The Building 180 Cryogenic infrastructure water cooling system Status Update Stefano Moccia, EN-CV Coordination meeting 14/10/15.

Slides:



Advertisements
Similar presentations
CEA DSM Irfu - Bernard GASTINEAU - R3B Technical Board Meeting -April 4, Reactions with Relativistic Radioactive ions Beams GSI Large Acceptance.
Advertisements

Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
GLAST LAT ProjectSubsystem Managers Meeting May 12, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager.
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
Current status Arkadiy Klebaner November 21, 2012
Construction and Installation of the CLIC Experimental Area
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
LBT Q Engineering Review DYB. 26-Oct-2007LBT Q Engineering Review Highlights (Q3/2007) Currently in Commissioning Phase Currently in Commissioning.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
1 Jim Thomas - LBL 4.2 Meters ~ 1 Meter The SSD: March Face to Face Meeting Jim Thomas Lawrence Berkeley Laboratory March 14 th, 2012 The SSD.
1 BROOKHAVEN SCIENCE ASSOCIATES Transition to Installation Erik Johnson ASD Deputy Director and Interface Manager NSLS-II CFAC Meeting November 9-10, 2009.
PSB MPS Building 245 CV Status EN-CV-PJMichel OBRECHT – Frédéric TEIXEIRA
IMPACTS OF INSTALLING THE REFERENCE MAGNET PLACEMENT IN B december 2014 Fulvio Boattini & Natacha Lopez Hernandez.
ISOLDE: Status report building th ISCC meeting CERN, 31 March 2014 Erwin Siesling, Magda Kowalska.
Cooling Loads. Critical System P&ID Critical system Main issues Oversized chillers Issues with switch over By-pass valve AHU5A/B? Looking at the T and.
Bulding 245 schedule update LIU Booster Meeting Fulvio Boattini & Michel Obrecht TE-EPC / EN-CV TEEPC.
ISOLDE: Status report building th ISCC meeting CERN, 22 October 2013 Maria Borge, Erwin Siesling.
19 th November 2010EN/CV/DC Thermosiphon project IV review - Overall cost estimation and planning Michele Battistin Elena Perez Rodriguez 19 th November.
1M. Ellis - MICE VC - 1st November 2007 Cosmic Ray Test Preparations  The cosmic ray test was initially planned to be held in R12, but this proved to.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62)
JCOV 24 NOVEMBER 2005 J.Godlewski EP-ATI 1 JCOV NOVEMBER 2005 ATLAS cooling systems installation plans Jan Godlewski CERN EP-ATI The H.Niewodniczanski.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Chiller control system Specification meeting Lukasz Zwalinski – PH/DT.
Update on Module Mounting on Staves and Stavelets 25/8/11 1.
ILD requirement for assembly space and time 2015/11/3 Yasuhiro 1.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
The Building 180 Cryogenic infrastructure water cooling system Stefano Moccia, EN-CV Coordination meeting 26/09/14.
Goddard Space Flight Center Cryogenics and Fluids Branch Status of the AMS-02 Cryocooler January 2007 TIM.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
CMS consolidation activities of detector cooling system Detector cooling project P. Tropea.
IBL CO 2 cooling planning 03 July 2013 Jan Godlewski, Bart Verlaat, Lukasz Zwalinski 1
1 Status of PT Cryocooler for Final Calorimeter KEK, ICEPP Tom HARUYAMA / Satoshi MIHARA MEG Pre-Meeting 1. Heat load and PT cryoooler 2.
NA62 CV activities Piero Valente 5 th September
Status of the ATLAS ID Evaporative cooling system JCOV 25 Nov P. Bonneau TS/CV/Detector Cooling CONTENTS Overall statusOverall status Cooling plant.
1 S-FRS Magnet Test Bench SuperFRS Magnet Test Bench Power Converter Status H. Thiesen 13 May 2015.
1 BROOKHAVEN SCIENCE ASSOCIATES CF Coordination with Technical Divisions Ove Dyling Conventional Facilities Advisory Committee Review October 5-6, 2010.
Gas system for NA62 Straw detector Roberto Guida On behalf of Gas Service Team NA62 Straw working meeting, March 26, 2012 Outline: P&I Drawing Schedule.
Thermosiphon Project for ATLAS ID C 3 F 8 Evaporative Cooling - Status Report ATLAS ID Week CERN – Geneva October 28 th, 2013 M. Battistin & all TS team.
CMTF Infrastructure Jerry Leibfritz PIP-II Machine Advisory Committee 9-11 March 2015.
1 BNL LHC Hi-Lumi QXF Vertical Test Facility Status Update M. Anerella, H. Hocker, P. Joshi, P. Kovach, A. Marone March 28, 2016.
H. Weick, 8 th MAC meeting, GSI, Super-FRS Status Target Area H. Weick / M. Winkler 8th FAIR - Machine Advisory Committee Meeting
110 th November 2010EN/CV/DC Detector Cooling Project - advancement status of Work Package N3 Thermosiphon project Michele Battistin 18 May 2011.
GIF in EHN1 - Vision 112/02/2014A. Fabich, EN-MEF-LE.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
R2E relocation & shielding activities: status report Anne Laure Perrot EN/MEF- LE On behalf of the R2E coordination team LS1 Committee – meeting #48, 27.
Programme for the Physics Start-up Stable and radioactive beams Jose Alberto Rodriguez, BE-OP-PSB (167538)
S A Griffiths CM42 June 2015 Electrical & Control.
WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011.
Cryoplant Controls Installation
TE-EPC internal review of the ELENA project
Status, Schedule and EVM for the test facility project
CBETA Technical Review
Francois and Lau EATM 17 July 2012
SPS cryogenic proximity equipment and SM18 validation
Coordination meeting 12/05/15
David Montanari / Johan Bremer Jun 11, 2015 Rev. 1
ATF2 Magnet Power Supplies
Teleconference ACS – FREIA 17th October 2017
Teleconference ACS – FREIA 31st October 2017
Scope, Requirements Deliverables & Schedule
Operator Training Requirements
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Presentation transcript:

The Building 180 Cryogenic infrastructure water cooling system Status Update Stefano Moccia, EN-CV Coordination meeting 14/10/15

Fabrication Status Summary The skids construction is well underway. The cooling tower has been manufactured Schedule Delivery of the two skids and the cooling tower: Mid November 2015 Interconnecting piping and electrical installation: before Xmas 2015 Commissioning: January-February 2016 Overall Heat load test: July 2016

Interfaces Status EN-EL: Next week meet about power connection cabling to skids’ power cubicles (temporary and/or final) EN-ICE: Functional analysis delivered to ICE for coding. Control software ready by mid November. GS-SE-CEB: Concrete slab outside Build. 279 almost ready. Concrete slab and “carottage” outside Build. 180 ready at the end of November. TE-CRG-ML/ME: Compressors layout in Build. 279 seems well advanced. Meet within the next two weeks to define piping integration. TE-EPC-MPC: reduced cooling requirements. Cooling power from 160 kW to 34 kW Demi water flow from 15 m ³ /h to 5 m ³ /h. Demi water skid bigger than needed. Too late to modify/optimize for the present needs. Integration in Build. 180 still ongoing.