.
NERC Lessons Learned Summary LLs Published in December 2015.
Restoration Concepts PEAK RC Training Classification: Confidential Version No.: 1.5 Date of Document: Document Owner/Author: B Pederson Classification:
Hurricane Lindahl 2016 System Operator Seminar. Hurricane Watch 2 The National Hurricane Center in Miami has issued a hurricane watch for the Southern.
Current Nodal OS Design 1.The NMMS database will have an OWNER and an OPERATOR designation for each piece of equipment in the model. The OWNER and OPERATOR.
FRCC Voice Communications OBJECTIVES FRCC Regional Voice Communications Procedure – Review the New FRCC Handbook Document Review Voice Comm. Requirements.
CIIMS Update Stacen Tyskiewicz CIIMS Chair March 22, 2016.
NERC BAL-005, BAL-006, FAC-001 Gary Nolan WECC ISAS April 20, 2016.
©2003 PJM 1 Presentation to: Maryland Public Service Commission May 16, 2003.
NERC Published Lessons Learned Summary
NERC Lessons Learned Summary
NERC Published Lessons Learned
“FRCC RESTORATION PLAN (BLACKOUT & BLACK START)” - TRAINING -
Phase Angle Limitations
NERC Published Lessons Learned
Western Electricity Coordinating Council
“TOP-010-1: Data Quality, Analysis Quality, and Alarm Process Monitor”
TOP-010-1(i) Implementation
PEAK’s RMTNET Tool Sarma (NDR) Nuthalapati, Principal NetApps Engineer
Coordinate Operations Standard
Presentation transcript:

Loss of EMS Events 2015 System Operator Seminar

Training Objectives 2 System Operators will be able to identify the ERO Event Analysis Process Category associated with a loss of EMS event System Operators will be able to demonstrate through a paper exercise the steps to take in response to a loss of Energy Management System (EMS) Event

NERC Event Analysis of EMS Event 3 ERO Event Analysis Process EMS Event Categories 1f - Unplanned evacuation from a control center facility with BPS SCADA functionality for 30 minutes or more. 1h - Loss of monitoring or control, at a control center, such that it significantly affects the entity’s ability to make operating decisions for 30 continuous minutes or more. 2b - Complete loss of SCADA, control or monitoring functionality for 30 minutes or more.

Examples of 1h Events 4 Examples include, but are not limited to the following: i. Loss of operator ability to remotely monitor, control Bulk Electric System (BES) elements, or both. ii. Loss of communications from SCADA RTUs iii. Unavailability of ICCP links reducing BES visibility iv. Loss of the ability to remotely monitor and control generating units via AGC v. Unacceptable State Estimator or Contingency Analysis solutions

Loss EMS Events 5 CategoryFRCCNERC (including FRCC) 1f121 1h275 2b10110 Total13206 CategoryFRCCNERC (including FRCC) Total28563 Category % NERC EMS Event to All Events 124% 281% All37% Data for all qualifying events from October 2010 through December 2014.

Loss of EMS Events 6 Are loss of EMS events impactful to System Operators? Have loss of EMS events been impactful to the BES?

Loss of EMS Events 7 Reasons for EMS events not having BES impact Most commonly occur during maintenance Planned for off peak hours and weekends with fairly flat loads EMS staff is nearby Heightened SO awareness Preparation and good SO action Processes and Procedures Training (Practice makes perfect) Interconnected Systems

FRCC RC Conservative Operations 8 Purpose: Implemented to maximize the FRCC’s ability to operate the BES reliably during limited or complete loss of EMS monitoring capabilities Identifies triggers to implement Conservative Operations Identifies actions and communications the RCSO should take during partial or complete loss of EMS/SCADA or RTCA Procedure title: FRCC Reliability Coordinator Conservative Operations Procedure FRCC-MS-OPRC-029

FRCC RC Conservative Operations 9 RCSO should declare Conservative Operations (Ops) if RC’s EMS, Data Acquisition, or RTCA is lost and ETR is >30 minutes or if RCSO has a reliability concern during loss of functionality In this presentation we will refer to this as a loss of functionality RCSO verify on duty supervisor is notified, request ETR, and (if applicable) ask about a plan to failover RCSO notify SE RC of loss of functionality and potential call for Conservative Ops Estimated Time of Repair (ETR) Southeastern (SE)

FRCC RC Conservative Operations 10 Operating Entities (OEs) as referenced in the RC Conservative Operations Procedure Balancing Authorities (BAs) Distribution Providers (DPs) Generator Owners (GOs) Generator Operators (GOPs) Load Serving Entities (LSEs) Transmission Operators (TOPs) Transmission Owners (TOs)

FRCC RC Conservative Operations 11 RCSO to request SE RC notify RCSO of any new contingencies and schedule discrepancies of >200 MWs until functionality is back RCSO to notify all OEs via hotline and FTMS of loss of functionality and Conservative Ops could be called OEs to acknowledge message over hotline RCSO to instruct all BAs to maintain ACE as close to zero as possible and notify RCSO of deviations >±50MWs

FRCC RC Conservative Operations 12 OEs to notify RCSO of any new contingencies OEs to notify RCSO if they get nominal voltages exceed or if they have any real-time overloads on their transmission facilities For nuclear switchyards, provide notification to the RCSO if the local transmission station voltage is outside of established limits.

FRCC RC Conservative Operations 13 RCSO to notify the MRCOO (or designee) of loss of functionality and Conservative Ops may be called RCSO to periodically check the RTCA internet sharing site to view other TOP’s CA output RCSO should log all pertinent data and OE reports received in a time sequenced manner

FRCC RC Conservative Operations 14 If the loss of functionality ETR is unknown or >30 minutes, the RCSO should declare Conservative Ops. Actions are similar but the RCSO will notify that Conservative Ops is being implemented Additional steps for SE RC: In addition to previous notify SE RC that Conservative Ops is implemented RCSO to contact SE RC for updates on actual vs. scheduled net interchange (ANI vs. SNI) in 15 minute intervals RCSO update SE RC on status of functionality every 60 minutes until Conservative Ops is terminated

FRCC RC Conservative Operations 15 Additional steps for OEs: RCSO to notify OEs via hotline and FTMS of loss of functionality and that Conservative Ops is being implemented Request acknowledgement OEs to provide ACE on the hotline RCSO to review ACE data against the data provided by SE RC RCSO request off schedule BAs to correct ACE and instruct FPL to redispatch to make up remaining discrepancies RCSO to update the OEs on the status of the EMS every 60 minutes until the Conservative Operations have been terminated

FRCC RC Conservative Operations 16 RCSO to notify MRCOO (or designee) of loss of functionality and implementation of Conservative Ops RCSO should: Verify with Next-day planner that outaged lines have been returned to service Defer any planned outages that haven’t been taken until Conservative Ops is terminated

FRCC RC Conservative Operations 17 RCSO should: Assess the need to reduce imports/exports with OEs Coordinate any interface reductions with interface owners Coordinate with OEs and assess the need to return to service any planned outage

FRCC RC Conservative Operations 18 When EMS/SCADA or RTCA is back: RCSO to terminate Conservative Ops and notify SE RC, OEs and MRCOO

“Conservative Operations” 19 All OEs need to understand what it means when the RC calls for Conservative Operations

“Conservative Operations” 20 FRCC RC requests: - OEs acknowledge the message on the hotline - BAs maintain ACE as close to zero as possible and notify FRCC RC of any deviations > 50 MWs - OEs notify FRCC RC of any new contingencies - OEs notify FRCC RC if nominal voltages exceed alarm limits, or if any real time overloads exist. - OEs notify FRCC RC if the local transmission stations on nuclear switchyards is outside of established limits

“Conservative Operations” 21 Internally each company may define Conservative Operations differently It’s also important to understand what it means within your company

Loss of EMS Exercise 22 An automated planned disk management activity began to run on HPC EMS server EMS was operating under normal conditions A file system error occurred on the primary EMS server which causes a critical process to stop and the server becomes hung This causes the replication of data to the backup EMS servers to be unavailable EMS-2, EMS-3, and EMS-4 become disabled

Loss of EMS Exercise 23 Physical Relocation Was not an Option!!! Primary EMS server remained enabled Therefore no automatic fail-over took place Gateway server lost it’s connection with the primary server Memory replication services application on the primary EMS server losses it’s connection to the three other servers that are designed to step in and take over The three backup EMS servers become invalid and unavailable for failover (status disabled)

Loss of EMS Exercise 24 FRCC RC and HPC share an EMS When HPC losses EMS functionality it usually means the RC will too HPC and the RC lost monitoring and control of their EMSs for over 1 hour HPC and the RC both called for Conservative Ops RC worked with Southeaster RC to monitor the state ACE

Loss of EMS Exercise 25 Assessment Instructions Three roles Reliability Coordinator, HPC Balancing Coordinator and HPC System Operator Checklist for each Sequence of Events provided Complete your work package and make sure to get a signature before you break

Questions? 26