First results from the study of the LHC cycle power consumption FCC I&O meeting 24 th June 2015 Davide Bozzini With the contribution of G. Burdet, B. Mouche,

Slides:



Advertisements
Similar presentations
Engineering Department EN Cooling and Ventilation issues 1 FUTURE EXPLOITATION OF THE EAST AREA EN-CV Michel OBRECHT.
Advertisements

LHC UPS Systems and Configurations: Changes during the LS1 V. Chareyre / EN-EL LHC Beam Operation Committee 11 February 2014 EDMS No /02/2014.
HLTC 15 th April 2014 EDMS: Y. Muttoni EN-MEF-INT with the contribution of P. Fessia.
E-CLOUD VACUUM OBSERVATIONS AND FORECAST IN THE LHC Vacuum Surfaces Coatings Group 03/07/2011 G. Bregliozzi On behalf of VSC Group with the contributions.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Preliminary Studies of the Electric Power Distribution for CLIC
Chilled water Meyrin consolidation Study 1 st Part Many thanks for their contribution to: Pasquale Alemanno, Fortunato Candito, Alexander Putzu.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
A NEW MARKET PLAYER: THE AGGREGATOR AND ITS INTERACTION WITH THE CONSUMER interaction Ramón Cerero, Iberdrola Distribución Paris, June 9th 2010 ADDRESS.
Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System October 24-26, 2012 THE HIGH-VOLTAGE NETWORK OF CERN.
Accelerators for ADS March 2014 CERN Approach for a reliable cryogenic system T. Junquera (ACS) *Work supported by the EU, FP7 MAX contract number.
Trieste (IT), 20 may 2008POPCA A novel 60 MW Pulsed Power System based on Capacitive Energy Storage for CERN PS machine Jean-Paul BURNET CERN, European.
Page 1J. Hourtoule, Electricity contract: scope and forecasted consumption, 16/07/2015 © ITER Organization Electricity Supply Contract: For the ITER Site.
Introduction to availability modelling in ELMAS Arto Niemi.
How can we reduce the “no beam„ time? Walter Venturini Delsolaro D. Arnoult, S. Claudet, G. Cumer, K. Dahlerup Petersen, R. Denz, F. Duval, V. Montabonnet,
Bulding 245 schedule update LIU Booster Meeting Fulvio Boattini & Michel Obrecht TE-EPC / EN-CV TEEPC.
LHC Hardware Commissioning Review May 2005, CERN, 1211 Geneva 23 1 LHC Hardware Commissioning Review Contribution ID: 20 – Quality assurance and.
CERN plans towards energy efficiency Serge CLAUDET Nov 2014.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
Preliminary Power Estimates for the FCC-hh FCC Week 2015 Washington, 26 April 2015 Rende Steerenberg, CERN - Geneva2 Rende Steerenberg, Paul Collier,
Consolidation and Upgrade of the SPS Electrical Networks Current Status JP. Sferruzza, on behalf of EN/EL.
Luminosity expectations for the first years of CLIC operation CTC MJ.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
NUCLOTRON CONTROL SYSTEM (NCS) V.Andreev, E.Frolov, A.Kirichenko, A.Kovalenko, B.Vasilishin, V.Volkov Laboratory of High Energies, JINR, Dubna.
Jean-Paul BURNET, AB/PO ATC-ABOC days, 22 January 2007 PS Main Power System: What has been done from June 2006? What will be the situation in 2007? PS.
An introduction to Energy aspects at CERN June 2014.
Power Quality Karsten KAHLE Electric Power Converter Group (TE-EPC) High Power Converter Section Review of CERN’s Electrical Power Network October.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
Power Converters and DC cablesSlide 1/.. LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005 Water cooled cables warm bus bars power converter.
SM18 cryogenics infrastructure upgrade L. Serio TE-CRG.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
TE-CRG Activities D. Delikaris, TE-CRG.
Wind Production intermittency Cross border compensation: what to expect in Western Europe? Analysis of Winter 2010/2011 Hubert Flocard and Jean-Pierre.
LHC cycle power consumption FCC I&O meeting 23 rd September 2015 D Bozzini & G. Peon EDMS xxxxx.
Design considerations for the FCC electrical network architecture FCC week 2016, Rome, April 2016 Davide Bozzini - CERN/EN/EL With the contribution.
110 th November 2010EN/CV/DC Detector Cooling Project - advancement status of Work Package N3 Thermosiphon project Michele Battistin 18 May 2011.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
First collisions in LHC
Update on the PSB Cooling and Ventilation Systems
Supply and Distribution of Electrical Energy
YETS & LS2 Works EN-EL / Power distribution
SR1 extension follow up 27-Mar-17 Marco Ciapetti.
YETS & LS2 Works EN-El on LHC / Power distribution
CLIC Civil Engineering & Infrastructure Working Group Meeting
Minimum Hardware Commissioning – Disclaimer
Innovative He cycle Francois Millet.
SPS cryogenic proximity equipment and SM18 validation
The LHC - Status Is COLD Is almost fully commissioned
the high-voltage network of CERN ToMORROW
FCC Tunnel and Shaft Cross Sections
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
Cooling systems for HL-LHC (WP17.3)
CLIC: from 380 GeV up to 3 TeV Will also study klystron based machine for initial stage.
YETS & LS2 Works EN-EL / Power distribution
COOLING & VENTILATION INFRASTRUCTURE
EN-CV: P8 systems and Detector Cooling
Business opportunities related to CERN electrical network
TEST PLANS for HL LHC IT STRING
Tue :25 Beams dumped due to RF vacuum interlock
Power cut 18kV cable for EMD404/E9 is heating
The SPS 800 MHz RF system E. Shaposhnikova for BE/RF
Mathew C. Wright January 26, 2009
Maintenance at ALBA facility: Strategy for the conventional services
ILO Industrial Opportunities Days, 6-7 June 2019
Review Bloc 4 and SM18 facilities and upgrade
Presentation transcript:

First results from the study of the LHC cycle power consumption FCC I&O meeting 24 th June 2015 Davide Bozzini With the contribution of G. Burdet, B. Mouche, R. Ledru, R.Sterenberg, P. Sollander EDMS Updated version including corrections and suggestions collected during the meeting

Outline 1.Terminology 2.LHC – Electrical network topology 3.LHC – Systems classification 4.Daily average 7 TeV and 13 TeV 5.Consumption variation between 7 TeV and 13 TeV 6.Comparison between 7 TeV, 13 TeV and LHC design values 7.Active power profile during two 13 TeV 8.Active power profile during a 13 TeV Ramp-down and a Ramp-up 9.Summary of steady state and peak active powers 10.Conclusion

Terminology Average power [P avg ]: is the mean value of the power consumption during the interval of interest (in our case at least 24 hours, weekly, monthly) Steady state power [P steady ]: Is the mean value of the power during an interval in which the system state variables are considered to be constant (in our case the duration of the: injection, stable beam, TS, etc…) Peak power [p peak ]: the maximum instantaneous power during an interval of interest (in our case: peak during magnets ramp-up) Installed power [P inst ]: the sum of the rated power of the supplied electrical equipment (example on CV) Power profile: is the time evolution of the power acquired through the fastest achievable sampling rate

LHC - Electrical network topology To Meyrin MEH59 To Meyrin ME9 Machine network Radial supply from 66 kV network 66 kV distribution to points LHC 1, 2, 4, 6 and 8 Point LHC 5 feed from point LHC 6 at 18 kV level Tunnel loop (also known as LHC General Services loop) 18 kV network installed in the tunnel and coming to surface on all 8 LHC points Feed from point 1 Operated in closed loop mode Included in the autotransfer system Admissible apparent power 30 MVA

LHC - Systems classification Classification given according to rules defined for EN-EL web energy application Systems Cooling: pumping station, cooling towers, air conditioning, etc,.. Ventilation: tunnel ventilation, chillers, air conditioning, etc… Cryogenics: Compressors and cooling stations Magnets and converters: Power converters supplying warm and superconducting magnets Radio Frequency: cavities in point 4, … Experiences: CMS, ATLAS, ALICE, LHCb General services: Loads not included in the other systems as : F1, F2, F3, F V sockets distribution, UPS systems, 48 V systems, fire and ODH detection, elevators, cranes, ….. Loads to be covered by auto transfer in case of internal of external power outage

Daily average 7 TeV and 13 TeV P AVG-14-days-june(2012) = 60.8 MW P AVG-14-days-june(2015) = 67.8 MW  = + 7 MW (+12%) Note: 21 MW for the LHC experiences are not included

Daily average 7 TeV and 13 TeV Notes: 1 Probable additional load on the LHC loop by EL operation (TBC) 2 Probable additional power request in SM18 (TBC) Analysis: Major contribution to daily power variation is done by magnets and power converters. Probably directly related to the number of ramp-up and ramp down of magnets and the number of hours of operation of the warm magnets Average daily power consumption during TS is between 48 and 52 MW RF + magnets and converters OFF Cryo decrease of consumption All other systems remains constant TS 1 2

Power consumption variation between 7 TeV and 13 TeV Comparison done on the first 14 days of June (2015 minus 2012) Comparison of the systems daily average power consumption variation: +15 to +20 % for the cryogenics +25 to +60 % for magnets and power converters +10 to +12 % for cooling -20 to +15 % for ventilation -15 to +5 % for radio frequency -10 to +30 % for general services

Comparison between average 7 TeV, 13 TeV and LHC design values Estimates / Survey Measurements System LHC design report (table 7.1) [MW] EN-EL survey March 2011 (EDMS ) [MW] LHC design 14 TeV (FCC meeting,24 November 2014) [MW] Nov TeV (FCC meeting, 24 November 2014) [MW] June TeV [MW] June TeV [MW] Duration of measurement Not applicable One month14 days Data acquisition Not applicable 10 min average power Stored only if +/- 10% variation compared to last point acquired 1min sampling rate 100 kW power variation 1min sampling rate 100 kW power variation Magnets and power converters Cryogenics Cooling 23.7 (32.8 winter) Ventilation Radio Frequency General Services13.6 Included in other systems Experiments Other machine1.92Not identified Total [MW] Copy of data presented on 24 th of November 2014

1 1 1 Power variations to be further investigated. Could be real or due to data processing mistakes Active power profile during LHC 13 TeV The period considered goes from the 13 June (16h30) to 14 June (17h16) P AVG 68 MW (dotted line) P peak = 83 MW P steady 450 GeV = 63 MW P steady 6.5 TeV = 70 MW

Active power profile during a Ramp-down and a Ramp-up Ramp-down and Ramp-up snapshot P AVG = 68 MW (dotted line) P peak = 82 MW P steady 450 GeV = 63 MW P steady 6.5 TeV = 70 MW Physics Dump Ramp injection injection Ramp up Tune squeeze adjust Physics Beam energy ramp up. Power increase mainly due to power converters 2 Power start to decrease before start of ramp-down. 3 Transitory period during ramp-down.

Summary of steady state and peak active powers DescriptionName June TeV [MW] June TeV [MW] Steady state at 450 GeV (injection)P steady 450 GeV Data not retrievable63 Steady state at 13 TeVP steady 6.5 TeV Data not retrievable70 Steady state during TSP steady TS 4950 Peak active power during a LHC runP peak Data not retrievable81 21 MW for the experiences are not counted and shall be added whenever applicable (i.e. not during TS) Deviation on measured data will be determined by additional measurements Steady state and peak consumptions under nominal LHC operational conditions are the key values for electrical network dimensioning, redoundancy layouts and optimization of network operation (i.e. systems outage in case of reduced power availability)

Conclusion DAQ system for LHC power consumption is now operational and tuned to acquire the maximum data points achievable Data for daily average consumption are sufficient to estimate LHC energy consumption and costs Dimensioning of the FCC network infrastructure require to study more in detail the steady states and peak power consumptions of LHC Definition of individual systems installed power vs. systems operational processes are necessary to define simultaneity factors and power profiles

Thank you for your attention

Annexes

Example: Cooling and ventilation Comparison of power 7 TeV, 13 TeV and announced values System Nov TeV June TeV June TeV Cooling Ventilation Total [MW] Cooling and ventilation power needs are stable during LHC 13 TeV Announced values diverge from measured values Need to use a common terminology (average, peak, steady state, etc…)

Power consumption for LHC cooling and ventilation (MW) G. PeonFCC I&O meeting Installed Power Sum of equipment rated power Cooling23 Ventilation 52 Total 75 Required power Accounting for back up Cooling18 Ventilation 39 Total 57 Average peak consumption over the year Cooling10 Ventilation 20 Total 30 Peak consumption (I) Running LHC in winter conditions Cooling12 Ventilation 26 Total 38 Peak consumption (II) LHC stopped in winter conditions Cooling 9 Ventilation 25 Total 34 Peak consumption (III) Running LHC in summer conditions Cooling13 Ventilation 18 Total 31

Systems - Installed active power SystemInstalled active power [MW]Notes Magnets and power converters39.4Max taken from LHC design report Cryogenics48.4Max taken from LHC design report Cooling23Provided by system owner Ventilation52Provided by system owner Radio Frequency17.9Max taken from LHC design report General Services13.6Max taken from LHC design report Experiments21.8Max taken from LHC design report Other machine1.92Max taken from LHC design report Total [MW]218.0 Network - Available active power SystemInstalled active power [MW]Notes LHC x 66 kV transformer rating – Meyrin load (20 MW) LHC x 66 kV transformer rating LHC x 66 kV transformer rating LHC x 66 kV transformer rating LHC x 66 kV transformer rating LHC loop21.8Limited by loop ampacity Total [MW]209.8

Impact of TI2 and TI8 on LHC active power profile (1)

Impact of TI2 and TI8 on LHC active power profile (2)